14645 W VOSE ST 91405
Certificate Information: 14645 W VOSE ST 91405
- Application / Permit
- 14014-20000-04787
- Plan Check / Job No.
- B14VN13613
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION AND REMODEL TO EXISTING 1-STORY S.F.D.
- Permit Issued
- Issued on 4/28/2016
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/28/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/3/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2014 | TARIK SAOUD |
| Corrections Issued | 12/9/2014 | TARIK SAOUD |
| Green Plans Picked Up | 12/12/2014 | APPLICANT |
| Quality Review Completed | 12/17/2014 | GARO TELMI |
| Applicant returned to address corrections | 9/24/2015 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/8/2015 | TARIK SAOUD |
| Applicant returned to address corrections | 12/22/2015 | TARIK SAOUD |
| Applicant returned to address corrections | 4/4/2016 | TARIK SAOUD |
| Plan Check Approved | 4/28/2016 | TARIK SAOUD |
| Issued | 4/28/2016 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2015 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/1/2015 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/1/2015 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 7/24/2015 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 7/28/2015 | ARMEN DERMENJIAN |
| Green Code | Cleared | 9/1/2015 | MICKEY YAMASHITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/18/2016 | Partial Approval | MICHAEL YOUNG |
| Footing/Foundation/Slab | 5/26/2017 | Partial Approval | GREG ALLTON |
| BUILDING-Rough-Frame | 9/8/2017 | Partial Approval | GREG ALLTON |
| PLUMBING-Rough | 9/8/2017 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2017 | Partial Approval | GREG ALLTON |
| Insulation | 10/4/2017 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2018 | Partial Approval | GREG ALLTON |
| Shower Pan | 10/1/2018 | No Access for Inspection | GREG ALLTON |
| Shower Pan | 10/2/2018 | Approved | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 3/21/2019 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2019 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 1/10/2020 | Conditional Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 1/29/2020 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 8/11/2020 | No Access for Inspection | WILLIAM KUEHN |
| Drywall Nailing | 2/19/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 7/29/2021 | Partial Inspection | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 12/8/2021 | No Access for Inspection | RICHARD DOCKUS |
| Deputy Wood Construction | 12/8/2021 | No Access for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Not Ready for Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Conditional Approval | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 8/12/2022 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 8/30/2022 | Approved | WILLIAM WREN |
| Service/Power Release | 9/11/2023 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 2/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 7/8/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 7/8/2024 | Approved | RYAN SALAZAR |
| Insulation | 10/4/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 2/7/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 8/1/2025 | Partial Approval | MISAEL ESPARZA |
| Insulation | 2/12/2026 | Approved | MICHAEL CORTEZ |