1243 N SUNSET PLAZA DR 90069
Certificate Information: 1243 N SUNSET PLAZA DR 90069
- Application / Permit
- 14010-30002-03519
- Plan Check / Job No.
- B16WL06248
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- supplemental ref to pcis # 14010-30000-03519, to add to the 1st floor and garage level
- Permit Issued
- Issued on 5/1/2017
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/1/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/29/2016 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2016 | MARJAN SHENASI |
| Corrections Issued | 12/15/2016 | MARJAN SHENASI |
| Quality Review Completed | 12/20/2016 | STEVEN KIM |
| Green Plans Picked Up | 12/20/2016 | APPLICANT |
| Building Plans Picked Up | 12/21/2016 | APPLICANT |
| Applicant returned to address corrections | 1/30/2017 | MARJAN SHENASI |
| Applicant returned to address corrections | 2/13/2017 | MARJAN SHENASI |
| Applicant returned to address corrections | 2/27/2017 | MARJAN SHENASI |
| Plan Check Approved | 5/1/2017 | MARJAN SHENASI |
| Issued | 5/1/2017 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 1/27/2017 | BRYAN MEYER |
| Excavation more than 5-ft deep | Cleared | 1/30/2017 | CALOSHA APPROVED |
Contact Information
| Architect | Khoudikian, Kaaren G; Lic. No.: C13183 | 221 E GLENOAKS BLVD # 230 GLENDALE, CA 91207 |
| Contractor | Madison Medical Construction Corp; Lic. No.: 941838-B | 5737 KANAN ROAD #200 AGOURA HILLS, CA 91301 |
| Engineer | Abrahamian, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Khanjian, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
| Engineer | Zlotnik, Alexander; Lic. No.: C69417 | 18521 MAYALL SR #A NORTHRIDGE, CA 91324 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/19/2017 | No Access for Inspection | BRAD BESCOS |
| Deputy Reinf. Concrete | 6/20/2017 | Conditional Approval | DAVID CHAN |
| ELECTRICAL-Rough | 6/17/2019 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 6/17/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 6/17/2019 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 6/17/2019 | Partial Approval | DANNY TOLENTINO |
| Deputy Reinf. Concrete | 6/20/2019 | Conditional Approval | DANNY TOLENTINO |