777 N SARBONNE ROAD 90077

Certificate Information: 777 N SARBONNE ROAD 90077

Application / Permit
14014-30000-03508
Plan Check / Job No.
B14WL03479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to and major remodeling to existing single family dwelling, connecting to existing accessory living quarters and covert ALQ to part of dwelling.
Permit Issued
Issued on 3/23/2015
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2014 APPLICANT
Assigned to Plan Check Engineer 8/14/2014 KAMRAN GHOTBI RAVANDI
Corrections Issued 8/19/2014 KAMRAN GHOTBI RAVANDI
Quality Review Completed 8/19/2014 ARA SARGSYAN
Green Plans Picked Up 8/25/2014 APPLICANT
Applicant returned to address corrections 9/30/2014 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/16/2014 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/17/2014 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/23/2014 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/18/2014 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/9/2014 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/24/2015 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/5/2015 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/23/2015 KAMRAN GHOTBI RAVANDI
Issued 3/23/2015 LADBS
CofO in Progress 3/25/2021 CHRISTOPHER WILSON
Permit Finaled 4/19/2021 VINCENT COTTON
CofO Issued 4/19/2021 VINCENT COTTON
Permit Finaled 4/19/2021 VINCENT COTTON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/17/2014 TAO YANG
BHO/Hillside ordinance Cleared 10/17/2014 TAO YANG
BHO/Hillside ordinance Cleared 10/17/2014 TAO YANG
BHO/Hillside ordinance Cleared 10/17/2014 TAO YANG
Eng Process Fee Ord 176,300 Cleared 10/17/2014 TAO YANG
Permit Cleared 10/17/2014 TAO YANG
Sewer availability Cleared 10/17/2014 TAO YANG
Green Code Cleared 2/25/2015 KAMRAN GHOTBI RAVANDI
Low Impact Development Cleared 2/26/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/27/2015 ANGEL SALCEDO

Contact Information

Contractor Pacific Construction Enterprises; Lic. No.: 791355-B 3719 S ROBERTSON BLVD.      CULVER CITY, CA 90232
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Fishburn, Scott David; Lic. No.: EG2114 1545 VICTORY BLVD.      GLENDALE, CA 91201

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/12/2015 Corrections Issued DAVID JAMES
Piling/Pier/Caisson 7/1/2015 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 7/9/2015 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 10/1/2015 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 10/9/2015 Partial Inspection RONALD MYRICK
PLUMBING-Rough 1/27/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 2/24/2016 Corrections Issued ANTHONY ANDERSON
Footing/Foundation/Slab 3/2/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 3/29/2016 Partial Approval ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/13/2016 Partial Approval ANTHONY ANDERSON
Green Building Rough 4/13/2016 Not Ready for Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 4/13/2016 Not Ready for Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 4/18/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 6/6/2016 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 7/8/2016 Partial Approval JOEL LAUNCHBAUGH
Floor/Roof Diaphrgm/Shear Wall 1/27/2017 Partial Approval ANTHONY ANDERSON
Underground Mechanical 1/27/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 2/28/2017 Partial Approval ANTHONY ANDERSON
PLUMBING-Rough 3/8/2017 Partial Approval ANTHONY ANDERSON
Gas Test 3/31/2017 Corrections Issued ANTHONY ANDERSON
PLUMBING-Rough 3/31/2017 Corrections Issued ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/28/2017 Partial Approval ANTHONY ANDERSON
HVAC-Rough 9/18/2017 Approved ANTHONY ANDERSON
Wood Frame 1/8/2018 Partial Inspection ANTHONY ANDERSON
Wood Frame 1/18/2018 Partial Approval ANTHONY ANDERSON
Interior/Exterior Lathing 2/13/2018 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/21/2018 Approved ANTHONY ANDERSON
PLUMBING-Rough 2/21/2018 Not Ready for Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 3/12/2018 Not Ready for Inspection ANTHONY ANDERSON
Green Building Rough 3/12/2018 Not Ready for Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 3/12/2018 Not Ready for Inspection ANTHONY ANDERSON
BUILDING-Rough-Frame 3/19/2018 Corrections Issued ANTHONY ANDERSON
Green Building Rough 3/19/2018 Not Ready for Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 3/19/2018 Not Ready for Inspection ANTHONY ANDERSON
Drywall Nailing 5/1/2018 Not Ready for Inspection ANTHONY ANDERSON
Green Building Rough 5/1/2018 Approved ANTHONY ANDERSON
Insulation 5/1/2018 Conditional Approval ANTHONY ANDERSON
BUILDING-Rough-Frame 5/4/2018 Approved ANTHONY ANDERSON
Drywall Nailing 5/4/2018 Approved ANTHONY ANDERSON
Verify Sprinkler Sign Off 5/4/2018 Approved ANTHONY ANDERSON
Service/Power Release 1/6/2020 Not Ready for Inspection ANTHONY MCDOWALL
Service/Power Release 1/14/2020 Approved ANTHONY MCDOWALL
PLUMBING-Final 1/21/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 1/24/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Final 2/4/2020 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Final 2/5/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 2/10/2020 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/11/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 8/31/2020 Approved CHRISTOPHER WILSON
HVAC-Final 10/30/2020 Approved CHRISTOPHER WILSON
PLUMBING-Final 11/5/2020 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 11/19/2020 Approved CHRISTOPHER WILSON
Final 2/8/2021 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 2/8/2021 Approved CHRISTOPHER WILSON
Green Building Final 2/8/2021 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 2/8/2021 Approved CHRISTOPHER WILSON
Final 3/24/2021 OK to Issue CofO CHRISTOPHER WILSON