3220 S HELMS AVE 90034
Certificate Information: 3220 S HELMS AVE 90034
- Application / Permit
- 14016-10000-05177
- Plan Check / Job No.
- B14LA03454
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM RETAIL FURNITURE STORE TO RESTAURANT/BAKERY/RETAIL. ADD NEW BASEMENT STORAGE AND MEZZANINE FOOD PREP & STORAGE AREA. SEE COMMENTS.
- Permit Issued
- Issued on 6/30/2014
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2014 | HAYATO TSUCHIYA |
| Corrections Issued | 4/2/2014 | HAYATO TSUCHIYA |
| Disabled Access Plans Picked Up | 4/3/2014 | APPLICANT |
| Green Plans Picked Up | 4/4/2014 | APPLICANT |
| Quality Review Completed | 4/8/2014 | GARO TELMI |
| Building Plans Picked Up | 4/9/2014 | APPLICANT |
| Plan Check Approved | 6/30/2014 | HAYATO TSUCHIYA |
| Issued | 6/30/2014 | LADBS |
| CofO in Progress | 12/11/2024 | FARHAD DADBIN |
| Permit Finaled | 2/11/2025 | DAVID TSAU |
| CofO Issued | 2/11/2025 | DAVID TSAU |
| Permit Finaled | 2/11/2025 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/7/2014 | HERMAN VAN BUREN |
| CPC | Cleared | 5/7/2014 | HERMAN VAN BUREN |
| ZA Case | Cleared | 5/7/2014 | HERMAN VAN BUREN |
| ZA Case | Cleared | 5/7/2014 | HERMAN VAN BUREN |
| ZA Case | Cleared | 5/7/2014 | HERMAN VAN BUREN |
| ZA Case | Cleared | 5/7/2014 | HERMAN VAN BUREN |
| Food Service Establishment | Cleared | 5/29/2014 | KENNETH BROWNE |
| DAS Clearance | Cleared | 6/5/2014 | SHINE LIN |
| Green Code | Cleared | 6/17/2014 | MEL KHACHATOURIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2014 | AVALYN KAMACHI |
| Food establishment approval | Cleared | 6/20/2014 | LACDHS APPROVED |
| Sewer availability | Cleared | 6/20/2014 | AVALYN KAMACHI |
Contact Information
| Architect | Oakes, Julia Harder; Lic. No.: C18150 | 1934 AVA AVENUE HERMOSA BEACH, CA 90254 |
| Contractor | Owner-Builder | , |
| Engineer | Brown, Richard L; Lic. No.: S970 | 18980 VENTURA BLVD #350 TARZANA, CA 91356 |
| Engineer | Hill, Edward Foster; Lic. No.: GE2126 | GEOTECH 439 WESTERN AVE GLENDALE, CA 91201 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2014 | Not Ready for Inspection | TONY HARTONO |
| Grading Pre-Inspection | 6/19/2015 | Partial Approval | JASON MARKOWSKI |
| Deputy Reinf. Concrete | 7/21/2015 | Approved | JASON MARKOWSKI |
| Excavation/Setback/Form/Re-Bar | 7/21/2015 | Not Ready for Inspection | JASON MARKOWSKI |
| Deputy Reinf. Concrete | 7/23/2015 | Approved | JASON MARKOWSKI |
| Excavation/Setback/Form/Re-Bar | 7/23/2015 | Partial Approval | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 7/28/2015 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 7/29/2015 | Approved | JASON MARKOWSKI |
| Green Building Rough | 7/29/2015 | No Access for Inspection | ROLLIN GETTLE III |
| Reinforced Masonry Frame | 7/29/2015 | Partial Approval | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 7/30/2015 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 7/31/2015 | Partial Approval | JASON MARKOWSKI |
| Green Building Rough | 8/3/2015 | Partial Inspection | ROLLIN GETTLE III |
| Deputy Reinf. Masonry | 8/4/2015 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 8/5/2015 | Partial Approval | JASON MARKOWSKI |
| Deputy Reinf. Concrete | 8/7/2015 | No Access for Inspection | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 8/7/2015 | No Access for Inspection | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 8/12/2015 | Approved | JASON MARKOWSKI |
| Reinforced Masonry Frame | 8/12/2015 | Not Ready for Inspection | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 8/13/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/4/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/8/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/9/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/10/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/11/2015 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 10/20/2015 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 10/20/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/20/2015 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 10/21/2015 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 10/21/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/21/2015 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 10/22/2015 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 10/22/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/22/2015 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/23/2015 | Approved | JASON MARKOWSKI |
| Green Building Rough | 10/26/2015 | Not Ready for Inspection | JOHN KLARIN |
| Reinforced Masonry Frame | 10/26/2015 | Partial Approval | JASON MARKOWSKI |
| Green Building Rough | 11/9/2015 | Not Ready for Inspection | JOHN KLARIN |
| Reinforced Masonry Frame | 11/9/2015 | Partial Approval | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 11/25/2015 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 5/9/2016 | Approved | JASON MARKOWSKI |
| Deputy Reinf. Masonry | 5/9/2016 | Approved | JASON MARKOWSKI |
| Pre-Inspection | 7/20/2016 | Approved | JASON MARKOWSKI |
| Footing/Foundation/Slab | 7/25/2016 | Conditional Approval | JASON MARKOWSKI |
| Reinforced Concrete Frame | 8/2/2016 | Partial Approval | JASON MARKOWSKI |
| Footing/Foundation/Slab | 8/10/2016 | Conditional Approval | JASON MARKOWSKI |
| Deputy Steel/Welding | 8/18/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 8/19/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 8/22/2016 | Approved | JASON MARKOWSKI |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2016 | Partial Approval | RAFAEL ESPINOZA |
| Structural Steel Frame | 8/24/2016 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/25/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/27/2016 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/29/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 9/30/2016 | Approved | JASON MARKOWSKI |
| Deputy Pre-Stress Concrete | 10/14/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/14/2016 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 10/17/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/17/2016 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 10/18/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/18/2016 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 10/19/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 10/19/2016 | Approved | JASON MARKOWSKI |
| Deputy Drilled-In Anchors | 11/4/2016 | Approved | JASON BORUTA |
| Deputy Steel/Welding | 11/4/2016 | Approved | JASON BORUTA |
| Deputy Drilled-In Anchors | 11/7/2016 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/7/2016 | Approved | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 11/15/2016 | Approved | JASON BORUTA |
| Deputy Steel/Welding | 11/15/2016 | Approved | JASON BORUTA |
| Deputy Drilled-In Anchors | 11/16/2016 | Approved | JASON MARKOWSKI |
| Deputy Steel/Welding | 11/16/2016 | Approved | JASON MARKOWSKI |
| Special/Order Compliance | 11/16/2016 | Approved | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 11/17/2016 | Approved | JASON BORUTA |
| Deputy Steel/Welding | 11/17/2016 | Approved | JASON BORUTA |
| Structural Steel Frame | 11/18/2016 | Partial Inspection | JASON BORUTA |
| Pre-Inspection | 1/13/2017 | Approved | JASON BORUTA |
| Structural Steel Frame | 1/26/2017 | Partial Approval | JASON BORUTA |
| Pre-Inspection | 6/23/2017 | Approved | JASON BORUTA |
| Special/Order Compliance | 9/29/2017 | Approved | JASON BORUTA |
| Final | 7/17/2018 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 7/31/2018 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 9/18/2018 | Approved | JASON BORUTA |
| Grading Pre-Inspection | 7/15/2019 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 7/15/2019 | Approved | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 10/1/2019 | Conditional Approval | JASON BORUTA |
| Footing/Foundation/Slab | 10/16/2019 | Approved | JASON BORUTA |
| Wood Frame | 12/5/2019 | Partial Approval | JASON BORUTA |
| Pre-Inspection | 8/4/2020 | Partial Approval | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 7/14/2023 | Approved | FARHAD DADBIN |
| Deputy Steel/Welding | 7/17/2023 | Conditional Approval | FARHAD DADBIN |
| Drywall Nailing | 7/19/2024 | Approved | FARHAD DADBIN |
| Final | 7/19/2024 | OK to Issue CofO | FARHAD DADBIN |
| Green Building Final | 7/19/2024 | Approved | FARHAD DADBIN |
| Green Building Rough | 7/19/2024 | Approved | FARHAD DADBIN |
| Reinforced Concrete Frame | 7/19/2024 | Approved | FARHAD DADBIN |
| Reinforced Masonry Frame | 7/19/2024 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 7/19/2024 | Approved | FARHAD DADBIN |