720 E 48TH ST 90011
Certificate Information: 720 E 48TH ST 90011
- Application / Permit
- 14014-70000-00415
- Plan Check / Job No.
- B14SL00135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- STORAGE ADDITION TO THE REAR OF (E) GARAGE PER WFPP
- Permit Issued
- Issued on 2/12/2014
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2014 | JOSHUA DIAZ |
| Corrections Issued | 2/5/2014 | JOSHUA DIAZ |
| Plan Check Approved | 2/11/2014 | ALBERT SERVIN |
| Issued | 2/12/2014 | LADBS |
| CofO in Progress | 2/10/2021 | OSVALDO PARAMO |
| CofO in Progress | 2/10/2021 | OSVALDO PARAMO |
| CofO in Progress | 2/10/2021 | OSVALDO PARAMO |
| Permit Finaled | 2/25/2021 | DEROLD HAUFF |
| CofO Issued | 2/25/2021 | DEROLD HAUFF |
| Permit Finaled | 2/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/5/2014 | ARMANDO MEDINA |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2014 | AVALYN KAMACHI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/21/2014 | Partial Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/21/2014 | Approved | ENRIQUE MIRELES |
| Green Building Final | 3/21/2014 | Not Ready for Inspection | DEROLD HAUFF |
| Green Building Rough | 3/21/2014 | Not Ready for Inspection | DEROLD HAUFF |
| Smoke Detectors | 3/21/2014 | Approved | ENRIQUE MIRELES |
| Wood Frame | 3/21/2014 | Approved | ENRIQUE MIRELES |
| Final | 3/27/2014 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 3/27/2014 | Approved | DEROLD HAUFF |
| Green Building Rough | 3/27/2014 | Approved | DEROLD HAUFF |
| Wood Frame | 3/27/2014 | Partial Approval | ENRIQUE MIRELES |
| Final | 1/26/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Final | 1/26/2021 | Approved | ROBERT MCDOWELL |
| Wood Frame | 1/26/2021 | Approved | ROBERT MCDOWELL |
| Final | 2/8/2021 | OK to Issue CofO | OSVALDO PARAMO |