1400 S FIGUEROA ST 90015
Certificate Information: 1400 S FIGUEROA ST 90015
- Application / Permit
- 14020-10000-03253
- Plan Check / Job No.
- B14LA17372
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING FOR NEW 110 UNIT APARTMENT COMPLEX, 7 STORIES WITH 2 LEVELS OF SUBTERRANEAN PARKING, AND GROUND FLOOR RETAIL.
- Permit Issued
- Issued on 11/17/2015
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2015 | RICARDO TRES |
| Corrections Issued | 2/9/2015 | RICARDO TRES |
| Quality Review Completed | 2/10/2015 | LINCOLN LEE |
| Disabled Access Plans Picked Up | 2/12/2015 | APPLICANT |
| Green Plans Picked Up | 3/6/2015 | APPLICANT |
| Plan Check Approved | 11/17/2015 | RICARDO TRES |
| Issued | 11/17/2015 | LADBS |
| Permit Finaled | 9/12/2023 | NICK DANERI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2015 | KARAN PATEL |
| Excavation more than 5-ft deep | Cleared | 9/10/2015 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 11/13/2015 | DAVID PEREZ |
| Work Adjacent to Public Way | Cleared | 11/13/2015 | DAVID PEREZ |
| Encroachment in public way | Cleared | 11/16/2015 | ARMENIA HERNANDEZ |
Contact Information
| Contractor | Fassberg Contracting Corporation; Lic. No.: 878820-B | 17000 VENTURA BLVD SUITE 200 ENCINO, CA 91316 |
| Engineer | Hill, Edward Foster; Lic. No.: GE2126 | GEOTECH 439 WESTERN AVE GLENDALE, CA 91201 |
| Engineer | Young, Don Yuk-Man; Lic. No.: C35713 | 650 SIERRA MADRE VILLA AVE #206 PASADENA, CA 91107 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 3/3/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 3/14/2016 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 3/15/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 3/16/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 3/17/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 3/18/2016 | Approved | TIMOTHY LYNN |
| Deputy Grading | 3/21/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 3/22/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/11/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 4/11/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/12/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 4/12/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/13/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 4/13/2016 | Conditional Approval | LESLIE TRUJILLO |
| Piling/Pier/Caisson | 4/13/2016 | Partial Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/14/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 4/14/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/15/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 4/15/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/19/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/20/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/21/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/22/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/26/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/27/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/28/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 4/29/2016 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 5/2/2016 | Partial Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 5/3/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 5/4/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Concrete | 5/5/2016 | Approved | TIMOTHY LYNN |
| Deputy Reinf. Concrete | 5/6/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 5/9/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 5/10/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 5/11/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 5/12/2016 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Grading | 5/13/2016 | Conditional Approval | LESLIE TRUJILLO |