900 N STRADELLA ROAD 90077

Certificate Information: 900 N STRADELLA ROAD 90077

Application / Permit
14014-30000-05206
Plan Check / Job No.
B14WL05413
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL. DEMOLISH PORTION OF EXISTING SINGLE FAMILY DWELLING. ADDITION AND RECONSTRUCTION. ADDITION OVER EXISITING DRIVEWAY.
Permit Issued
Issued on 6/2/2015
Issuing Office
Valley
Current Status
CofO Issued on 12/6/2017
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2014 APPLICANT
Application Withdrawn 12/2/2014 APPLICANT
Re-Activate Applicaton 12/2/2014 APPLICANT
Assigned to Plan Check Engineer 12/11/2014 RUDOLF KINAR MELIKOFF
Corrections Issued 12/15/2014 RUDOLF KINAR MELIKOFF
Quality Review Completed 12/15/2014 ARA SARGSYAN
Building Plans Picked Up 12/15/2014 APPLICANT
Green Plans Picked Up 12/15/2014 APPLICANT
Applicant returned to address corrections 1/21/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 2/25/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 3/4/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 3/16/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 3/20/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 4/22/2015 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 5/1/2015 RUDOLF KINAR MELIKOFF
Plan Check Approved 6/2/2015 RUDOLF KINAR MELIKOFF
Issued 6/2/2015 LADBS
CofO in Progress 11/29/2017 ANTHONY ANDERSON
Permit Finaled 12/6/2017 DANIEL ORRANTE
CofO Issued 12/6/2017 DANIEL ORRANTE
Permit Finaled 12/6/2017 DANIEL ORRANTE

Permit Application Clearance Information

Distance to fire station Cleared 3/17/2015 ROBERT DUFF
Hydrant and Access approval Cleared 3/17/2015 ROBERT DUFF
Low Impact Development Cleared 4/30/2015 MICHAEL SCADUTO
Address approval Cleared 5/1/2015 JOHN LIN
BHO/Hillside ordinance Cleared 5/1/2015 JOHN LIN
BHO/Hillside ordinance Cleared 5/1/2015 JOHN LIN
BHO/Hillside ordinance Cleared 5/1/2015 JOHN LIN
BHO/Hillside ordinance Cleared 5/1/2015 JOHN LIN
Excavation more than 5-ft deep Cleared 5/1/2015 CALOSHA APPROVED
Grading Pre-Inspection Cleared 5/1/2015 RUDOLF KINAR MELIKOFF
Roof/Waste drainage to street Cleared 5/1/2015 JOHN LIN
Green Code Cleared 5/5/2015 MICKEY YAMASHITA
Disturb/Remove Protected Trees Cleared 5/14/2015 TROY CALLEROS
Eng Process Fee Ord 176,300 Cleared 5/15/2015 RICHARD SOUTHERLAND
Sewer availability Cleared 5/15/2015 RICHARD SOUTHERLAND

Contact Information

Architect Peck, Christopher M; Lic. No.: C27316 25 SOUTH EL MOLINO AVENUE   C M PECK CONSULTING    PASADENA, CA 911012023
Contractor Gibson Gordon S Inc; Lic. No.: 524012-B 3000 31 STREET SUITE G      SANTA MONICA, CA 90405
Engineer Labib, Youhanna T; Lic. No.: C57391 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

CHRISTOPHER WILSON, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 9/1/2015 Conditional Approval ANTHONY ANDERSON
Piling/Pier/Caisson 9/4/2015 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 10/6/2015 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 11/16/2015 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/23/2015 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 1/4/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 1/5/2016 No Access for Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 1/11/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 1/20/2016 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 1/21/2016 Approved RONALD MYRICK
Excavation/Setback/Form/Re-Bar 1/28/2016 Partial Approval RONALD MYRICK
PLUMBING-Rough 1/28/2016 Partial Approval RONALD MYRICK
Deputy Reinf. Concrete 1/29/2016 Conditional Approval ERWIN LARRANAGA
PLUMBING-Rough 2/4/2016 Partial Approval ANTHONY ANDERSON
Wood Frame 2/4/2016 Partial Approval ANTHONY ANDERSON
Deputy Wood Construction 2/5/2016 Approved ANTHONY ANDERSON
Wood Frame 2/5/2016 Partial Approval ANTHONY ANDERSON
Deputy Wood Construction 2/26/2016 Approved ANTHONY ANDERSON
Wood Frame 2/26/2016 Partial Approval ANTHONY ANDERSON
Deputy Shotcrete 3/9/2016 Conditional Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 3/9/2016 Partial Approval ANTHONY ANDERSON
Deputy Shotcrete 3/11/2016 Conditional Approval DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 3/18/2016 Approved DANIEL ORRANTE
Deputy Reinf. Concrete 3/22/2016 Conditional Approval ANTHONY ANDERSON
Masonry Wall/Backfill 4/4/2016 Partial Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 4/21/2016 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 4/21/2016 Partial Approval ANTHONY ANDERSON
Masonry Wall/Backfill 4/21/2016 Approved ANTHONY ANDERSON
Deputy Reinf. Concrete 4/22/2016 Approved DANIEL ORRANTE
Footing/Foundation/Slab 5/6/2016 Partial Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 5/12/2016 Conditional Approval ANTHONY ANDERSON
PLUMBING-Rough 5/12/2016 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 5/17/2016 Conditional Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 5/23/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 5/23/2016 Conditional Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 5/24/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 5/24/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 5/25/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 5/27/2016 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 5/27/2016 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 6/1/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 6/20/2016 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 7/1/2016 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 7/1/2016 Not Ready for Inspection ANTHONY ANDERSON
Deputy Reinf. Concrete 7/6/2016 Approved ANTHONY ANDERSON
Deputy Wood Construction 7/11/2016 Approved JOEL LAUNCHBAUGH
Deputy Wood Construction 7/11/2016 Conditional Approval ANTHONY ANDERSON
PLUMBING-Rough 7/11/2016 Partial Approval JOEL LAUNCHBAUGH
ELECTRICAL-Rough 7/12/2016 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 7/19/2016 Approved ANTHONY ANDERSON
ELECTRICAL-Rough 8/5/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 8/15/2016 Corrections Issued ANTHONY ANDERSON
Deputy Steel/Welding 8/17/2016 Conditional Approval ANTHONY ANDERSON
Deputy Wood Construction 8/17/2016 Approved ANTHONY ANDERSON
Reinforced Concrete Frame 8/31/2016 Partial Approval ANTHONY ANDERSON
Deputy Steel/Welding 9/13/2016 Approved ANTHONY ANDERSON
Deputy Steel/Welding 9/14/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 9/15/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 9/16/2016 Conditional Approval ANTHONY ANDERSON
Reinforced Concrete Frame 9/21/2016 Partial Approval ANTHONY ANDERSON
Deputy Wood Construction 10/4/2016 Conditional Approval ANTHONY ANDERSON
Deputy Wood Construction 10/6/2016 Conditional Approval ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/11/2016 Partial Approval ANTHONY ANDERSON
Insulation 10/20/2016 Partial Approval ANTHONY ANDERSON
Deputy Wood Construction 10/31/2016 Conditional Approval ANTHONY ANDERSON
ELECTRICAL-Rough 11/1/2016 No Access for Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 11/2/2016 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/3/2016 Corrections Issued ANTHONY ANDERSON
Service/Power Release 11/16/2016 Partial Inspection ANTHONY ANDERSON
Deputy Wood Construction 11/28/2016 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 11/30/2016 Approved ANTHONY ANDERSON
PLUMBING-Rough 11/30/2016 Partial Approval ANTHONY ANDERSON
Wood Frame 11/30/2016 Partial Approval ANTHONY ANDERSON
Interior/Exterior Lathing 12/22/2016 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 12/30/2016 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 1/3/2017 Partial Approval JOEL LAUNCHBAUGH
Floor/Roof Diaphrgm/Shear Wall 1/3/2017 Partial Approval JOEL LAUNCHBAUGH
HVAC-Rough 1/3/2017 Partial Approval JOEL LAUNCHBAUGH
PLUMBING-Rough 1/3/2017 Partial Approval JOEL LAUNCHBAUGH
ELECTRICAL-Rough 1/13/2017 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Rough 1/17/2017 Approved ANTHONY ANDERSON
PLUMBING-Rough 1/17/2017 Approved ANTHONY ANDERSON
HVAC-Rough 1/23/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 1/23/2017 Partial Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 1/26/2017 Partial Approval ANTHONY ANDERSON
Green Building Rough 1/26/2017 Approved ANTHONY ANDERSON
Verify Sprinkler Sign Off 1/26/2017 Approved ANTHONY ANDERSON
Insulation 1/27/2017 Partial Approval ANTHONY ANDERSON
HVAC-Rough 2/1/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 2/3/2017 Approved ANTHONY ANDERSON
Drywall Nailing 2/6/2017 Partial Approval ANTHONY ANDERSON
Interior/Exterior Lathing 2/9/2017 Partial Approval ANTHONY ANDERSON
Drywall Nailing 2/13/2017 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/13/2017 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/15/2017 Partial Approval ANTHONY ANDERSON
Interior/Exterior Lathing 2/22/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 2/22/2017 Approved ANTHONY ANDERSON
Shower Pan 2/24/2017 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/2/2017 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 3/3/2017 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/13/2017 Approved ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 4/10/2017 Approved ANTHONY ANDERSON
Pool/Spa Cover 4/10/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 4/11/2017 Conditional Approval ANTHONY ANDERSON
Reinforced Concrete Frame 4/14/2017 Approved ANTHONY ANDERSON
PLUMBING-Rough 5/2/2017 Approved ANTHONY ANDERSON
Rough-Elec/Plmb/HVAC 5/2/2017 Partial Inspection ANTHONY ANDERSON
Sewer 5/2/2017 Partial Inspection ANTHONY ANDERSON
Underground Mechanical 5/2/2017 Approved ANTHONY ANDERSON
Sewer 5/4/2017 Approved ANTHONY ANDERSON
Interior/Exterior Lathing 5/25/2017 Partial Inspection ANTHONY ANDERSON
PLUMBING-Final 5/25/2017 Not Ready for Inspection ANTHONY ANDERSON
ELECTRICAL-Final 6/7/2017 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Rough 6/7/2017 Approved ANTHONY ANDERSON
PLUMBING-Final 6/7/2017 Partial Inspection ANTHONY ANDERSON
PLUMBING-Rough 6/7/2017 Approved ANTHONY ANDERSON
PLUMBING-Final 6/9/2017 Partial Inspection ANTHONY ANDERSON
ELECTRICAL-Final 6/12/2017 Partial Inspection ANTHONY ANDERSON
HVAC-Final 6/12/2017 Partial Inspection ANTHONY ANDERSON
HVAC-Final 6/15/2017 Partial Inspection ANTHONY ANDERSON
Gas Test 7/10/2017 Approved JOEL LAUNCHBAUGH
PLUMBING-Final 7/10/2017 Corrections Issued JOEL LAUNCHBAUGH
Enclosure/Fence 7/14/2017 Partial Inspection ANTHONY ANDERSON
Enclosure/Fence 7/20/2017 Partial Inspection ANTHONY ANDERSON
HVAC-Final 7/25/2017 Partial Inspection ANTHONY ANDERSON
Interior/Exterior Lathing 7/25/2017 Approved ANTHONY ANDERSON
Service/Power Release 7/25/2017 Approved ANTHONY ANDERSON
Special/Order Compliance 8/5/2017 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/19/2017 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 8/24/2017 Corrections Issued ANTHONY ANDERSON
Enclosure/Fence 8/24/2017 Approved ANTHONY ANDERSON
PLUMBING-Final 8/24/2017 Approved ANTHONY ANDERSON
Pool/Spa Cover 8/24/2017 Approved ANTHONY ANDERSON
ELECTRICAL-Final 8/30/2017 Partial Approval ANTHONY ANDERSON
ELECTRICAL-Final 10/12/2017 Approved ANTHONY ANDERSON
HVAC-Final 10/12/2017 Conditional Approval ANTHONY ANDERSON
Gas Test 10/16/2017 Approved ANTHONY ANDERSON
Green Building Final 10/16/2017 Partial Inspection ANTHONY ANDERSON
Green Building Final 10/31/2017 Approved ANTHONY ANDERSON
BUILDING-Rough-Frame 11/13/2017 Approved ANTHONY ANDERSON
Drywall Nailing 11/13/2017 Approved ANTHONY ANDERSON
Final 11/13/2017 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 11/13/2017 Approved ANTHONY ANDERSON
Reinforced Masonry Frame 11/13/2017 Approved ANTHONY ANDERSON
SGSOV-Seismic Gas S/O Valve 11/13/2017 SGSOV Approved ANTHONY ANDERSON
Smoke Detectors 11/13/2017 Approved ANTHONY ANDERSON
Structural Steel Frame 11/13/2017 Approved ANTHONY ANDERSON
Final 11/28/2017 OK to Issue CofO ANTHONY ANDERSON