6944 S KNOWLTON PL 90045

Certificate Information: 6944 S KNOWLTON PL 90045

Application / Permit
14010-30000-04177
Plan Check / Job No.
B14WL05958
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4- story with 36 units apartment building, including 3 low income units with first floor attched garage.
Permit Issued
Issued on 9/1/2016
Issuing Office
Valley
Current Status
CofO Issued on 1/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2014 APPLICANT
Assigned to Plan Check Engineer 2/5/2015 RODNEY SAMIIAN
Corrections Issued 2/18/2015 RODNEY SAMIIAN
Green Plans Picked Up 2/24/2015 APPLICANT
Quality Review Completed 2/25/2015 DOUGLAS NAKATANI
Building Plans Picked Up 3/6/2015 APPLICANT
Applicant returned to address corrections 5/7/2015 RODNEY SAMIIAN
Applicant returned to address corrections 7/6/2015 RODNEY SAMIIAN
Applicant returned to address corrections 7/15/2015 RODNEY SAMIIAN
Applicant returned to address corrections 10/15/2015 RODNEY SAMIIAN
Applicant returned to address corrections 1/7/2016 RODNEY SAMIIAN
Applicant returned to address corrections 1/15/2016 RODNEY SAMIIAN
Applicant returned to address corrections 1/19/2016 RODNEY SAMIIAN
Applicant returned to address corrections 1/25/2016 RODNEY SAMIIAN
Applicant returned to address corrections 2/23/2016 RODNEY SAMIIAN
Applicant returned to address corrections 3/16/2016 RODNEY SAMIIAN
Applicant returned to address corrections 3/22/2016 RODNEY SAMIIAN
Applicant returned to address corrections 3/31/2016 RODNEY SAMIIAN
Plan Check Approved 9/1/2016 RODNEY SAMIIAN
Issued 9/1/2016 LADBS
TCO Issued (Expire Date: 08-24-2019) 2/25/2019 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 02-20-2020) 8/24/2019 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 08-18-2020) 2/20/2020 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 02-16-2021) 8/20/2020 NICK LAROCCA
CofO in Progress 12/30/2020 NICK LAROCCA
Permit Finaled 1/4/2021 HENRY BAGHDASSARIAN
CofO Issued 1/4/2021 HENRY BAGHDASSARIAN
Permit Finaled 1/4/2021 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 4/7/2015 HOWARD COOPER
Address approval Cleared 4/7/2015 HOWARD COOPER
Grading Pre-Inspection Cleared 5/8/2015 PATRICK MISCHLICH
Housing density bonus Cleared 6/5/2015 REX LEE
Miscellaneous Cleared 6/25/2015 KEVIN AZARMAHAN
Miscellaneous Cleared 6/25/2015 KEVIN AZARMAHAN
Permit Cleared 10/15/2015 KEVIN AZARMAHAN
Stormwater Pollution Mitigatn Cleared 10/15/2015 VIJAY DESAI
DAS Clearance Cleared 12/9/2015 FARUK SEZER
Green Code Cleared 12/10/2015 RUSSELL KELLY
Opn space landscape/Water mgmt Cleared 12/17/2015 DANIEL SKOLNICK
Eng Process Fee Ord 176,300 Cleared 12/30/2015 RICHARD SOUTHERLAND
Sewer availability Cleared 12/30/2015 RICHARD SOUTHERLAND
Building over 3-story or 36-ft Cleared 1/7/2016 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 1/7/2016 RICK TORRES
GPI Written Notices Cleared 1/7/2016 RODNEY SAMIIAN
Tract Map conditions Cleared 1/7/2016 RICK TORRES
Roof/Waste drainage to street Cleared 1/14/2016 ANGEL SALCEDO
Hydrant and Access approval Cleared 1/20/2016 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 1/27/2016 SUSIE ADAMIAN
Specific Plan Cleared 3/1/2016 CLIVE GRAWE
Construction within easement Cleared 3/7/2016 LUCIO FERRER

Contact Information

Contractor Burrell Builders; Lic. No.: 1009680-B 927 NOVARRO ST      WEST COVINA, CA 91791
Engineer Javadvesian, Hrach; Lic. No.: C42319 411 N CENTRAL 605      GLENDALE, CA 91203
Engineer Rybak, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/8/2016 Partial Inspection NICK LAROCCA
Piling/Pier/Caisson 9/12/2016 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 9/23/2016 Approved NICK LAROCCA
Deputy Steel/Welding 9/29/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 9/29/2016 Partial Approval NICK LAROCCA
METHANE-Barrier 9/29/2016 Approved NICK LAROCCA
METHANE-Subgrade 9/29/2016 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/7/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 11/7/2016 Partial Approval NICK LAROCCA
Masonry Wall/Backfill 11/16/2016 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 1/4/2017 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 1/6/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 1/17/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 1/17/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 1/30/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 2/1/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 2/9/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 2/10/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 2/15/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/23/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/24/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/28/2017 Approved NICK LAROCCA
Masonry Wall/Backfill 2/28/2017 Partial Inspection NICK LAROCCA
Deputy Reinf. Masonry 3/1/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/2/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/6/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/8/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/9/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/10/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/13/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/14/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/15/2017 Approved NICK LAROCCA
Masonry Wall/Backfill 3/15/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 3/16/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/20/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 3/20/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 3/23/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 3/23/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 3/29/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 3/29/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 4/4/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 4/4/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 4/18/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 4/19/2017 Approved NICK LAROCCA
Masonry Wall/Backfill 4/19/2017 Partial Inspection NICK LAROCCA
Footing/Foundation/Slab 5/11/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 6/6/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 6/7/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 6/13/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 6/14/2017 Partial Inspection NICK LAROCCA
Deputy Reinf. Masonry 6/15/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 6/16/2017 Approved NICK LAROCCA
Masonry Wall/Backfill 6/16/2017 Not Ready for Inspection NICK LAROCCA
Deputy Reinf. Masonry 6/19/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 6/29/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 6/29/2017 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 7/11/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/1/2017 Partial Approval NICK LAROCCA
Deputy Steel/Welding 8/8/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 8/10/2017 Partial Approval JONATHAN ALLEN
Deputy Reinf. Concrete 8/11/2017 Approved NICK LAROCCA
Deputy Drilled-In Anchors 8/21/2017 Approved DERRICK SPENCER
Deputy Steel/Welding 8/21/2017 Approved DERRICK SPENCER
Deputy Wood Construction 8/29/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/29/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 9/1/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 9/1/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 9/7/2017 Approved NICK LAROCCA
Footing/Foundation/Slab 9/8/2017 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 9/11/2017 Approved NICK LAROCCA
Deputy Steel/Welding 9/14/2017 Approved NICK LAROCCA
Deputy Steel/Welding 9/19/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/19/2017 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/20/2017 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 9/20/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/10/2017 Approved DERRICK SPENCER
Deputy Wood Construction 10/11/2017 Approved NICK LAROCCA
Deputy Wood Construction 10/13/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/13/2017 Partial Approval NICK LAROCCA
Deputy Steel/Welding 10/17/2017 Approved NICK LAROCCA
Deputy Steel/Welding 10/20/2017 Approved NICK LAROCCA
Deputy Wood Construction 10/31/2017 Partial Approval ALAN NOVAK
Floor/Roof Diaphrgm/Shear Wall 11/1/2017 Partial Approval NICK LAROCCA
Deputy Steel/Welding 11/28/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 12/8/2017 Partial Approval DERRICK SPENCER
Deputy Wood Construction 12/11/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 12/12/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 12/14/2017 Partial Approval NICK LAROCCA
Deputy Wood Construction 12/21/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 12/22/2017 Partial Approval JONATHAN ALLEN
Floor/Roof Diaphrgm/Shear Wall 1/2/2018 Corrections Issued NICK LAROCCA
Insulation 1/17/2018 Partial Approval JONATHAN ALLEN
Insulation 1/30/2018 Not Ready for Inspection NICK LAROCCA
Insulation 2/2/2018 Partial Approval NICK LAROCCA
Deputy Wood Construction 2/8/2018 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 2/13/2018 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 2/21/2018 Partial Inspection NICK LAROCCA
Insulation 2/21/2018 Not Ready for Inspection NICK LAROCCA
Drywall Nailing 2/26/2018 Partial Approval NICK LAROCCA
Green Building Rough 2/26/2018 Approved NICK LAROCCA
Insulation 2/26/2018 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 3/5/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/13/2018 Partial Approval NICK LAROCCA
Insulation 3/15/2018 Partial Approval NICK LAROCCA
Wood Frame 3/15/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/19/2018 Not Ready for Inspection TONY HARTONO
Insulation 3/19/2018 Not Ready for Inspection TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 3/20/2018 Partial Approval NICK LAROCCA
Insulation 3/20/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/22/2018 Partial Approval NICK LAROCCA
Insulation 3/22/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/28/2018 Not Ready for Inspection DAVID TSAU
Insulation 3/28/2018 Not Ready for Inspection DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 3/29/2018 Partial Approval NICK LAROCCA
Insulation 3/29/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 3/30/2018 Partial Inspection NICK LAROCCA
Insulation 3/30/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/4/2018 Partial Approval NICK LAROCCA
Insulation 4/4/2018 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/6/2018 Partial Approval NICK LAROCCA
Insulation 4/6/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/12/2018 Not Ready for Inspection NICK LAROCCA
Insulation 4/12/2018 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/13/2018 Partial Inspection NICK LAROCCA
Insulation 4/13/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 4/17/2018 Approved NICK LAROCCA
Insulation 4/17/2018 Partial Approval NICK LAROCCA
Drywall Nailing 4/20/2018 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 4/30/2018 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 5/4/2018 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 5/8/2018 Approved NICK LAROCCA
Drywall Nailing 6/6/2018 Approved NICK LAROCCA
Insulation 7/10/2018 Approved NICK LAROCCA
Insulation 7/16/2018 Approved NICK LAROCCA
Interior/Exterior Lathing 8/27/2018 Not Ready for Inspection NICK LAROCCA
Final 8/30/2018 Corrections Issued NICK LAROCCA
Green Building Final 8/30/2018 Not Ready for Inspection NICK LAROCCA
METHANE-Final 8/30/2018 Approved NICK LAROCCA
METHANE-Rough 8/30/2018 Approved NICK LAROCCA
Reinforced Masonry Frame 8/30/2018 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 8/30/2018 SGSOV Approved NICK LAROCCA
Smoke Detectors 8/30/2018 Approved NICK LAROCCA
Structural Steel Frame 8/30/2018 Approved NICK LAROCCA
Verify Sprinkler Sign Off 8/30/2018 Approved NICK LAROCCA
Wood Frame 8/30/2018 Approved NICK LAROCCA
Final 10/3/2018 Not Ready for Inspection DERRICK SPENCER
Green Building Final 10/3/2018 Not Ready for Inspection DERRICK SPENCER
Final 10/10/2018 Not Ready for Inspection DERRICK SPENCER
Green Building Final 10/10/2018 Not Ready for Inspection DERRICK SPENCER
Final 10/15/2018 Partial Inspection NICK LAROCCA
Green Building Final 10/15/2018 Not Ready for Inspection NICK LAROCCA
Light Gage Steel Frame 10/25/2018 Partial Inspection NICK LAROCCA
Final 12/7/2018 Corrections Issued NICK LAROCCA
Green Building Final 12/7/2018 Not Ready for Inspection NICK LAROCCA
Final 12/14/2018 Not Ready for Inspection NICK LAROCCA
Green Building Final 12/14/2018 Approved NICK LAROCCA
Final 1/10/2019 Corrections Issued NICK LAROCCA
Final 1/30/2019 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 2/6/2019 Approved NICK LAROCCA
Final 2/19/2019 Partial Inspection NICK LAROCCA
Special/Order Compliance 7/31/2019 Approved DERRICK SPENCER
Special/Order Compliance 1/24/2020 Approved NICK LAROCCA
Special/Order Compliance 7/22/2020 Approved NICK LAROCCA
Final 12/29/2020 OK to Issue CofO NICK LAROCCA