546 N MCCADDEN PL 90004
Certificate Information: 546 N MCCADDEN PL 90004
- Application / Permit
- 14014-30000-03721
- Plan Check / Job No.
- B14WL03699
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior remodel to (e) two story s.f.d. including addition to (e) basement, new windows/doors, removal of (e) trellis *** 1 of 2 ***
- Permit Issued
- Issued on 11/24/2014
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2014 | CHIHARU SUZUKI |
| Corrections Issued | 9/7/2014 | CHIHARU SUZUKI |
| Quality Review Completed | 9/12/2014 | RUDOLF KINAR MELIKOFF |
| Green Plans Picked Up | 9/12/2014 | APPLICANT |
| Building Plans Picked Up | 9/15/2014 | APPLICANT |
| Applicant returned to address corrections | 10/30/2014 | CHIHARU SUZUKI |
| Plan Check Approved | 11/24/2014 | CHIHARU SUZUKI |
| Issued | 11/24/2014 | LADBS |
| CofO in Progress | 9/21/2021 | BRIAN SULLIVAN |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| CofO Issued | 9/25/2021 | DEROLD HAUFF |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/23/2014 | PHONG NGUYEN |
| Low Impact Development | Cleared | 10/20/2014 | MARTIN FRAGOSO |
| HPOZ | Cleared | 10/29/2014 | KIMBERLY HENRY |
| ZA Case | Cleared | 10/29/2014 | KIMBERLY HENRY |
| ZA Case | Cleared | 10/29/2014 | KIMBERLY HENRY |
| ZI | Cleared | 11/10/2014 | MINDY NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2014 | KELTON KIRBY |
| Green Code | Cleared | 11/21/2014 | DEROLD HAUFF |
Contact Information
| Architect | Caplow, Bradley Richard; Lic. No.: C29973 | 3620 VALLEY MEADOW ROAD SHERMAN OAKS, CA 91403 |
| Contractor | Chastain Construction; Lic. No.: 669868-B | 3574 SCHAEFER STREET CULVER CITY, CA 90230 |
| Engineer | Polon, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2015 | Partial Approval | RUBEN SALAS |
| METHANE-Barrier | 10/26/2015 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Subgrade | 10/26/2015 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 3/15/2016 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 3/15/2016 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Rough | 3/15/2016 | Partial Inspection | RUBEN SALAS |
| Deck | 10/25/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Test | 12/18/2018 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 12/20/2018 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/8/2021 | Approved | BRIAN SULLIVAN |
| Final | 2/8/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 2/8/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 2/8/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 2/8/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 2/8/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Final | 2/8/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Rough | 2/8/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 2/8/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 2/8/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 9/20/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| Smoke Detectors | 9/20/2021 | Approved | BRIAN SULLIVAN |