864 S VERMONT AVE 90005

Certificate Information: 864 S VERMONT AVE 90005

Application / Permit
15010-10000-00909
Plan Check / Job No.
B15LA03261
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
4 story type II B building with retail and parking
Permit Issued
Issued on 8/19/2016
Issuing Office
Metro
Current Status
CofO Issued on 5/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2015 APPLICANT
Assigned to Plan Check Engineer 4/16/2015 LARRY LEE
Corrections Issued 4/28/2015 LARRY LEE
Quality Review Completed 5/4/2015 BILL STUTSMAN
Building Plans Picked Up 5/5/2015 APPLICANT
Applicant returned to address corrections 6/1/2015 LARRY LEE
Applicant returned to address corrections 12/22/2015 LARRY LEE
Applicant returned to address corrections 1/15/2016 LARRY LEE
Applicant returned to address corrections 3/3/2016 LARRY LEE
Plan Check Approved 4/19/2016 LARRY LEE
Issued 8/19/2016 LADBS
TCO Issued (Expire Date: 10-20-2020) 4/23/2020 DAVID TSAU
CofO in Progress 5/18/2020 NICK DANERI
CofO Issued 5/20/2020 DAVID TSAU
Permit Finaled 5/20/2020 DAVID TSAU

Permit Application Clearance Information

CPC Cleared 6/9/2015 VINCENT QUITORIANO
HPOZ Cleared 6/9/2015 VINCENT QUITORIANO
ZA Case Cleared 6/9/2015 VINCENT QUITORIANO
ZA Case Cleared 6/9/2015 VINCENT QUITORIANO
Hydrant and Access approval Cleared 10/1/2015 JOHN CONNEALLY
Address approval Cleared 10/2/2015 JAMES MORALEZ
Project located in CRA area Cleared 10/7/2015 JIM URQUHART
Comm Cor/Mini-Mall Cleared 10/29/2015 JUSTIN BILOW
ZA Case Cleared 10/30/2015 JUSTIN BILOW
Prkng lot landscape/Water mgmt Cleared 11/24/2015 LAURA FRAZIN-STEELE
DAS Clearance Cleared 12/11/2015 SHINE LIN
Eng Process Fee Ord 176,300 Cleared 12/17/2015 RAVIL MANAPOV
Highway dedication Cleared 12/17/2015 RAVIL MANAPOV
Green Code Cleared 2/18/2016 RUSSELL KELLY
Food establishment approval Cleared 3/23/2016 LACDHS APPROVED
Low Impact Development Cleared 3/24/2016 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/24/2016 ADRIAN SANCHEZ
Stormwater Pollution Mitigatn Cleared 3/24/2016 AMMAR ELTAWIL
Food Service Establishment Cleared 3/30/2016 RAMESHBHAIR PATEL
Sewer availability Cleared 4/14/2016 ARNULFO NUNO
Building over 3-story or 36-ft Cleared 4/22/2016 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/22/2016 CALOSHA APPROVED

Contact Information

Architect Pak, Christopher C; Lic. No.: C25621 8157 ZITOLA TERRACE      PLAYA DEL REY, CA 90293
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/29/2016 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 3/29/2017 Partial Inspection SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 3/30/2017 Not Ready for Inspection LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 3/31/2017 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 3/31/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/3/2017 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 4/3/2017 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/4/2017 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/19/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/24/2017 Conditional Approval ERNESTO CORRAL
Special/Order Compliance 4/24/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 5/2/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 5/2/2017 Partial Inspection ERNESTO CORRAL
Deputy Shotcrete 5/4/2017 Conditional Approval NICK DANERI
Deputy Shotcrete 5/5/2017 Conditional Approval NICK DANERI
Green Building Rough 5/9/2017 Not Ready for Inspection RICHARD DOCKUS
Reinforced Concrete Frame 5/9/2017 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 5/9/2017 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 5/11/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 6/2/2017 Partial Approval NICK DANERI
Structural Steel Frame 6/2/2017 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/2/2017 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/5/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 6/5/2017 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/9/2017 Partial Approval NICK DANERI
Footing/Foundation/Slab 6/12/2017 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/14/2017 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 6/29/2017 Conditional Approval NICK DANERI
Masonry Wall/Backfill 6/30/2017 Partial Approval NICK DANERI
Deputy Steel/Welding 7/12/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 7/12/2017 Partial Approval NICK DANERI
Deputy Reinf. Concrete 7/14/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 7/20/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/26/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/7/2017 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/9/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/30/2017 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/31/2017 Conditional Approval NICK DANERI
Green Building Rough 9/1/2017 Not Ready for Inspection RICHARD DOCKUS
Reinforced Concrete Frame 9/1/2017 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/1/2017 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 9/8/2017 Partial Approval NICK DANERI
Deputy Steel/Welding 9/29/2017 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/4/2017 Partial Approval NICK DANERI
Special/Order Compliance 10/30/2017 Partial Inspection NICK DANERI
Deputy Grading 11/7/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/8/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/9/2017 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/9/2017 Partial Approval NICK DANERI
Deputy Steel/Welding 11/13/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/14/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/15/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/16/2017 Conditional Approval NICK DANERI
Green Building Rough 11/16/2017 Partial Inspection NICK DANERI
Reinforced Concrete Frame 11/16/2017 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/16/2017 Partial Inspection NICK DANERI
Deputy Steel/Welding 11/17/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/21/2017 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/21/2017 Partial Approval NICK DANERI
Deputy Steel/Welding 11/22/2017 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 11/27/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/28/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/29/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/30/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/1/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/4/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/5/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/6/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/8/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/14/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/15/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/18/2017 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/18/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/19/2017 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/20/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/21/2017 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/22/2017 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/16/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/20/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/22/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/23/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/26/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/27/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/28/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/1/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/5/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/6/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/7/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/8/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/9/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/12/2018 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/13/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/14/2018 Conditional Approval NICK DANERI
Green Building Rough 3/14/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 3/14/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/14/2018 Not Ready for Inspection NICK DANERI
Deputy Steel/Welding 3/15/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/16/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/19/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/20/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/21/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/22/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/23/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/27/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/28/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/29/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/30/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/30/2018 Conditional Approval NICK DANERI
Green Building Rough 3/30/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 3/30/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/30/2018 Partial Inspection NICK DANERI
Deputy Steel/Welding 4/2/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/3/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/4/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/6/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/6/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/9/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/9/2018 Conditional Approval NICK DANERI
Green Building Rough 4/9/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 4/9/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/9/2018 Not Ready for Inspection NICK DANERI
Deputy Steel/Welding 4/10/2018 Conditional Approval NICK DANERI
Reinforced Concrete Frame 4/10/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/11/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/12/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/16/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/17/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/18/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/19/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/20/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/24/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/25/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/26/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/27/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/30/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 5/1/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/2/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/3/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/4/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/7/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/8/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/9/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/10/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/11/2018 Conditional Approval NICK DANERI
Special/Order Compliance 5/11/2018 Partial Inspection NICK DANERI
Deputy Steel/Welding 5/14/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/15/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/17/2018 Conditional Approval NICK DANERI
Reinforced Concrete Frame 5/24/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/4/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/6/2018 Conditional Approval NICK DANERI
Green Building Rough 6/6/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 6/6/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/6/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/7/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/8/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/11/2018 Conditional Approval NICK DANERI
Green Building Rough 6/12/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/12/2018 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 6/12/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/13/2018 Conditional Approval NICK DANERI
Reinforced Masonry Frame 6/13/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 6/15/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/18/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/20/2018 Conditional Approval NICK DANERI
Green Building Rough 6/20/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/20/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/20/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/21/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/22/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 6/25/2018 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 6/25/2018 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 6/25/2018 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 6/26/2018 Conditional Approval LARRY ARNICK
Pre-Inspection 6/26/2018 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 6/27/2018 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/27/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/29/2018 Conditional Approval NICK DANERI
Green Building Rough 6/29/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/29/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/29/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/6/2018 Conditional Approval NICK DANERI
Green Building Rough 7/6/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/6/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/6/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/9/2018 Conditional Approval NICK DANERI
Reinforced Masonry Frame 7/9/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/16/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/18/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/20/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/25/2018 Conditional Approval NICK DANERI
Green Building Rough 7/25/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/25/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 7/25/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 7/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/27/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 7/27/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 7/30/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/1/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/2/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/2/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/3/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/6/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/7/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/8/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/10/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/13/2018 Conditional Approval NICK DANERI
Green Building Rough 8/13/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 8/13/2018 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 8/13/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/13/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 8/14/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/14/2018 Not Ready for Inspection NICK DANERI
Masonry Wall/Backfill 8/14/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/15/2018 Conditional Approval NICK DANERI
Wall Anchors 8/15/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/16/2018 Conditional Approval NICK DANERI
Green Building Rough 8/16/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/16/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/16/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 8/17/2018 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/20/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/21/2018 Conditional Approval NICK DANERI
Green Building Rough 8/21/2018 Partial Inspection NICK DANERI
Pre-Inspection 8/21/2018 Partial Approval NICK DANERI
Reinforced Masonry Frame 8/21/2018 Partial Approval NICK DANERI
Structural Steel Frame 8/21/2018 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 8/21/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/22/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/23/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/30/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/30/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 8/31/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/5/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/5/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/6/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/7/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 9/14/2018 Conditional Approval NICK DANERI
Green Building Rough 9/14/2018 Partial Inspection NICK DANERI
Reinforced Masonry Frame 9/14/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/14/2018 Partial Inspection NICK DANERI
Deputy Steel/Welding 9/20/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 9/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 9/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/25/2018 Conditional Approval NICK DANERI
Green Building Rough 9/25/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 9/25/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/25/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 9/26/2018 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 10/4/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/4/2018 Partial Approval NICK DANERI
Green Building Rough 10/4/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 10/4/2018 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 10/4/2018 Partial Inspection NICK DANERI
Deputy Reinf. Masonry 10/5/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 10/9/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/10/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/11/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/12/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/15/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 10/16/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/16/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 10/17/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 10/22/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/24/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 10/24/2018 Partial Approval NICK DANERI
Deputy Steel/Welding 10/26/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/29/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/30/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 10/31/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/1/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/2/2018 Conditional Approval NICK DANERI
Green Building Rough 11/2/2018 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 11/2/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/2/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 11/5/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/6/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/7/2018 Conditional Approval NICK DANERI
Reinforced Masonry Frame 11/7/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/8/2018 Conditional Approval NICK DANERI
Green Building Rough 11/8/2018 Partial Inspection NICK DANERI
Reinforced Concrete Frame 11/8/2018 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 11/8/2018 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 11/9/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/15/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/16/2018 Conditional Approval NICK DANERI
Pre-Inspection 11/16/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/26/2018 Conditional Approval NICK DANERI
Footing/Foundation/Slab 11/26/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/27/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/28/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/28/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/29/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/29/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/30/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 11/30/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/3/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/4/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/5/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/6/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/7/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/11/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/12/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/13/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/14/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/17/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/19/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/21/2018 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 12/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/26/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/26/2018 Conditional Approval NICK DANERI
Deputy Steel/Welding 12/27/2018 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/27/2018 Partial Approval NICK DANERI
Green Building Rough 12/27/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 12/27/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/27/2018 Not Ready for Inspection NICK DANERI
Deputy Steel/Welding 12/28/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 1/3/2019 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 1/3/2019 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 1/3/2019 Partial Approval WINSTON DUNNING
Deputy Reinf. Concrete 1/4/2019 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 1/4/2019 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 1/7/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 1/8/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 1/9/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 1/10/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/11/2019 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 1/15/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 1/18/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 1/22/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 1/23/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 1/23/2019 Partial Approval NICK DANERI
Deputy Fireproofing 1/24/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 1/25/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 1/28/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 1/29/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/30/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 2/1/2019 Not Ready for Inspection NICK DANERI
Deputy Steel/Welding 2/4/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/5/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/6/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/7/2019 Conditional Approval NICK DANERI
Green Building Rough 2/7/2019 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/7/2019 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 2/7/2019 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 2/8/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/8/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/12/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/14/2019 Conditional Approval NICK DANERI
Green Building Rough 2/14/2019 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/14/2019 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 2/14/2019 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 2/15/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 2/15/2019 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/21/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/22/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/26/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/27/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 2/27/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/28/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/1/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/1/2019 Partial Approval NICK DANERI
Deputy Fireproofing 3/4/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 3/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 3/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 3/12/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 3/13/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 3/14/2019 Conditional Approval NICK DANERI
Deputy Fireproofing 3/15/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/20/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/21/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/22/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/22/2019 Conditional Approval NICK DANERI
Piling/Pier/Caisson 3/22/2019 Partial Approval NICK DANERI
Deputy Steel/Welding 3/26/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/27/2019 Conditional Approval NICK DANERI
Pre-Inspection 3/27/2019 Partial Inspection NICK DANERI
Deputy Fireproofing 3/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/1/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/1/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/2/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/3/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/5/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/8/2019 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/9/2019 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/9/2019 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/10/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/11/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/12/2019 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/12/2019 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 4/15/2019 Conditional Approval NICK DANERI
Deputy Shotcrete 4/15/2019 Conditional Approval NICK DANERI
Footing/Foundation/Slab 4/15/2019 Partial Approval NICK DANERI
Deputy Steel/Welding 4/16/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/17/2019 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/18/2019 Conditional Approval NICK DANERI
Green Building Rough 4/18/2019 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 4/18/2019 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/18/2019 Not Ready for Inspection NICK DANERI
Deputy Steel/Welding 4/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 4/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 4/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 4/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 4/25/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/25/2019 Partial Approval LESLIE TRUJILLO
Deputy Fireproofing 4/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/29/2019 Conditional Approval DANIEL COLLINS
Deputy Fireproofing 4/30/2019 Partial Approval JAMES POWERS
Deputy Fireproofing 5/1/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/3/2019 Partial Approval JAMES POWERS
Deputy Fireproofing 5/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/7/2019 Conditional Approval LESLIE TRUJILLO
Masonry Wall/Backfill 5/9/2019 Partial Approval LESLIE TRUJILLO
Deputy Fireproofing 5/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/21/2019 Conditional Approval ERNESTO CORRAL
Deputy Fireproofing 5/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/28/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 5/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Fireproofing 6/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 6/4/2019 Conditional Approval LESLIE TRUJILLO
Pre-Inspection 6/4/2019 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 6/5/2019 Conditional Approval LESLIE TRUJILLO
Interior/Exterior Lathing 6/20/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 6/24/2019 Corrections Issued LESLIE TRUJILLO
Footing/Foundation/Slab 7/1/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 7/11/2019 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 7/18/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 8/9/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 8/22/2019 Partial Approval LESLIE TRUJILLO
Drywall Nailing 9/18/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 9/18/2019 Partial Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 9/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 9/24/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/25/2019 Partial Approval LESLIE TRUJILLO
Drywall Nailing 10/16/2019 Partial Approval DANIEL MC AULIFFE
Green Building Rough 10/16/2019 Partial Approval DANIEL MC AULIFFE
Green Building Rough 12/11/2019 Partial Inspection LESLIE TRUJILLO
Interior/Exterior Lathing 12/11/2019 Partial Inspection LESLIE TRUJILLO
T-Bar Ceiling 1/21/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 2/7/2020 Approved LESLIE TRUJILLO
Final 2/7/2020 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 2/7/2020 Approved LESLIE TRUJILLO
Green Building Final 2/7/2020 Not Ready for Inspection LESLIE TRUJILLO
Green Building Rough 2/7/2020 Approved LESLIE TRUJILLO
Reinforced Concrete Frame 2/7/2020 Approved LESLIE TRUJILLO
Reinforced Masonry Frame 2/7/2020 Approved LESLIE TRUJILLO
SGSOV-Seismic Gas S/O Valve 2/7/2020 SGSOV Not Ready LESLIE TRUJILLO
Smoke Detectors 2/7/2020 Not Ready for Inspection LESLIE TRUJILLO
Structural Steel Frame 2/7/2020 Approved LESLIE TRUJILLO
Verify Sprinkler Sign Off 2/7/2020 Approved LESLIE TRUJILLO
T-Bar Ceiling 2/18/2020 Corrections Issued LESLIE TRUJILLO
Wall Anchors 3/16/2020 Partial Inspection LESLIE TRUJILLO
Final 4/6/2020 Not Ready for Inspection LESLIE TRUJILLO
Green Building Final 4/6/2020 Approved LESLIE TRUJILLO
SGSOV-Seismic Gas S/O Valve 4/6/2020 SGSOV Approved LESLIE TRUJILLO
Smoke Detectors 4/6/2020 Approved LESLIE TRUJILLO
Pre-Inspection 4/7/2020 Partial Approval LESLIE TRUJILLO
Final 4/15/2020 OK for TCO LESLIE TRUJILLO
Final 4/20/2020 Partial Inspection LESLIE TRUJILLO
Final 4/23/2020 Partial Approval LESLIE TRUJILLO
Final 5/7/2020 Not Ready for Inspection NICK DANERI
Final 5/12/2020 Partial Approval NICK DANERI
Final 5/15/2020 OK to Issue CofO NICK DANERI