4755 W GLENALBYN DR 90065
Certificate Information: 4755 W GLENALBYN DR 90065
- Application / Permit
- 14014-20000-01775
- Plan Check / Job No.
- B14VN05203
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2nd story addition to (e) one story sfd. Demo entire interior first floor to remodel and add irr shape 26'8"x24'9 1/2" 2nd story and irr shape roof top deck.Building to have NFPA 13d fire sprinkler system.
- Permit Issued
- Issued on 6/2/2015
- Issuing Office
- South Los Angeles
- Current Status
- Permit Finaled on 4/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2014 | FARUK SEZER |
| Corrections Issued | 5/7/2014 | FARUK SEZER |
| Quality Review Completed | 5/7/2014 | TAMERA SVETICH |
| Applicant returned to address corrections | 12/16/2014 | FARUK SEZER |
| Applicant returned to address corrections | 1/9/2015 | FARUK SEZER |
| Applicant returned to address corrections | 3/10/2015 | FARUK SEZER |
| Applicant returned to address corrections | 3/23/2015 | FARUK SEZER |
| Plan Check Approved | 3/27/2015 | FARUK SEZER |
| Issued | 6/2/2015 | LADBS |
| Permit Expired-Status Void | 6/26/2017 | APPLICANT |
| Re-Activate Permit | 8/22/2017 | DOMINIC DANERI |
| Permit Finaled-Status Void | 4/1/2022 | OSVALDO PARAMO |
| Re-Activate Permit | 4/21/2022 | OSVALDO PARAMO |
| Permit Finaled | 4/21/2022 | OSVALDO PARAMO |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/13/2014 | VALENTINO PUEBLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2014 | VALENTINO PUEBLOS |
| Sewer availability | Cleared | 5/13/2014 | VALENTINO PUEBLOS |
| Work Adjacent to Public Way | Cleared | 5/13/2014 | TERRY PHAN |
| Green Code | Cleared | 12/5/2014 | ROLLIN GETTLE III |
| Grading Pre-Inspection | Cleared | 12/16/2014 | FARUK SEZER |
| Low Impact Development | Cleared | 3/4/2015 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 3/4/2015 | JOSHUA LOPEZ |
| Specific Plan | Cleared | 3/13/2015 | MINDY NGUYEN |
Contact Information
| Engineer | Khoury, Nader Bulos; Lic. No.: C61402 | 3406 LINDA VISTA TER FALLBROOK, CA 92028 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/17/2015 | Corrections Issued | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 12/23/2015 | Not Ready for Inspection | RONALD COWAN |
| Footing/Foundation/Slab | 3/16/2017 | Not Ready for Inspection | LUIS ALVAREZ |
| Pre-Inspection | 3/16/2017 | Approved | LUIS ALVAREZ |
| Pre-Inspection | 3/13/2019 | Partial Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 4/11/2019 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/21/2021 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 9/21/2021 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 9/21/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/4/2021 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 10/4/2021 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/4/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/5/2021 | Partial Approval | OSVALDO PARAMO |
| Insulation | 10/8/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 10/15/2021 | Approved | OSVALDO PARAMO |
| Shower Pan | 12/10/2021 | Approved | OSVALDO PARAMO |
| Final | 4/1/2022 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/1/2022 | Approved | OSVALDO PARAMO |
| Green Building Final | 4/1/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 4/1/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 4/1/2022 | Approved | OSVALDO PARAMO |
| Final | 4/21/2022 | Permit Finaled | OSVALDO PARAMO |
| Service/Power Release | 4/21/2022 | Approved | OSVALDO PARAMO |