10535 W VESTONE WAY 90077

Certificate Information: 10535 W VESTONE WAY 90077

Application / Permit
14014-40004-05560
Plan Check / Job No.
B16SP00550
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLIMENTAIL PERMIT TO 14014-40000-05560 TO ADD ADDDTIONAL FLOOR AREA TO EXISTING SINGLE FAMILY DWELLING. CONVERT THE EXISTING ATTACHED GARAGE TO LIVING AREA. REVISE THE ROOF FRAMING.
Permit Issued
Issued on 10/24/2016
Issuing Office
Valley
Current Status
Issued on 10/24/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/27/2016 APPLICANT
Assigned to Plan Check Engineer 7/21/2016 RUDOLF KINAR MELIKOFF
Corrections Issued 7/25/2016 RUDOLF KINAR MELIKOFF
Quality Review Completed 7/27/2016 TIEN JEN WANG
Applicant returned to address corrections 9/15/2016 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 9/27/2016 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 10/7/2016 RUDOLF KINAR MELIKOFF
Plan Check Approved 10/21/2016 RUDOLF KINAR MELIKOFF
Issued 10/24/2016 LADBS

Permit Application Clearance Information

Green Code Cleared 8/15/2016 BRYAN MEYER
Grading Pre-Inspection Cleared 9/27/2016 BRIAN OLSON
Low Impact Development Cleared 10/11/2016 MICHAEL SCADUTO
Certificate of Compliance Cleared 10/14/2016 NORALI MARTINEZ
Private street Cleared 10/14/2016 NORALI MARTINEZ
Distance to fire station Cleared 10/17/2016 ROBERT DUFF
Hydrant and Access approval Cleared 10/17/2016 ROBERT DUFF
BHO/Hillside ordinance Cleared 10/18/2016 HUGO RICO
BHO/Hillside ordinance Cleared 10/18/2016 HUGO RICO
BHO/Hillside ordinance Cleared 10/18/2016 HUGO RICO
BHO/Hillside ordinance Cleared 10/18/2016 HUGO RICO
Eng Process Fee Ord 176,300 Cleared 10/18/2016 HUGO RICO
Roof/Waste drainage to street Cleared 10/18/2016 HUGO RICO
Sewer availability Cleared 10/18/2016 HUGO RICO
Excavation more than 5-ft deep Cleared 10/21/2016 CALOSHA APPROVED

Contact Information

Architect James, William Douglas; Lic. No.: C28863 415 W NINTH STREET      SAN PEDRO, CA 90731
Contractor Owner-Builder       ,
Engineer Khazra, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2016 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 11/2/2016 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/9/2016 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 11/10/2016 Conditional Approval ANTHONY ANDERSON
BUILDING-Rough-Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
Drywall Nailing 12/28/2017 Partial Inspection ANTHONY ANDERSON
Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 12/28/2017 Approved ANTHONY ANDERSON
Green Building Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
Green Building Rough 12/28/2017 Partial Inspection ANTHONY ANDERSON
Reinforced Masonry Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
Smoke Detectors 12/28/2017 Partial Inspection ANTHONY ANDERSON
Structural Steel Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 12/28/2017 Not Ready for Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 1/23/2018 Partial Inspection ANTHONY ANDERSON
Green Building Rough 1/23/2018 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 1/23/2018 Partial Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Drywall Nailing 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Final 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Final 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 1/18/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 1/18/2019 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Drywall Nailing 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Final 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Final 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Pre-Inspection 10/22/2021 Partial Approval CHRISTOPHER WILSON