10535 W VESTONE WAY 90077

Certificate Information: 10535 W VESTONE WAY 90077

Application / Permit
14014-40000-05560
Plan Check / Job No.
B14SP00676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE AND RECONSTRUCT PORTION OF EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND BASEMENT. ADDITION AND REMODEL.
Permit Issued
Issued on 7/24/2015
Issuing Office
Valley
Current Status
Issued on 7/24/2015
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/22/2014 APPLICANT
Assigned to Plan Check Engineer 12/30/2014 RUDOLF KINAR MELIKOFF
Green Plans Picked Up 1/13/2015 APPLICANT
Corrections Issued 4/7/2015 RUDOLF KINAR MELIKOFF
Quality Review Completed 4/7/2015 BINH PHAN
Applicant returned to address corrections 4/7/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 5/29/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/8/2015 RUDOLF KINAR MELIKOFF
Plan Check Approved 7/24/2015 RUDOLF KINAR MELIKOFF
Issued 7/24/2015 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/2/2015 KELTON KIRBY
BHO/Hillside ordinance Cleared 4/2/2015 KELTON KIRBY
BHO/Hillside ordinance Cleared 4/2/2015 KELTON KIRBY
BHO/Hillside ordinance Cleared 4/2/2015 KELTON KIRBY
Eng Process Fee Ord 176,300 Cleared 4/2/2015 KELTON KIRBY
Sewer availability Cleared 4/2/2015 KELTON KIRBY
Green Code Cleared 4/30/2015 RICHARD DOCKUS
Low Impact Development Cleared 5/6/2015 AMMAR ELTAWIL
Distance to fire station Cleared 5/20/2015 ROBERT DUFF
Hydrant and Access approval Cleared 5/20/2015 ROBERT DUFF
Roof/Waste drainage to street Cleared 5/20/2015 KELTON KIRBY
Certificate of Compliance Cleared 5/22/2015 SUSAN ZERMENO
Private street Cleared 5/22/2015 SUSAN ZERMENO
Excavation more than 5-ft deep Cleared 5/29/2015 CALOSHA APPROVED
Grading Pre-Inspection Cleared 5/29/2015 BRIAN OLSON

Contact Information

Architect James, William Douglas; Lic. No.: C28863 415 W NINTH STREET      SAN PEDRO, CA 90731
Contractor Owner-Builder       ,
Engineer Khazra, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 7/30/2015 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 8/20/2015 Corrections Issued ANTHONY ANDERSON
Piling/Pier/Caisson 8/26/2015 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 9/14/2015 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 9/14/2015 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 10/1/2015 Corrections Issued ANTHONY ANDERSON
Footing/Foundation/Slab 10/14/2015 Partial Inspection ANTHONY ANDERSON
Deputy Reinf. Concrete 10/16/2015 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 10/16/2015 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/23/2015 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 11/23/2015 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/30/2015 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 12/17/2015 Partial Inspection ANTHONY ANDERSON
Deputy Reinf. Concrete 2/3/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 8/18/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 8/19/2016 Conditional Approval ANTHONY ANDERSON
Underground Mechanical 9/21/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 10/25/2016 Partial Inspection ANTHONY ANDERSON
Shower Pan 1/10/2017 Partial Approval ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/8/2017 Partial Approval ANTHONY ANDERSON
Green Building Rough 2/8/2017 Not Ready for Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 2/8/2017 Not Ready for Inspection ANTHONY ANDERSON
Insulation 4/13/2017 Not Ready for Inspection DANIEL ORRANTE
Interior/Exterior Lathing 4/13/2017 No Access for Inspection DANIEL ORRANTE
Insulation 4/18/2017 Partial Inspection ANTHONY ANDERSON
Interior/Exterior Lathing 4/18/2017 Partial Inspection ANTHONY ANDERSON
Shower Pan 6/1/2017 Approved ANTHONY ANDERSON
Rough-Elec/Plmb/HVAC 6/15/2017 Approved ANTHONY ANDERSON
BUILDING-Rough-Frame 8/3/2017 Partial Inspection ANTHONY ANDERSON
Green Building Rough 8/3/2017 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 11/28/2017 Not Ready for Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 12/8/2017 Partial Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
Drywall Nailing 12/28/2017 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
Final 12/28/2017 Corrections Issued ANTHONY ANDERSON
Footing/Foundation/Slab 12/28/2017 Approved ANTHONY ANDERSON
Green Building Final 12/28/2017 Not Ready for Inspection ANTHONY ANDERSON
HVAC-Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
PLUMBING-Final 12/28/2017 Partial Inspection ANTHONY ANDERSON
Reinforced Masonry Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
SGSOV-Seismic Gas S/O Valve 12/28/2017 SGSOV Not Ready ANTHONY ANDERSON
Smoke Detectors 12/28/2017 Not Ready for Inspection ANTHONY ANDERSON
Structural Steel Frame 12/28/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 12/28/2017 Not Ready for Inspection ANTHONY ANDERSON
Structural Steel Frame 8/29/2018 Partial Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/12/2018 SGSOV Not Required CARLOS MATAMOROS
BUILDING-Rough-Frame 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Drywall Nailing 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Final 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Final 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Reinforced Masonry Frame 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 2/19/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/19/2019 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Drywall Nailing 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Final 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Final 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Pre-Inspection 3/11/2019 Corrections Issued MICHAEL TEMPLE
Reinforced Masonry Frame 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Smoke Detectors 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 3/11/2019 Partial Inspection CHRISTOPHER WILSON
Pre-Inspection 9/17/2021 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 10/22/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 2/7/2022 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 6/27/2022 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 7/27/2022 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 7/27/2022 Partial Inspection MICHAEL PELHAM
Pre-Inspection 10/28/2025 Partial Inspection JUAN VALENZUELA
Pre-Inspection 5/6/2026 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 5/6/2026 Partial Inspection ANDREW NAVE