Piling/Pier/Caisson
|
9/8/2016
|
Partial Inspection
|
NICK LAROCCA
|
Piling/Pier/Caisson
|
9/12/2016
|
Partial Approval
|
DERRICK SPENCER
|
Deputy Reinf. Concrete
|
9/23/2016
|
Approved
|
NICK LAROCCA
|
Deputy Steel/Welding
|
9/29/2016
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
9/29/2016
|
Partial Approval
|
NICK LAROCCA
|
METHANE-Barrier
|
9/29/2016
|
Approved
|
NICK LAROCCA
|
METHANE-Subgrade
|
9/29/2016
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
11/7/2016
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
11/7/2016
|
Partial Approval
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
11/16/2016
|
Partial Approval
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
1/4/2017
|
Partial Approval
|
DERRICK SPENCER
|
Footing/Foundation/Slab
|
1/6/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
1/17/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
1/17/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
1/30/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
2/1/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
2/9/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
2/10/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
2/15/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
2/23/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
2/24/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
2/28/2017
|
Approved
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
2/28/2017
|
Partial Inspection
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/1/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/2/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/6/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/8/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/9/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/10/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/13/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/14/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/15/2017
|
Approved
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
3/15/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
3/16/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
3/20/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
3/20/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
3/23/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
3/23/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
3/29/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
3/29/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
4/4/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
4/4/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
4/18/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
4/19/2017
|
Approved
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
4/19/2017
|
Partial Inspection
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
5/11/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/6/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/7/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/13/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
6/14/2017
|
Partial Inspection
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/15/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/16/2017
|
Approved
|
NICK LAROCCA
|
Masonry Wall/Backfill
|
6/16/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Deputy Reinf. Masonry
|
6/19/2017
|
Approved
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
6/29/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
6/29/2017
|
Partial Approval
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
7/11/2017
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/1/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Steel/Welding
|
8/8/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
8/10/2017
|
Partial Approval
|
JONATHAN ALLEN
|
Deputy Reinf. Concrete
|
8/11/2017
|
Approved
|
NICK LAROCCA
|
Deputy Drilled-In Anchors
|
8/21/2017
|
Approved
|
DERRICK SPENCER
|
Deputy Steel/Welding
|
8/21/2017
|
Approved
|
DERRICK SPENCER
|
Deputy Wood Construction
|
8/29/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/29/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
9/1/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
9/1/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
9/7/2017
|
Approved
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
9/8/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Reinf. Concrete
|
9/11/2017
|
Approved
|
NICK LAROCCA
|
Deputy Steel/Welding
|
9/14/2017
|
Approved
|
NICK LAROCCA
|
Deputy Steel/Welding
|
9/19/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/19/2017
|
Not Ready for Inspection
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/20/2017
|
Partial Approval
|
NICK LAROCCA
|
Footing/Foundation/Slab
|
9/20/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/10/2017
|
Approved
|
DERRICK SPENCER
|
Deputy Wood Construction
|
10/11/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/13/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
10/13/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Steel/Welding
|
10/17/2017
|
Approved
|
NICK LAROCCA
|
Deputy Steel/Welding
|
10/20/2017
|
Approved
|
NICK LAROCCA
|
Deputy Wood Construction
|
10/31/2017
|
Partial Approval
|
ALAN NOVAK
|
Floor/Roof Diaphrgm/Shear Wall
|
11/1/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Steel/Welding
|
11/28/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2017
|
Partial Approval
|
DERRICK SPENCER
|
Deputy Wood Construction
|
12/11/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2017
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2017
|
Partial Approval
|
NICK LAROCCA
|
Deputy Wood Construction
|
12/21/2017
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/22/2017
|
Partial Approval
|
JONATHAN ALLEN
|
Floor/Roof Diaphrgm/Shear Wall
|
1/2/2018
|
Corrections Issued
|
NICK LAROCCA
|
Insulation
|
1/17/2018
|
Partial Approval
|
JONATHAN ALLEN
|
Insulation
|
1/30/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Insulation
|
2/2/2018
|
Partial Approval
|
NICK LAROCCA
|
Deputy Wood Construction
|
2/8/2018
|
Approved
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
2/13/2018
|
Partial Inspection
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
2/21/2018
|
Partial Inspection
|
NICK LAROCCA
|
Insulation
|
2/21/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Drywall Nailing
|
2/26/2018
|
Partial Approval
|
NICK LAROCCA
|
Green Building Rough
|
2/26/2018
|
Approved
|
NICK LAROCCA
|
Insulation
|
2/26/2018
|
Partial Approval
|
NICK LAROCCA
|
Interior/Exterior Lathing
|
3/5/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/13/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
3/15/2018
|
Partial Approval
|
NICK LAROCCA
|
Wood Frame
|
3/15/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2018
|
Not Ready for Inspection
|
TONY HARTONO
|
Insulation
|
3/19/2018
|
Not Ready for Inspection
|
TONY HARTONO
|
Floor/Roof Diaphrgm/Shear Wall
|
3/20/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
3/20/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/22/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
3/22/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/28/2018
|
Not Ready for Inspection
|
DAVID TSAU
|
Insulation
|
3/28/2018
|
Not Ready for Inspection
|
DAVID TSAU
|
Floor/Roof Diaphrgm/Shear Wall
|
3/29/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
3/29/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
3/30/2018
|
Partial Inspection
|
NICK LAROCCA
|
Insulation
|
3/30/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
4/4/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
4/4/2018
|
Partial Inspection
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2018
|
Partial Approval
|
NICK LAROCCA
|
Insulation
|
4/6/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Insulation
|
4/12/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2018
|
Partial Inspection
|
NICK LAROCCA
|
Insulation
|
4/13/2018
|
Partial Approval
|
NICK LAROCCA
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2018
|
Approved
|
NICK LAROCCA
|
Insulation
|
4/17/2018
|
Partial Approval
|
NICK LAROCCA
|
Drywall Nailing
|
4/20/2018
|
Partial Approval
|
NICK LAROCCA
|
Interior/Exterior Lathing
|
4/30/2018
|
Partial Approval
|
NICK LAROCCA
|
Reinforced Concrete Frame
|
5/4/2018
|
Partial Approval
|
NICK LAROCCA
|
Interior/Exterior Lathing
|
5/8/2018
|
Approved
|
NICK LAROCCA
|
Drywall Nailing
|
6/6/2018
|
Approved
|
NICK LAROCCA
|
Insulation
|
7/10/2018
|
Approved
|
NICK LAROCCA
|
Insulation
|
7/16/2018
|
Approved
|
NICK LAROCCA
|
Interior/Exterior Lathing
|
8/27/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Final
|
8/30/2018
|
Corrections Issued
|
NICK LAROCCA
|
Green Building Final
|
8/30/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
METHANE-Final
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
METHANE-Rough
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
Reinforced Masonry Frame
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
SGSOV-Seismic Gas S/O Valve
|
8/30/2018
|
SGSOV Approved
|
NICK LAROCCA
|
Smoke Detectors
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
Structural Steel Frame
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
Verify Sprinkler Sign Off
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
Wood Frame
|
8/30/2018
|
Approved
|
NICK LAROCCA
|
Final
|
10/3/2018
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Green Building Final
|
10/3/2018
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Final
|
10/10/2018
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Green Building Final
|
10/10/2018
|
Not Ready for Inspection
|
DERRICK SPENCER
|
Final
|
10/15/2018
|
Partial Inspection
|
NICK LAROCCA
|
Green Building Final
|
10/15/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Light Gage Steel Frame
|
10/25/2018
|
Partial Inspection
|
NICK LAROCCA
|
Final
|
12/7/2018
|
Corrections Issued
|
NICK LAROCCA
|
Green Building Final
|
12/7/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Final
|
12/14/2018
|
Not Ready for Inspection
|
NICK LAROCCA
|
Green Building Final
|
12/14/2018
|
Approved
|
NICK LAROCCA
|
Final
|
1/10/2019
|
Corrections Issued
|
NICK LAROCCA
|
Final
|
1/30/2019
|
Not Ready for Inspection
|
NICK LAROCCA
|
Pre-Inspection
|
2/6/2019
|
Approved
|
NICK LAROCCA
|
Final
|
2/19/2019
|
Partial Inspection
|
NICK LAROCCA
|
Special/Order Compliance
|
7/31/2019
|
Approved
|
DERRICK SPENCER
|
Special/Order Compliance
|
1/24/2020
|
Approved
|
NICK LAROCCA
|
Special/Order Compliance
|
7/22/2020
|
Approved
|
NICK LAROCCA
|
Final
|
12/29/2020
|
OK to Issue CofO
|
NICK LAROCCA
|