1774 W 92ND ST 90047

Certificate Information: 1774 W 92ND ST 90047

Application / Permit
14016-10001-14093
Plan Check / Job No.
B23LA23532
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Take Out
Work Description
SUPPLEMENTAL TO 14016-10000-14093 FOR REVISIONS TO EXTERIOR WALL
Permit Issued
Issued on 6/24/2024
Issuing Office
Metro
Current Status
Issued on 6/24/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 SINA KHOSRAVI
Corrections Issued 12/28/2023 SINA KHOSRAVI
Quality Review Completed 12/29/2023 KEN GILL
Building Plans Picked Up 1/16/2024 APPLICANT
Plan Check Approved 4/9/2024 SINA KHOSRAVI
Issued 6/24/2024 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 2/13/2024 SINA KHOSRAVI
Community Plan Implem. Overlay Cleared 4/4/2024 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 7/5/2024 Approved DARRYL ARNOLD
Wood Frame 12/11/2024 Partial Inspection ALFREDO LOPEZ
Drywall Nailing 3/19/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 3/19/2025 Partial Approval RAFAEL CORTES
Insulation 6/12/2025 Conditional Approval DARRYL ARNOLD
T-Bar Ceiling 7/1/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
T-Bar Ceiling 7/11/2025 Approved DARRYL ARNOLD
T-Bar Ceiling 7/18/2025 Approved DARRYL ARNOLD
Drywall Nailing 8/11/2025 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Conditional Approval DARRYL ARNOLD
Drywall Nailing 10/24/2025 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 10/24/2025 Not Ready for Inspection DARRYL ARNOLD
Drywall Nailing 10/27/2025 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 10/27/2025 Not Ready for Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Not Ready for Inspection ALFREDO LOPEZ
Insulation 12/5/2025 Approved ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Partial Inspection DARRYL ARNOLD
Insulation 1/14/2026 Approved ALFREDO LOPEZ