Footing/Foundation/Slab
|
5/9/2016
|
Partial Approval
|
DANIEL ORRANTE
|
|
Deputy Reinf. Concrete
|
5/11/2016
|
Approved
|
DANIEL ORRANTE
|
|
Footing/Foundation/Slab
|
6/14/2016
|
Partial Approval
|
JOHN LUMB
|
|
Underground Mechanical
|
6/15/2016
|
Partial Approval
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
7/11/2016
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
7/13/2016
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2016
|
Partial Approval
|
JOHN LUMB
|
|
Masonry Wall/Backfill
|
7/26/2016
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Shotcrete
|
7/28/2016
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Shotcrete
|
8/2/2016
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Deputy Reinf. Concrete
|
8/18/2016
|
Approved
|
CHRISTOPHER WILSON
|
|
Sewer
|
8/30/2016
|
Approved
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
8/30/2016
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/1/2016
|
Approved
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2016
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Masonry
|
9/23/2016
|
Approved
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/6/2016
|
Partial Approval
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
10/6/2016
|
Partial Approval
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2016
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
10/19/2016
|
Approved
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
11/7/2016
|
Approved
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
11/9/2016
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
11/10/2016
|
Partial Approval
|
JOHN LUMB
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/30/2016
|
Not Ready for Inspection
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
12/19/2016
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
12/21/2016
|
Approved
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
12/21/2016
|
Partial Approval
|
JOHN LUMB
|
|
Footing/Foundation/Slab
|
3/7/2017
|
Partial Approval
|
JOHN LUMB
|
|
Pool Piping
|
3/7/2017
|
Not Ready for Inspection
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
5/8/2017
|
Not Ready for Inspection
|
JOHN LUMB
|
|
Excavation/Setback/Form/Re-Bar
|
7/11/2017
|
Partial Approval
|
JOHN LUMB
|
|
Deputy Reinf. Concrete
|
7/13/2017
|
Partial Approval
|
JOHN LUMB
|
|
Pre-Inspection
|
8/4/2017
|
Corrections Issued
|
VINCENT SCIPIONI
|
|
Special/Order Compliance
|
9/11/2017
|
Partial Inspection
|
VINCENT SCIPIONI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/21/2017
|
Corrections Issued
|
DANIEL ORRANTE
|
|
Masonry Wall/Backfill
|
10/4/2017
|
Partial Approval
|
VINCENT SCIPIONI
|
|
Pre-Inspection
|
10/18/2017
|
Partial Inspection
|
VINCENT SCIPIONI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/15/2017
|
Partial Inspection
|
VINCENT SCIPIONI
|
|
Special/Order Compliance
|
1/4/2018
|
No Access for Inspection
|
DANIEL ORRANTE
|
|
Pre-Inspection
|
1/31/2018
|
Partial Inspection
|
VINCENT SCIPIONI
|
|
Special/Order Compliance
|
1/31/2018
|
Conditional Approval
|
DANIEL ORRANTE
|
|
PLUMBING-Rough
|
2/27/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Gas Test
|
3/1/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
PLUMBING-Rough
|
3/1/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
HVAC-Rough
|
3/6/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
HVAC-Rough
|
3/15/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Insulation
|
3/15/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
ELECTRICAL-Rough
|
3/19/2018
|
Corrections Issued
|
JOHN LUMB
|
|
ELECTRICAL-Rough
|
3/20/2018
|
Partial Approval
|
JOHN LUMB
|
|
Insulation
|
3/20/2018
|
Partial Approval
|
JOHN LUMB
|
|
Masonry Wall/Backfill
|
3/20/2018
|
Not Ready for Inspection
|
JOHN LUMB
|
|
HVAC-Rough
|
4/9/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Special/Order Compliance
|
4/17/2018
|
Corrections Issued
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
4/19/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/19/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Green Building Rough
|
4/19/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Verify Sprinkler Sign Off
|
4/19/2018
|
Approved
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
4/23/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
4/23/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Special/Order Compliance
|
4/23/2018
|
Not Ready for Inspection
|
DANIEL ORRANTE
|
|
Excavation/Setback/Form/Re-Bar
|
4/25/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
Pre-Inspection
|
4/25/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Excavation/Setback/Form/Re-Bar
|
5/2/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Pre-Inspection
|
5/2/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Special/Order Compliance
|
5/7/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
5/8/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
5/8/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Interior/Exterior Lathing
|
5/8/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/9/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
5/15/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/15/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
5/15/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/17/2018
|
Not Ready for Inspection
|
VINCENT SCIPIONI
|
|
BUILDING-Rough-Frame
|
5/23/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/23/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
5/23/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Special/Order Compliance
|
6/5/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
6/7/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/7/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Green Building Rough
|
6/7/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
ELECTRICAL-Rough
|
6/11/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/11/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
HVAC-Rough
|
6/11/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
PLUMBING-Rough
|
6/11/2018
|
Partial Inspection
|
KENNETH NAGLE
|
|
HVAC-Rough
|
6/25/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
PLUMBING-Rough
|
6/25/2018
|
No Access for Inspection
|
KENNETH NAGLE
|
|
ELECTRICAL-Rough
|
6/29/2018
|
Corrections Issued
|
KENNETH NAGLE
|
|
HVAC-Rough
|
6/29/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
PLUMBING-Rough
|
6/29/2018
|
Corrections Issued
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
7/3/2018
|
Partial Approval
|
KENNETH NAGLE
|
|
Green Building Rough
|
7/3/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
HVAC-Rough
|
7/3/2018
|
Approved
|
KENNETH NAGLE
|
|
PLUMBING-Rough
|
7/3/2018
|
Approved
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
7/26/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
7/26/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Insulation
|
7/26/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
7/31/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
7/31/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
8/1/2018
|
Corrections Issued
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
8/2/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Green Building Rough
|
8/2/2018
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
BUILDING-Rough-Frame
|
8/6/2018
|
Approved
|
KENNETH NAGLE
|
|
Green Building Rough
|
8/6/2018
|
Approved
|
KENNETH NAGLE
|
|
Verify Sprinkler Sign Off
|
8/6/2018
|
Approved
|
KENNETH NAGLE
|
|
Drywall Nailing
|
8/8/2018
|
Approved
|
KENNETH NAGLE
|
|
Green Building Rough
|
8/8/2018
|
Approved
|
KENNETH NAGLE
|
|
Interior/Exterior Lathing
|
9/18/2018
|
Partial Approval
|
RICHARD STEINBACH
|
|
Shower Pan
|
9/18/2018
|
Approved
|
RICHARD STEINBACH
|
|
Special/Order Compliance
|
3/6/2020
|
Corrections Issued
|
ROBERT SHELLY
|
|
Special/Order Compliance
|
3/6/2020
|
Permit Expired-Status Void
|
ROBERT SHELLY
|
|
Pre-Inspection
|
9/9/2020
|
Corrections Issued
|
TIM CHRISTENSEN
|
|
ELECTRICAL-Final
|
2/3/2021
|
Approved
|
JOHN KIDWELL
|
|
ELECTRICAL-Final
|
2/12/2021
|
Approved
|
ANDREW NAVE
|
|
Gas Test
|
2/12/2021
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Special/Order Compliance
|
2/12/2021
|
Partial Inspection
|
ANDREW NAVE
|
|
Special/Order Compliance
|
3/3/2021
|
Partial Inspection
|
DAVID HEINE
|
|
Gas Test
|
3/17/2021
|
Approved
|
ANDREW NAVE
|
|
HVAC-Final
|
3/23/2021
|
Corrections Issued
|
JUAN VALENZUELA
|
|
PLUMBING-Final
|
3/23/2021
|
Approved
|
JUAN VALENZUELA
|
|
Final
|
6/2/2021
|
Corrections Issued
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
6/2/2021
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Green Building Final
|
6/2/2021
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Reinforced Concrete Frame
|
6/2/2021
|
Partial Inspection
|
JUAN VALENZUELA
|
|
SGSOV-Seismic Gas S/O Valve
|
6/2/2021
|
SGSOV Not Ready
|
JUAN VALENZUELA
|
|
Service/Power Release
|
6/2/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Smoke Detectors
|
6/2/2021
|
Approved
|
JUAN VALENZUELA
|
|
HVAC-Final
|
6/18/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Final
|
9/24/2021
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
9/24/2021
|
Approved
|
JUAN VALENZUELA
|
|
Green Building Final
|
9/24/2021
|
Approved
|
JUAN VALENZUELA
|
|
Reinforced Concrete Frame
|
9/24/2021
|
Approved
|
JUAN VALENZUELA
|
|
SGSOV-Seismic Gas S/O Valve
|
9/24/2021
|
SGSOV Approved
|
JUAN VALENZUELA
|
|
Service/Power Release
|
9/24/2021
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Final
|
10/1/2021
|
Conditional Approval
|
JUAN VALENZUELA
|
|
HVAC-Final
|
10/1/2021
|
Approved
|
JUAN VALENZUELA
|
|
Service/Power Release
|
10/1/2021
|
Approved
|
JUAN VALENZUELA
|
|
Final
|
10/15/2021
|
OK to Issue CofO
|
DANIEL ORRANTE
|