1100 S BROADWAY 90015

Certificate Information: 1100 S BROADWAY 90015

Application / Permit
14014-10000-01277
Plan Check / Job No.
B14LA04122
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
CHANGE OF USE FROM (E) CLUB BUILDING TO HOTEL W/ 148 GUEST ROOMS. (N) RESTAURANTS ON THE 1ST FLOOR AND ROOF. (N) ROOF DECK WITH SPA AND MECH. ROOM. REDUCE SIZE OF (E) SWIMMING POOL ON 7TH FLOOR. **VOLUNTARY SEISMIC UPGRADE ONLY**
Permit Issued
Issued on 8/28/2015
Issuing Office
Metro
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2014 APPLICANT
Assigned to Plan Check Engineer 4/17/2014 HOK CHI CHIU
Corrections Issued 5/20/2014 HOK CHI CHIU
Quality Review Completed 5/28/2014 BILL STUTSMAN
Building Plans Picked Up 5/29/2014 APPLICANT
Applicant returned to address corrections 6/11/2014 HOK CHI CHIU
Applicant returned to address corrections 7/8/2014 HOK CHI CHIU
Applicant returned to address corrections 7/14/2014 HOK CHI CHIU
Applicant returned to address corrections 10/29/2014 HOK CHI CHIU
Applicant returned to address corrections 11/5/2014 HOK CHI CHIU
Applicant returned to address corrections 11/13/2014 HOK CHI CHIU
Applicant returned to address corrections 12/12/2014 HOK CHI CHIU
Applicant returned to address corrections 12/16/2014 HOK CHI CHIU
Applicant returned to address corrections 3/12/2015 EUGENE BARBEAU
Applicant returned to address corrections 7/30/2015 EUGENE BARBEAU
Plan Check Approved 8/25/2015 EUGENE BARBEAU
Issued 8/28/2015 LADBS
TCO Issued (Expire Date: 04-10-2022) 10/12/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 10-01-2022) 4/4/2022 ERNESTO CORRAL
TCO Issued (Expire Date: 04-01-2023) 10/3/2022 ERNESTO CORRAL
TCO Issued (Expire Date: 09-30-2023) 4/3/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 03-19-2024) 9/21/2023 ERNESTO CORRAL
CofO Issued 4/23/2024 ERNESTO CORRAL
Permit Finaled 4/23/2024 ERNESTO CORRAL

Permit Application Clearance Information

Encroachment in public way Cleared 9/8/2014 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 9/8/2014 RICHARD SOUTHERLAND
Highway dedication Cleared 9/8/2014 RICHARD SOUTHERLAND
DAS Clearance Cleared 7/6/2015 HOK CHI CHIU
Green Code Cleared 7/7/2015 MARCUS LEVIAS
Hydrant and Access approval Cleared 7/7/2015 JOHN CONNEALLY
Fire Marshall Fire Life Safety Cleared 7/10/2015 DAVE MYERS
City Hist. Cultural Monument Cleared 7/13/2015 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 7/13/2015 LAMBERT GIESSINGER
Historic monument Cleared 7/13/2015 LAMBERT GIESSINGER
Miscellaneous Cleared 7/13/2015 LAMBERT GIESSINGER
Historical monument Cleared 7/15/2015 JIM URQUHART
Project located in CRA area Cleared 7/15/2015 JIM URQUHART
"D" conditions Cleared 7/16/2015 HERMAN VAN BUREN
ZA Case Cleared 7/22/2015 ROXANNE WILES
Sewer availability Cleared 7/23/2015 ARNULFO NUNO
Address approval Cleared 7/30/2015 ARNULFO NUNO
Building over 3-story or 36-ft Cleared 7/30/2015 CALOSHA APPROVED
Food establishment approval Cleared 7/30/2015 LACDHS APPROVED
Public Swimming Pool approval Cleared 7/30/2015 LACDHS APPROVED
Food Service Establishment Cleared 7/31/2015 MICHAEL SCADUTO
Low Impact Development Cleared 7/31/2015 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 7/31/2015 JAMES KHO
Residential hotels Cleared 8/20/2015 MARITES CUNANAN
CMU Activity Summary Cleared 8/25/2015 HOK CHI CHIU

Contact Information

Architect Liljegren, Karin J; Lic. No.: C28158 727 W 7TH STREET # 610      LOS ANGELES, CA 90017
Contractor Hopkins George C Construction Co Inc; Lic. No.: 397266-B 919 W GLENOAKS BLVD      GLENDALE, CA 91202
Engineer Cazeneuve, Michael Allan; Lic. No.: C71490 235 E FOOTHILLL BL J      MONROVIA, CA 91016
Engineer Rezaian, Reza; Lic. No.: C62048 3665 MOUNTAIN VIEW AVENUE      LOS ANGELES, CA 90066
Engineer Youssef, Nabih Fouad Guirg; Lic. No.: S2026 550 S HOPE ST SUITE 1700      LOS ANGELES, CA 90017

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/18/2016 Approved SAKO AGHAZARIAN
Pre-Inspection 8/8/2016 Partial Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 1/31/2017 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 2/27/2017 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/27/2017 Conditional Approval LESLIE TRUJILLO
Special/Order Compliance 8/16/2017 Partial Inspection NICK DANERI
Deputy Drilled-In Anchors 3/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 3/13/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/13/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/14/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/14/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/15/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/15/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 3/16/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/16/2018 Conditional Approval NICK DANERI
Deputy Fireproofing 11/20/2018 Conditional Approval NICK DANERI
Deputy Fireproofing 11/21/2018 Conditional Approval NICK DANERI
Drywall Nailing 5/18/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/4/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/4/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/2/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/17/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/17/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/22/2021 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 3/31/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/5/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2021 Partial Approval JAMES POWERS
T-Bar Ceiling 4/7/2021 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 4/13/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/13/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/14/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/14/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/15/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/15/2021 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 4/16/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/16/2021 Partial Approval JAMES POWERS
Final 5/5/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 5/5/2021 Approved JAMES POWERS
Green Building Final 5/5/2021 Approved JAMES POWERS
Green Building Rough 5/5/2021 Approved JAMES POWERS
METHANE-Barrier 5/5/2021 Approved JAMES POWERS
METHANE-Final 5/5/2021 Approved JAMES POWERS
METHANE-Rough 5/5/2021 Approved JAMES POWERS
METHANE-Subgrade 5/5/2021 Approved JAMES POWERS
Reinforced Concrete Frame 5/5/2021 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 5/5/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 5/5/2021 Approved JAMES POWERS
Final 5/24/2021 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Not Ready JAMES POWERS
Deputy Drilled-In Anchors 5/25/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/25/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/26/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/26/2021 Partial Approval JAMES POWERS
Pre-Inspection 5/26/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/27/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/27/2021 Partial Approval JAMES POWERS
Pre-Inspection 6/1/2021 Partial Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved JAMES POWERS
Light Gage Steel Frame 7/2/2021 Not Ready for Inspection JAMES POWERS
Final 9/15/2021 OK for TCO JAMES POWERS
Special/Order Compliance 3/16/2022 Partial Approval JAMES POWERS
Special/Order Compliance 9/13/2022 Conditional Approval NICK DANERI
Special/Order Compliance 3/9/2023 Conditional Approval NICK DANERI
Special/Order Compliance 9/6/2023 Conditional Approval NICK DANERI
Special/Order Compliance 2/28/2024 Conditional Approval NICK DANERI