2547 N SUNDOWN DR 90065

Certificate Information: 2547 N SUNDOWN DR 90065

Application / Permit
15010-10000-00177
Plan Check / Job No.
B15LA00536
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SFD W/ATTACHED 2-CAR GARAGE. FULLY SPRINKLERED WITH NFPA-13D.
Permit Issued
Issued on 3/23/2017
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2015 APPLICANT
Assigned to Plan Check Engineer 2/20/2015 VERONICA LOPEZ
Corrections Issued 2/25/2015 VERONICA LOPEZ
Quality Review Completed 3/10/2015 LAWRENCE QUIRANTE
Building Plans Picked Up 3/10/2015 APPLICANT
Green Plans Picked Up 3/11/2015 APPLICANT
Applicant returned to address corrections 6/19/2015 VERONICA LOPEZ
Applicant returned to address corrections 7/2/2015 VERONICA LOPEZ
Applicant returned to address corrections 7/27/2015 VERONICA LOPEZ
Plan Check Approved 3/22/2017 VERONICA LOPEZ
Issued 3/23/2017 LADBS
CofO in Progress 3/28/2024 HAMIK HARTOUNIAN
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 6/12/2015 TERRY PHAN
BHO/Hillside ordinance Cleared 6/17/2015 JAMES MORALEZ
BHO/Hillside ordinance Cleared 6/17/2015 JAMES MORALEZ
BHO/Hillside ordinance Cleared 6/17/2015 JAMES MORALEZ
BHO/Hillside ordinance Cleared 6/17/2015 JAMES MORALEZ
Permit Cleared 6/17/2015 JAMES MORALEZ
GPI Written Notices Cleared 6/19/2015 GEORGE KUC
Grading Pre-Inspection Cleared 6/19/2015 JOHNNY KAZARIAN
Eng Process Fee Ord 176,300 Cleared 7/1/2015 KARAN PATEL
BHO/Hillside ordinance Cleared 7/16/2015 NATALIE MOORE
Roof/Waste drainage to street Cleared 7/31/2015 KARAN PATEL
Disturb/Remove Protected Trees Cleared 12/16/2016 LUIS TORRES
CPC Cleared 1/4/2017 JUSTIN BILOW
Miscellaneous Cleared 1/4/2017 JUSTIN BILOW
Miscellaneous Cleared 3/16/2017 JUSTIN BILOW
Specific Plan Cleared 3/16/2017 JUSTIN BILOW
Green Code Cleared 3/22/2017 SEAN DANG
Hydrant and Access approval Cleared 3/22/2017 ROBERT DUFF
Low Impact Development Cleared 3/22/2017 MARTIN FRAGOSO

Contact Information

Architect Simon, Storey; Lic. No.: C35346 1800 S. BRAND   STE #117    GLENDALE, CA 91204
Contractor Flowers Innovative Design And Construct Inc; Lic. No.: 995868-B 13273 VENTURA BLVD STE 211      STUDIO CITY, CA 91604
Engineer Nastarin, Hooman; Lic. No.: C62199 1436 S LA CIENEGA BLVD 101      LOS ANGELES, CA 90035
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Fishburn, Scott David; Lic. No.: EG2114 1545 VICTORY BLVD.      GLENDALE, CA 91201

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 7/21/2017 Partial Approval LUIS ALVAREZ
Footing/Foundation/Slab 8/16/2017 Partial Approval LUIS ALVAREZ
Footing/Foundation/Slab 8/23/2017 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 9/12/2017 Partial Approval LUIS ALVAREZ
Reinforced Concrete Frame 9/27/2017 Partial Approval LUIS ALVAREZ
Reinforced Concrete Frame 10/31/2017 Partial Approval BRIAN SULLIVAN
Reinforced Concrete Frame 11/8/2017 Partial Approval LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 11/16/2017 Partial Approval LUIS ALVAREZ
Green Building Rough 11/16/2017 Not Ready for Inspection LUIS ALVAREZ
Verify Sprinkler Sign Off 11/16/2017 Not Ready for Inspection LUIS ALVAREZ
Footing/Foundation/Slab 1/10/2018 Approved LUIS ALVAREZ
BUILDING-Rough-Frame 2/12/2018 Not Ready for Inspection LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 2/12/2018 Not Ready for Inspection LUIS ALVAREZ
Green Building Rough 2/12/2018 Not Ready for Inspection LUIS ALVAREZ
Verify Sprinkler Sign Off 2/12/2018 Not Ready for Inspection LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 2/14/2018 Not Ready for Inspection LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2018 Approved LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 6/20/2018 Approved LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 9/11/2018 Not Ready for Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 9/11/2018 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 10/29/2018 Corrections Issued FRANCISCO MORADO
ELECTRICAL-Rough 10/29/2018 Not Ready for Inspection FRANCISCO MORADO
Green Building Rough 10/29/2018 Not Ready for Inspection FRANCISCO MORADO
HVAC-Rough 10/29/2018 Not Ready for Inspection FRANCISCO MORADO
PLUMBING-Rough 10/29/2018 Not Ready for Inspection FRANCISCO MORADO
Verify Sprinkler Sign Off 10/29/2018 Approved FRANCISCO MORADO
ELECTRICAL-Rough 12/3/2018 Partial Approval FRANCISCO MORADO
Floor/Roof Diaphrgm/Shear Wall 12/3/2018 Not Ready for Inspection FRANCISCO MORADO
HVAC-Rough 12/3/2018 Partial Approval FRANCISCO MORADO
PLUMBING-Rough 12/3/2018 Approved FRANCISCO MORADO
ELECTRICAL-Rough 12/18/2018 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Partial Approval SCOTT FINNILA
HVAC-Rough 12/18/2018 Approved SCOTT FINNILA
PLUMBING-Rough 12/18/2018 Approved SCOTT FINNILA
BUILDING-Rough-Frame 5/14/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 5/14/2019 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/14/2019 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/20/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/28/2019 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 5/28/2019 Corrections Issued HAMIK HARTOUNIAN
Insulation 7/1/2019 Approved RUBEN SALAS
Interior/Exterior Lathing 8/8/2019 Partial Approval HAMIK HARTOUNIAN
Shower Pan 8/8/2019 Approved HAMIK HARTOUNIAN
Drywall Nailing 8/19/2019 Approved RUBEN SALAS
HVAC-Final 7/22/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 7/22/2020 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 7/22/2020 Corrections Issued HAMIK HARTOUNIAN
Service/Power Release 7/22/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/31/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/31/2020 Approved HAMIK HARTOUNIAN
Gas Test 8/31/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 8/31/2020 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 10/13/2020 Partial Approval HAMIK HARTOUNIAN
Special/Order Compliance 4/5/2023 Approved HAMIK HARTOUNIAN
Pre-Inspection 8/9/2023 Corrections Issued HAMIK HARTOUNIAN
Final 2/15/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/15/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 2/15/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/15/2024 Approved HAMIK HARTOUNIAN
Structural Steel Frame 2/15/2024 Approved HAMIK HARTOUNIAN
Final 3/26/2024 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 3/26/2024 Approved HAMIK HARTOUNIAN