11507 W ORUM ROAD 90049

Certificate Information: 11507 W ORUM ROAD 90049

Application / Permit
14014-10000-01698
Plan Check / Job No.
B14LA05345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE NEW SECOND FLOOR ADDITION AND MAJOR REMODLE OVER (E) ONE STORY SFD W/ ATT GARAGE_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D
Permit Issued
Issued on 1/16/2015
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2018
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2014 APPLICANT
Assigned to Plan Check Engineer 5/15/2014 DAWN MC NULTY
Corrections Issued 6/3/2014 DAWN MC NULTY
Quality Review Completed 6/5/2014 GARO TELMI
Building Plans Picked Up 7/2/2014 APPLICANT
Green Plans Picked Up 7/2/2014 APPLICANT
Applicant returned to address corrections 8/19/2014 DAWN MC NULTY
Applicant returned to address corrections 9/4/2014 DAWN MC NULTY
Applicant returned to address corrections 9/22/2014 DAWN MC NULTY
Plan Check Approved 11/17/2014 DAWN MCNULTY
Issued 1/16/2015 LADBS
CofO in Progress 8/25/2018 CHRISTOPHER WILSON
Permit Finaled 9/5/2018 DANIEL ORRANTE
CofO Issued 9/5/2018 DANIEL ORRANTE
Permit Finaled 9/5/2018 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/7/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 7/7/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 7/7/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 7/7/2014 RICHARD SOUTHERLAND
Distance to fire station Cleared 7/7/2014 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 7/7/2014 RICHARD SOUTHERLAND
Permit Cleared 7/7/2014 RICHARD SOUTHERLAND
Sewer availability Cleared 7/7/2014 RICHARD SOUTHERLAND
Frnt yard landscape/Water mgmt Cleared 8/5/2014 EMMANUELA GUTIERREZ
Grading Pre-Inspection Cleared 8/19/2014 DAWN MCNULTY
Mailing Labels Cleared 8/19/2014 DAWN MCNULTY
Green Code Cleared 8/21/2014 MARTHA DIAZ
BHO/Hillside ordinance Cleared 9/4/2014 RICHARD SOUTHERLAND
Low Impact Development Cleared 11/14/2014 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/14/2014 RICHARD SOUTHERLAND
Miscellaneous Cleared 11/17/2014 DAWN MCNULTY

Contact Information

Architect Harouni, Faradj-Ollah; Lic. No.: C13577 6334 WILSHIRE BLVD      LOS ANGELES, CA 90048
Contractor J C A Construction Company; Lic. No.: 940685-B 8665 WILSHIRE BLVD      BEVERLY HILLS, CA 90211
Engineer Berkoz, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Salehipour, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

CARLOS MATAMOROS, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2015 Approved DANIEL ORRANTE
Footing/Foundation/Slab 1/27/2016 Partial Approval DANIEL ORRANTE
Deputy Reinf. Concrete 2/8/2016 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 2/11/2016 Partial Approval DANIEL ORRANTE
Footing/Foundation/Slab 2/17/2016 Not Ready for Inspection DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 2/18/2016 Partial Inspection DANIEL ORRANTE
Deputy Steel/Welding 2/24/2016 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 2/26/2016 Approved DANIEL ORRANTE
Footing/Foundation/Slab 2/26/2016 Partial Approval DANIEL ORRANTE
Deputy Reinf. Concrete 2/29/2016 Approved DANIEL ORRANTE
Deputy Reinf. Concrete 3/18/2016 Approved DANIEL ORRANTE
Footing/Foundation/Slab 3/31/2016 Partial Approval DAVID JAMES
Excavation/Setback/Form/Re-Bar 4/4/2016 Approved DANIEL ORRANTE
Footing/Foundation/Slab 4/4/2016 Approved DANIEL ORRANTE
Masonry Wall/Backfill 4/6/2016 Not Ready for Inspection DANIEL ORRANTE
Sewer 4/6/2016 Approved DANIEL ORRANTE
Underground Mechanical 4/6/2016 Approved DANIEL ORRANTE
Sewer 4/18/2016 Approved DANIEL ORRANTE
Underground Mechanical 4/18/2016 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 4/20/2016 Approved DANIEL ORRANTE
Deputy Reinf. Concrete 4/22/2016 Approved DANIEL ORRANTE
ELECTRICAL-Rough 4/22/2016 Partial Approval DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 4/22/2016 Approved DANIEL ORRANTE
Piling/Pier/Caisson 4/29/2016 Approved DANIEL ORRANTE
Deputy Steel/Welding 5/16/2016 Approved DANIEL ORRANTE
ELECTRICAL-Rough 5/16/2016 Partial Approval DANIEL ORRANTE
HVAC-Rough 5/16/2016 Partial Approval DANIEL ORRANTE
PLUMBING-Rough 5/16/2016 Partial Approval DANIEL ORRANTE
Deputy Steel/Welding 5/18/2016 Approved JOHN LUMB
Deputy Steel/Welding 5/23/2016 Conditional Approval DANIEL ORRANTE
Deputy Steel/Welding 6/17/2016 Conditional Approval DANIEL ORRANTE
Deputy Wood Construction 6/23/2016 Conditional Approval DANIEL ORRANTE
Wood Frame 6/24/2016 Approved DANIEL ORRANTE
Deputy Wood Construction 8/11/2016 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/12/2016 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/3/2016 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/3/2016 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 10/3/2016 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 10/3/2016 Not Ready for Inspection THOMAS FINNILA
Deputy Steel/Welding 10/25/2016 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 12/8/2016 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 12/20/2016 Not Ready for Inspection THOMAS FINNILA
Wood Frame 12/20/2016 Partial Inspection THOMAS FINNILA
Wood Frame 1/11/2017 Partial Inspection THOMAS FINNILA
Wood Frame 1/31/2017 Partial Approval THOMAS FINNILA
PLUMBING-Rough 2/1/2017 Partial Inspection THOMAS FINNILA
Wood Frame 2/1/2017 Partial Approval THOMAS FINNILA
PLUMBING-Rough 2/10/2017 Approved THOMAS FINNILA
Wood Frame 2/10/2017 Partial Approval THOMAS FINNILA
HVAC-Rough 2/21/2017 Partial Inspection THOMAS FINNILA
Shower Pan 2/21/2017 Not Ready for Inspection CHRISTOPHER WILSON
Sewer 3/13/2017 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/20/2017 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/20/2017 Partial Approval CHRISTOPHER WILSON
Shower Pan 3/20/2017 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/21/2017 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/21/2017 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/23/2017 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/24/2017 Partial Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/24/2017 Partial Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 3/28/2017 Partial Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 3/30/2017 Partial Approval DANIEL ORRANTE
Rough-Elec/Plmb/HVAC 4/5/2017 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 4/10/2017 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 4/17/2017 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 4/26/2017 Partial Approval CHRISTOPHER WILSON
Insulation 5/1/2017 Partial Approval CRAIG DAVIS
Insulation 5/3/2017 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 5/11/2017 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 5/16/2017 Partial Inspection THOMAS FINNILA
HVAC-Rough 5/16/2017 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/19/2017 Partial Approval THOMAS FINNILA
HVAC-Rough 5/19/2017 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/24/2017 No Access for Inspection THOMAS FINNILA
Interior/Exterior Lathing 5/26/2017 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/1/2017 Partial Approval THOMAS FINNILA
Green Building Rough 6/1/2017 Partial Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 6/1/2017 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/5/2017 Partial Approval THOMAS FINNILA
Green Building Rough 6/5/2017 Partial Approval THOMAS FINNILA
Insulation 6/9/2017 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/16/2017 No Access for Inspection THOMAS FINNILA
Green Building Rough 6/16/2017 No Access for Inspection THOMAS FINNILA
Interior/Exterior Lathing 6/19/2017 Partial Approval THOMAS FINNILA
Wood Frame 6/19/2017 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/22/2017 Partial Approval THOMAS FINNILA
Green Building Rough 6/22/2017 Approved THOMAS FINNILA
Drywall Nailing 6/28/2017 Partial Approval THOMAS FINNILA
Insulation 7/3/2017 Approved THOMAS FINNILA
Drywall Nailing 7/18/2017 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 7/26/2017 Partial Approval THOMAS FINNILA
Special/Order Compliance 8/19/2017 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 9/7/2017 Partial Approval THOMAS FINNILA
Special/Order Compliance 9/7/2017 Partial Inspection CHRISTOPHER WILSON
Insulation 9/12/2017 Approved THOMAS FINNILA
Drywall Nailing 10/24/2017 Partial Approval THOMAS FINNILA
Drywall Nailing 11/17/2017 Approved THOMAS FINNILA
Service/Power Release 2/23/2018 Partial Inspection JOEL LAUNCHBAUGH
Service/Power Release 2/27/2018 Partial Inspection CHRISTOPHER WILSON
Service/Power Release 3/6/2018 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/8/2018 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/28/2018 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/27/2018 Partial Approval CHRISTOPHER WILSON
PLUMBING-Final 5/17/2018 Corrections Issued RYAN MCGILL
Gas Test 5/21/2018 Partial Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/21/2018 SGSOV Approved CHRISTOPHER WILSON
Enclosure/Fence 5/25/2018 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 6/4/2018 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Final 6/4/2018 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/18/2018 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 6/18/2018 Approved CHRISTOPHER WILSON
Final 6/18/2018 Partial Inspection CHRISTOPHER WILSON
Green Building Final 6/18/2018 Partial Inspection CHRISTOPHER WILSON
HVAC-Final 6/18/2018 Approved CHRISTOPHER WILSON
Smoke Detectors 6/18/2018 Approved CHRISTOPHER WILSON
Final 7/24/2018 Partial Inspection CHRISTOPHER WILSON
Green Building Final 7/24/2018 Partial Inspection CHRISTOPHER WILSON
Final 7/27/2018 Corrections Issued CHRISTOPHER WILSON
Green Building Final 7/27/2018 Corrections Issued CHRISTOPHER WILSON
Final 8/2/2018 Conditional Approval CHRISTOPHER WILSON
Green Building Final 8/2/2018 Approved CHRISTOPHER WILSON