15012 W ROMAR ST 91345
Certificate Information: 15012 W ROMAR ST 91345
- Application / Permit
- 14047-20000-00527
- Plan Check / Job No.
- B14VN04562
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 21'X33'6" SWIMMING POOL AND 8'X9' SPA PER STD PLAN 268
- Permit Issued
- Issued on 4/16/2014
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2014 | SIAVOSH POURSABAHIAN |
| Plan Check Approved | 4/16/2014 | JOSE MENDOZA |
| Issued | 4/16/2014 | LADBS |
| CofO in Progress | 9/11/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/19/2025 | RUBEN SALAS |
| CofO Issued | 9/19/2025 | RUBEN SALAS |
| Permit Finaled | 9/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2014 | MIKE KOUYOUMDJIAN |
| Sewer availability | Cleared | 4/16/2014 | MIKE KOUYOUMDJIAN |
| Public Works-Highway Ded. | Cleared | 4/16/2014 | MIKE KOUYOUMDJIAN |
| Public Works-Open Permits | Cleared | 4/16/2014 | MIKE KOUYOUMDJIAN |
| Public Works-Sewers | Cleared | 4/16/2014 | MIKE KOUYOUMDJIAN |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C35 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Biedenbach, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/6/2014 | Approved | DONALD GALLAGHER |
| Deputy Shotcrete | 5/8/2014 | Approved | DONALD GALLAGHER |
| Deck | 7/9/2014 | Corrections Issued | DONALD GALLAGHER |
| Deck | 7/10/2014 | Approved | DONALD GALLAGHER |
| Enclosure/Fence | 7/24/2014 | Corrections Issued | DONALD GALLAGHER |
| Equipment Noise Level | 7/29/2014 | Not Ready for Inspection | DONALD GALLAGHER |
| Excavation/Setback/Form/Re-Bar | 8/1/2014 | Approved | DONALD GALLAGHER |
| Final | 8/1/2014 | Not Ready for Inspection | DONALD GALLAGHER |
| SGSOV-Seismic Gas S/O Valve | 8/1/2014 | SGSOV Approved | DONALD GALLAGHER |
| Deck | 10/28/2014 | Approved | DONALD GALLAGHER |
| Final | 3/28/2018 | Not Ready for Inspection | MARK JOHNSON |
| Pool Equipment Noise Test | 3/29/2018 | No Access for Inspection | FELIPE PENICHE |
| Equipment Noise Level | 4/3/2018 | Approved | FELIPE PENICHE |
| Special/Order Compliance | 5/6/2020 | Corrections Issued | ARAM AVEDISIAN |
| Special/Order Compliance | 2/4/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Enclosure/Fence | 3/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 7/31/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/11/2025 | OK to Issue CofO | JENNIFER RABUCHIN |