10905 W CHALON ROAD 90077
Certificate Information: 10905 W CHALON ROAD 90077
- Application / Permit
- 14047-20000-01804
- Plan Check / Job No.
- B14VN15321
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL/SPA INTERGRATED W/NEW HOUSE
- Permit Issued
- Issued on 6/7/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2014 | APPLICANT |
| Green Plans Picked Up | 1/22/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2015 | JESSE JIMENEZ |
| Corrections Issued | 2/10/2015 | JESSE JIMENEZ |
| Quality Review Completed | 2/13/2015 | BINH PHAN |
| Building Plans Picked Up | 2/17/2015 | APPLICANT |
| Applicant returned to address corrections | 3/17/2015 | JESSE JIMENEZ |
| Applicant returned to address corrections | 4/25/2016 | JESSE JIMENEZ |
| Applicant returned to address corrections | 4/27/2016 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/2/2016 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/3/2016 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/10/2016 | JESSE JIMENEZ |
| Plan Check Approved | 6/7/2016 | JESSE JIMENEZ |
| Issued | 6/7/2016 | LADBS |
| Permit Expired-Status Void | 7/11/2018 | APPLICANT |
| Re-Activate Permit | 8/15/2018 | DANIEL ORRANTE |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
| CofO Issued | 8/14/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/14/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2016 | NATALIE MOORE |
| Sewer availability | Cleared | 4/26/2016 | NATALIE MOORE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/31/2019 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/31/2019 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Other (see comments) | 6/3/2019 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 6/13/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Grounding or Bonding | 8/25/2020 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 8/25/2020 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 8/25/2020 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 8/25/2020 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 9/9/2020 | Conditional Approval | CHRISTOPHER WILSON |
| Enclosure/Fence | 3/17/2023 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Final | 6/12/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 8/22/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 8/25/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 9/1/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 9/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Final | 7/30/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 8/5/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |