726-728 N ECHO PARK AVE 90026

Certificate Information: 726-728 N ECHO PARK AVE 90026

Application / Permit
14030-20000-00008
Plan Check / Job No.
B14VN00020
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR PROPOSED DUPLEX, SFD AND RETAINING WALLS
Permit Issued
Issued on 10/20/2021
Issuing Office
Metro
Current Status
Issued on 10/20/2021

Permit Application Status History

Submitted 1/9/2014 APPLICANT
Assigned to Plan Check Engineer 2/20/2014 HERNAN ARREOLA
Corrections Issued 2/28/2014 HERNAN ARREOLA
Quality Review Completed 2/28/2014 TAMERA SVETICH
Building Plans Picked Up 3/11/2014 APPLICANT
Applicant returned to address corrections 7/12/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/19/2021 HERNAN ARREOLA
Plan Check Approved 9/2/2021 HERNAN ARREOLA
Issued 10/20/2021 APPLICANT

Permit Application Clearance Information

HPOZ Cleared 1/4/2021 CHRISTINA PARK

Contact Information

Contractor Owner-Builder       ,
Engineer Fan,, Sea Kong; Lic. No.: S2524 21220 CORRAL COURT      WALNUT, CA 91789
Geologist Fishburn,, Scott David; Lic. No.: EG2114 1545 VICTORY BLVD.      GLENDALE, CA 91201

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 6/7/2022 Corrections Issued ROBERT HUGHES
Excavation 3/31/2023 Not Ready for Inspection JONATHAN HOM
Initial Grading 3/31/2023 Corrections Issued JONATHAN HOM
Excavation 4/4/2023 Not Ready for Inspection ROBERT HUGHES
Initial Grading 4/4/2023 Not Ready for Inspection ROBERT HUGHES
Excavation 5/19/2023 Not Ready for Inspection ROBERT HUGHES
Bottom/Toe 10/11/2023 Corrections Issued ROBERT HUGHES
Rough 10/11/2023 Not Ready for Inspection ROBERT HUGHES
Initial Grading 10/24/2023 Not Ready for Inspection ROBERT HUGHES
Excavation 2/28/2024 Not Ready for Inspection RUSSELL BONVOULOIR
Rough 2/28/2024 Not Ready for Inspection RUSSELL BONVOULOIR
Initial Grading 9/18/2024 Not Ready for Inspection LANNY MERRICK
Sub-Drain 9/18/2024 Not Ready for Inspection LANNY MERRICK
Drainage Devices/Catch Basin 9/20/2024 Partial Approval JONATHAN HOM
Special/Order Compliance 10/17/2024 Corrections Issued MICHAEL TEMPLE
Special/Order Compliance 10/29/2024 Partial Inspection LANNY MERRICK
Rough 12/17/2024 Not Ready for Inspection LANNY MERRICK
Sub-Drain 12/17/2024 Not Ready for Inspection LANNY MERRICK
Sub-Drain 12/19/2024 Partial Inspection LANNY MERRICK
Sub-Drain 8/15/2025 Not Ready for Inspection RAMAZANALI ALMASI
Sub-Drain 8/18/2025 Partial Approval RAMAZANALI ALMASI
Special/Order Compliance 1/5/2026 Partial Inspection JONATHAN HOM