823-831 N CROFT AVE 90069

Certificate Information: 823-831 N CROFT AVE 90069

Application / Permit
14010-30000-03159
Plan Check / Job No.
B14WL04335
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New apartment building consisting of 15 units. 4 story with rooftop deck of type III-A on 1 level of subterranean type I-A. THIS PROJECT IS NOT FOR CONDO NOR DENSITY BONUS IS USED.
Permit Issued
Issued on 3/30/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2014 APPLICANT
Assigned to Plan Check Engineer 10/30/2014 CHIHARU SUZUKI
Corrections Issued 11/17/2014 CHIHARU SUZUKI
Quality Review Completed 11/25/2014 ARA SARGSYAN
Building Plans Picked Up 12/17/2014 APPLICANT
Disabled Access Plans Picked Up 12/17/2014 APPLICANT
Green Plans Picked Up 12/17/2014 APPLICANT
Applicant returned to address corrections 9/17/2015 CHIHARU SUZUKI
Applicant returned to address corrections 1/20/2016 CHIHARU SUZUKI
Plan Check Approved 3/24/2016 CHIHARU SUZUKI
Issued 3/30/2016 LADBS
CofO in Progress 10/18/2021 EDWIN GREGORYONA
Permit Finaled 10/22/2021 ERNESTO CORRAL
CofO Issued 10/22/2021 ERNESTO CORRAL
Permit Finaled 10/22/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/24/2015 AVALYN KAMACHI
Eng Process Fee Ord 176,300 Cleared 3/24/2015 AVALYN KAMACHI
Permit Cleared 3/24/2015 AVALYN KAMACHI
Sewer availability Cleared 3/24/2015 AVALYN KAMACHI
Low Impact Development Cleared 4/7/2015 AYMAN JABBOURI
DAS Clearance Cleared 4/23/2015 FARUK SEZER
Green Code Cleared 4/24/2015 RICHARD GARCIA
Work Adjacent to Public Way Cleared 4/24/2015 KELTON KIRBY
Construction near power lines Cleared 7/23/2015 LUCIO FERRER
Hydrant and Access approval Cleared 7/23/2015 ROBERT DUFF
Stormwater Pollution Mitigatn Cleared 7/23/2015 VIJAY DESAI
ZA Case Cleared 8/12/2015 JUSTIN BILOW
ZA Case Cleared 8/12/2015 JUSTIN BILOW
ZA Case Cleared 8/12/2015 JUSTIN BILOW
Building over 3-story or 36-ft Cleared 8/20/2015 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/20/2015 CALOSHA APPROVED
"Q" conditions Cleared 10/14/2015 GABRIELA JUAREZ
CPC Cleared 10/14/2015 GABRIELA JUAREZ
Frnt yard landscape/Water mgmt Cleared 10/14/2015 GABRIELA JUAREZ
Opn space landscape/Water mgmt Cleared 10/14/2015 GABRIELA JUAREZ
ZI Cleared 10/14/2015 GABRIELA JUAREZ
ZI Cleared 10/14/2015 GABRIELA JUAREZ
ZI Cleared 10/14/2015 GABRIELA JUAREZ
Roof/Waste drainage to street Cleared 10/16/2015 VALENTINO PUEBLOS
Fire Marshall Fire Life Safety Cleared 12/10/2015 DAVE MYERS
Hold Cleared 1/6/2017 YAN YAN

Contact Information

Architect Hefner, Charles David; Lic. No.: C23963 28378 ROADSIDE DRIVE      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,
Engineer Dejban, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/30/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 1/31/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/1/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/2/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/3/2017 Conditional Approval GREGORY POMISH
Special/Order Compliance 3/14/2017 Partial Inspection GREGORY POMISH
Special/Order Compliance 4/5/2017 Approved DAVID BURKHEAD
Pre-Inspection 4/27/2017 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 7/25/2017 Approved DAVID BURKHEAD
Special/Order Compliance 10/18/2017 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/2/2017 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 11/3/2017 Corrections Issued GREGORY POMISH
Excavation/Setback/Form/Re-Bar 11/4/2017 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/7/2017 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/9/2017 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/14/2017 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 11/15/2017 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/21/2017 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/22/2017 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 11/27/2017 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/27/2017 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 11/27/2017 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Masonry 12/1/2017 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 12/4/2017 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 12/7/2017 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 12/15/2017 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/20/2017 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 1/8/2018 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/12/2018 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 3/28/2018 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/28/2018 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/29/2018 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 3/29/2018 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 4/2/2018 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 4/10/2018 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/23/2018 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2018 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/9/2018 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/16/2018 Partial Approval DAVID BURKHEAD
Green Building Rough 5/16/2018 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/16/2018 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 5/17/2018 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 5/22/2018 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/28/2018 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 6/28/2018 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/13/2018 Partial Approval DAVID BURKHEAD
Special/Order Compliance 9/7/2018 Approved DAVID BURKHEAD
Footing/Foundation/Slab 10/10/2018 Partial Approval GREGORY POMISH
Drywall Nailing 11/5/2018 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/5/2018 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 11/5/2018 Approved DAVID BURKHEAD
Pre-Inspection 11/5/2018 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 11/7/2018 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 11/7/2018 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 11/8/2018 Partial Inspection DAVID BURKHEAD
Pre-Inspection 11/13/2018 Partial Inspection DAVID BURKHEAD
Pre-Inspection 11/14/2018 Approved DAVID BURKHEAD
Insulation 11/15/2018 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/15/2019 Partial Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/22/2019 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/11/2019 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/11/2019 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 4/29/2019 Partial Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 5/3/2019 Approved DAVID BURKHEAD
Wood Frame 5/3/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 5/7/2019 Partial Inspection DAVID BURKHEAD
Insulation 5/9/2019 Not Ready for Inspection DAVID BURKHEAD
Insulation 5/13/2019 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/15/2019 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/23/2019 Partial Approval DAVID BURKHEAD
Insulation 5/28/2019 Partial Approval FELIX CEBALLOS
Wood Frame 5/31/2019 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 6/7/2019 Partial Approval DAVID BURKHEAD
Insulation 6/7/2019 Partial Approval DAVID BURKHEAD
Wood Frame 6/10/2019 Approved LARRY ARNICK
Insulation 6/17/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 6/18/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 6/25/2019 Not Ready for Inspection DAVID BURKHEAD
Insulation 6/25/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 6/28/2019 Partial Approval FELIX CEBALLOS
Insulation 6/28/2019 Partial Approval FELIX CEBALLOS
Drywall Nailing 7/8/2019 Partial Approval DAVID BURKHEAD
Drywall Nailing 7/11/2019 Approved DAVID BURKHEAD
Interior/Exterior Lathing 8/6/2019 Partial Inspection DAVID BURKHEAD
Interior/Exterior Lathing 8/8/2019 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 8/13/2019 Approved DAVID BURKHEAD
Special/Order Compliance 10/24/2019 Approved DAVID BURKHEAD
Interior/Exterior Lathing 6/15/2020 Not Ready for Inspection JONATHAN QUACH
Green Building Final 12/16/2020 Not Ready for Inspection LARRY ARNICK
Green Building Final 1/25/2021 Not Ready for Inspection LARRY ARNICK
Final 8/6/2021 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 8/6/2021 Approved EDWIN GREGORYONA
Green Building Final 8/6/2021 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 8/6/2021 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 8/6/2021 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 8/6/2021 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 8/6/2021 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 8/6/2021 Approved EDWIN GREGORYONA
Final 9/30/2021 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 9/30/2021 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Not Ready EDWIN GREGORYONA
Final 10/6/2021 Partial Approval EDWIN GREGORYONA
Green Building Final 10/6/2021 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Approved EDWIN GREGORYONA
Final 10/15/2021 Partial Inspection EDWIN GREGORYONA