1638 N CASALE ROAD 90272

Certificate Information: 1638 N CASALE ROAD 90272

Application / Permit
15010-10000-00663
Plan Check / Job No.
B15LA02777
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New two story single-family dwelling over a basement with 3-car attached garage.
Permit Issued
Issued on 11/20/2015
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2015 APPLICANT
Assigned to Plan Check Engineer 3/19/2015 JESSE CARDOZA
Corrections Issued 3/23/2015 JESSE CARDOZA
Green Plans Picked Up 3/24/2015 APPLICANT
Quality Review Completed 3/25/2015 LAWRENCE QUIRANTE
Building Plans Picked Up 3/27/2015 APPLICANT
Applicant returned to address corrections 4/13/2015 JESSE CARDOZA
Applicant returned to address corrections 4/15/2015 JESSE CARDOZA
Applicant returned to address corrections 5/18/2015 KESETE HAREGOT
Applicant returned to address corrections 5/29/2015 KESETE HAREGOT
Applicant returned to address corrections 6/12/2015 KESETE HAREGOT
Plan Check Approved 7/7/2015 KESETE HAREGOT
Plan Check Approved 10/2/2015 KESETE HAREGOT
Issued 11/20/2015 LADBS
Permit Expired-Status Void 3/6/2020 ROBERT SHELLY
Re-Activate Permit 4/6/2020 RONALD MYRICK
CofO in Progress 10/15/2021 DANIEL ORRANTE
CofO in Progress 10/15/2021 DANIEL ORRANTE
CofO Issued 10/19/2021 RONALD MYRICK
Permit Finaled 10/19/2021 RONALD MYRICK

Permit Application Clearance Information

Hold Cleared 2/27/2015 PRECY SANCHEZ
BHO/Hillside ordinance Cleared 3/26/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 3/26/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 3/26/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 3/26/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 3/26/2015 ARMENIA HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/26/2015 ARMENIA HERNANDEZ
Hydrant and Access approval Cleared 3/26/2015 ROBERT DUFF
Low Impact Development Cleared 6/5/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/8/2015 GREGG VANDERGRIFF
Sewer availability Cleared 6/11/2015 ARMENIA HERNANDEZ
Grading Pre-Inspection Cleared 6/12/2015 JESSE CARDOZA
Green Code Cleared 6/12/2015 RICHARD DOCKUS
Miscellaneous Cleared 6/24/2015 JESSE CARDOZA
Excavation more than 5-ft deep Cleared 7/7/2015 CALOSHA APPROVED

Contact Information

Contractor So Cal Custom Construction & Design Inc; Lic. No.: 985849-B 2445 GLYNDON AVENUE      VENICE, CA 90291
Engineer Barr, Joseph Daniel Iii; Lic. No.: C70708 1910 20TH AVE DRIVE NE #109      HICKORY, NC 28601
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245
Geologist Miller, Jonathan Steven; Lic. No.: EG2391 2800 NEILSON WAY #210      SANTA MONICA, CA 90405

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2016 Partial Approval DANIEL ORRANTE
Deputy Reinf. Concrete 5/11/2016 Approved DANIEL ORRANTE
Footing/Foundation/Slab 6/14/2016 Partial Approval JOHN LUMB
Underground Mechanical 6/15/2016 Partial Approval JOHN LUMB
Footing/Foundation/Slab 7/11/2016 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 7/13/2016 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 7/26/2016 Partial Approval JOHN LUMB
Masonry Wall/Backfill 7/26/2016 Partial Approval JOHN LUMB
Deputy Shotcrete 7/28/2016 Partial Approval JOHN LUMB
Deputy Shotcrete 8/2/2016 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 8/18/2016 Approved CHRISTOPHER WILSON
Sewer 8/30/2016 Approved CHRISTOPHER WILSON
Underground Mechanical 8/30/2016 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/1/2016 Approved JOHN LUMB
Excavation/Setback/Form/Re-Bar 9/22/2016 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Masonry 9/23/2016 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/6/2016 Partial Approval JOHN LUMB
Footing/Foundation/Slab 10/6/2016 Partial Approval JOHN LUMB
Excavation/Setback/Form/Re-Bar 10/18/2016 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 10/19/2016 Approved JOHN LUMB
Deputy Reinf. Concrete 11/7/2016 Approved JOHN LUMB
Excavation/Setback/Form/Re-Bar 11/9/2016 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 11/10/2016 Partial Approval JOHN LUMB
Floor/Roof Diaphrgm/Shear Wall 11/30/2016 Not Ready for Inspection JOHN LUMB
Excavation/Setback/Form/Re-Bar 12/19/2016 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 12/21/2016 Approved JOHN LUMB
Footing/Foundation/Slab 12/21/2016 Partial Approval JOHN LUMB
Footing/Foundation/Slab 3/7/2017 Partial Approval JOHN LUMB
Pool Piping 3/7/2017 Not Ready for Inspection JOHN LUMB
Excavation/Setback/Form/Re-Bar 5/8/2017 Not Ready for Inspection JOHN LUMB
Excavation/Setback/Form/Re-Bar 7/11/2017 Partial Approval JOHN LUMB
Deputy Reinf. Concrete 7/13/2017 Partial Approval JOHN LUMB
Pre-Inspection 8/4/2017 Corrections Issued VINCENT SCIPIONI
Special/Order Compliance 9/11/2017 Partial Inspection VINCENT SCIPIONI
Floor/Roof Diaphrgm/Shear Wall 9/21/2017 Corrections Issued DANIEL ORRANTE
Masonry Wall/Backfill 10/4/2017 Partial Approval VINCENT SCIPIONI
Pre-Inspection 10/18/2017 Partial Inspection VINCENT SCIPIONI
Floor/Roof Diaphrgm/Shear Wall 11/15/2017 Partial Inspection VINCENT SCIPIONI
Special/Order Compliance 1/4/2018 No Access for Inspection DANIEL ORRANTE
Pre-Inspection 1/31/2018 Partial Inspection VINCENT SCIPIONI
Special/Order Compliance 1/31/2018 Conditional Approval DANIEL ORRANTE
PLUMBING-Rough 2/27/2018 Not Ready for Inspection KENNETH NAGLE
Gas Test 3/1/2018 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 3/1/2018 Partial Approval KENNETH NAGLE
HVAC-Rough 3/6/2018 No Access for Inspection KENNETH NAGLE
HVAC-Rough 3/15/2018 Not Ready for Inspection KENNETH NAGLE
Insulation 3/15/2018 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 3/19/2018 Corrections Issued JOHN LUMB
ELECTRICAL-Rough 3/20/2018 Partial Approval JOHN LUMB
Insulation 3/20/2018 Partial Approval JOHN LUMB
Masonry Wall/Backfill 3/20/2018 Not Ready for Inspection JOHN LUMB
HVAC-Rough 4/9/2018 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/17/2018 Not Ready for Inspection KENNETH NAGLE
Special/Order Compliance 4/17/2018 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 4/19/2018 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/19/2018 Partial Approval KENNETH NAGLE
Green Building Rough 4/19/2018 Partial Approval KENNETH NAGLE
Verify Sprinkler Sign Off 4/19/2018 Approved KENNETH NAGLE
BUILDING-Rough-Frame 4/23/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 4/23/2018 Not Ready for Inspection KENNETH NAGLE
Special/Order Compliance 4/23/2018 Not Ready for Inspection DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 4/25/2018 Partial Inspection KENNETH NAGLE
Pre-Inspection 4/25/2018 Not Ready for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 5/2/2018 Not Ready for Inspection KENNETH NAGLE
Pre-Inspection 5/2/2018 Not Ready for Inspection KENNETH NAGLE
Special/Order Compliance 5/7/2018 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 5/8/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 5/8/2018 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 5/8/2018 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/9/2018 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 5/15/2018 Not Ready for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/15/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 5/15/2018 Not Ready for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/17/2018 Not Ready for Inspection VINCENT SCIPIONI
BUILDING-Rough-Frame 5/23/2018 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/23/2018 No Access for Inspection KENNETH NAGLE
Green Building Rough 5/23/2018 No Access for Inspection KENNETH NAGLE
Special/Order Compliance 6/5/2018 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 6/7/2018 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/7/2018 Partial Approval KENNETH NAGLE
Green Building Rough 6/7/2018 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 6/11/2018 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/11/2018 Partial Inspection KENNETH NAGLE
HVAC-Rough 6/11/2018 Partial Inspection KENNETH NAGLE
PLUMBING-Rough 6/11/2018 Partial Inspection KENNETH NAGLE
HVAC-Rough 6/25/2018 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 6/25/2018 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 6/29/2018 Corrections Issued KENNETH NAGLE
HVAC-Rough 6/29/2018 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 6/29/2018 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 7/3/2018 Partial Approval KENNETH NAGLE
Green Building Rough 7/3/2018 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 7/3/2018 Approved KENNETH NAGLE
PLUMBING-Rough 7/3/2018 Approved KENNETH NAGLE
BUILDING-Rough-Frame 7/26/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 7/26/2018 Not Ready for Inspection KENNETH NAGLE
Insulation 7/26/2018 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 7/31/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 7/31/2018 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 8/1/2018 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 8/2/2018 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 8/2/2018 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 8/6/2018 Approved KENNETH NAGLE
Green Building Rough 8/6/2018 Approved KENNETH NAGLE
Verify Sprinkler Sign Off 8/6/2018 Approved KENNETH NAGLE
Drywall Nailing 8/8/2018 Approved KENNETH NAGLE
Green Building Rough 8/8/2018 Approved KENNETH NAGLE
Interior/Exterior Lathing 9/18/2018 Partial Approval RICHARD STEINBACH
Shower Pan 9/18/2018 Approved RICHARD STEINBACH
Special/Order Compliance 3/6/2020 Corrections Issued ROBERT SHELLY
Special/Order Compliance 3/6/2020 Permit Expired-Status Void ROBERT SHELLY
Pre-Inspection 9/9/2020 Corrections Issued TIM CHRISTENSEN
ELECTRICAL-Final 2/3/2021 Approved JOHN KIDWELL
ELECTRICAL-Final 2/12/2021 Approved ANDREW NAVE
Gas Test 2/12/2021 Not Ready for Inspection ANDREW NAVE
Special/Order Compliance 2/12/2021 Partial Inspection ANDREW NAVE
Special/Order Compliance 3/3/2021 Partial Inspection DAVID HEINE
Gas Test 3/17/2021 Approved ANDREW NAVE
HVAC-Final 3/23/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 3/23/2021 Approved JUAN VALENZUELA
Final 6/2/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 6/2/2021 Conditional Approval JUAN VALENZUELA
Green Building Final 6/2/2021 Partial Inspection JUAN VALENZUELA
Reinforced Concrete Frame 6/2/2021 Partial Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 6/2/2021 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 6/2/2021 Approved JUAN VALENZUELA
HVAC-Final 6/18/2021 Not Ready for Inspection JUAN VALENZUELA
Final 9/24/2021 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 9/24/2021 Approved JUAN VALENZUELA
Green Building Final 9/24/2021 Approved JUAN VALENZUELA
Reinforced Concrete Frame 9/24/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved JUAN VALENZUELA
Service/Power Release 9/24/2021 Not Ready for Inspection JUAN VALENZUELA
Final 10/1/2021 Conditional Approval JUAN VALENZUELA
HVAC-Final 10/1/2021 Approved JUAN VALENZUELA
Service/Power Release 10/1/2021 Approved JUAN VALENZUELA
Final 10/15/2021 OK to Issue CofO DANIEL ORRANTE