Work Description
Remodel (E) detached ALQ;New roof, doors & windows in existing 1286 sqft accessory living quarter ; reduce one room by 39 sqft(2'3"x17'8");increase height to 22'.Not a major remodel.
Permit Issued
Issued on 5/16/2014
Issuing Office
Valley
Current Status
Issued on 5/16/2014
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/10/2014 APPLICANT
Assigned to Plan Check Engineer 2/13/2014 FARUK SEZER
Corrections Issued 2/19/2014 FARUK SEZER
Quality Review Completed 2/21/2014 TAMERA SVETICH
Building Plans Picked Up 2/24/2014 APPLICANT
Plan Check Approved 3/26/2014 FARUK SEZER
Issued 5/16/2014 LADBS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/3/2014 BRIAN OLSON

Contact Information

Contractor Owner-Builder       ,
Engineer Golabtounkar, Tony Hamid; Lic. No.: C49104 18345 VENTURA BLVD #208      TARZANA, CA 91356

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/23/2014 Corrections Issued ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 12/26/2014 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 12/31/2014 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 1/12/2015 Approved ANTHONY ANDERSON
FLOOD-Proofing Certificate 5/6/2015 Approved ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/6/2015 Approved ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/7/2016 Corrections Issued ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/11/2016 Partial Approval ANTHONY ANDERSON
ELECTRICAL-Rough 1/28/2016 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Rough 2/29/2016 Approved ANTHONY ANDERSON
Wood Frame 4/11/2016 Approved ANTHONY ANDERSON
Drywall Nailing 8/22/2016 Approved ANTHONY ANDERSON
Interior/Exterior Lathing 8/22/2016 Approved ANTHONY ANDERSON
Shower Pan 8/17/2017 Approved ANTHONY ANDERSON
Interior/Exterior Lathing 1/12/2018 Approved ANTHONY ANDERSON
Final 8/8/2018 No Access for Inspection JOEL LAUNCHBAUGH
Gas Test 1/10/2019 Corrections Issued CHRISTOPHER WILSON
Gas Test 1/11/2019 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 6/11/2019 Partial Inspection CHRISTOPHER WILSON
Shower Pan 6/11/2019 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 2/25/2020 Approved CHRISTOPHER WILSON
HVAC-Final 2/17/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 2/24/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 3/9/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/20/2024 Approved CHRISTOPHER WILSON
Final 12/20/2024 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 12/20/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 4/4/2025 Approved CHRISTOPHER WILSON