1200 N BEL-AIR ROAD 90077

Certificate Information: 1200 N BEL-AIR ROAD 90077

Application / Permit
14010-30000-02037
Plan Check / Job No.
B14WL02760
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 4-story single family dwelling with attached garage and carport
Permit Issued
Issued on 12/7/2015
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2014 APPLICANT
Assigned to Plan Check Engineer 7/10/2014 CHRISTINE MAALOUF
Green Plans Picked Up 7/10/2014 APPLICANT
Corrections Issued 7/21/2014 CHRISTINE MAALOUF
Quality Review Completed 7/31/2014 RUDOLF KINAR MELIKOFF
Building Plans Picked Up 7/31/2014 APPLICANT
Applicant returned to address corrections 1/13/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 1/27/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 7/29/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 8/20/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 9/16/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 10/7/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 10/27/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 11/4/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 11/18/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 11/25/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 12/2/2015 CHRISTINE MAALOUF
Plan Check Approved 12/7/2015 CHRISTINE MAALOUF
Issued 12/7/2015 LADBS
CofO in Progress 11/17/2020 CHRISTOPHER WILSON
Permit Finaled 1/5/2021 KENNETH NAGLE
CofO Issued 1/5/2021 KENNETH NAGLE
Permit Finaled 1/5/2021 KENNETH NAGLE

Permit Application Clearance Information

Distance to fire station Cleared 8/6/2014 ROBERT DUFF
Hydrant and Access approval Cleared 8/6/2014 ROBERT DUFF
BHO/Hillside ordinance Cleared 8/12/2014 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/12/2014 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/12/2014 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/12/2014 MARYAM AZARBAYJANI
BHO/Hillside ordinance Cleared 8/12/2014 MARYAM AZARBAYJANI
Permit Cleared 8/12/2014 MARYAM AZARBAYJANI
Eng Process Fee Ord 176,300 Cleared 11/17/2015 JAMES MORALEZ
Sewer availability Cleared 11/17/2015 JAMES MORALEZ
ZI Cleared 11/19/2015 ERIC CLAROS
Excavation more than 5-ft deep Cleared 11/24/2015 CALOSHA APPROVED
Grading Pre-Inspection Cleared 11/24/2015 CHRISTINE MAALOUF
Low Impact Development Cleared 11/24/2015 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 11/30/2015 NATALIE MOORE
Green Code Cleared 12/1/2015 BRYAN MEYER
Work Adjacent to Public Way Cleared 12/1/2015 WARREN LIU

Contact Information

Architect Biglin, Brian W; Lic. No.: C29771 704 RUSTIC HILLS DRIVE      SIMI VALLEY, CA 93065
Contractor Owner-Builder       ,
Engineer Burgess, John J; Lic. No.: C21877 22921 TRITON WAY SUITE 227   THE BURGESS ENGINEERING GROUP    LAGUNA HILLS, CA 926531236
Engineer Cox, Steven Jeffrey; Lic. No.: C48940 130 MAGELLAN ST      THOUSAND OAKS, CA 91360

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/21/2016 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 3/30/2016 Conditional Approval ANTHONY ANDERSON
Piling/Pier/Caisson 3/30/2016 Not Ready for Inspection ANTHONY ANDERSON
Piling/Pier/Caisson 4/13/2016 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 5/24/2016 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 5/26/2016 Partial Approval ANTHONY ANDERSON
Piling/Pier/Caisson 6/14/2016 Corrections Issued ANTHONY ANDERSON
Piling/Pier/Caisson 6/22/2016 Partial Inspection ANTHONY ANDERSON
Piling/Pier/Caisson 7/25/2016 Partial Approval ANTHONY ANDERSON
Underground Mechanical 11/9/2016 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 2/15/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 2/21/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 2/24/2017 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/3/2017 Corrections Issued ANTHONY ANDERSON
Deputy Reinf. Concrete 3/10/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 3/10/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 3/28/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 3/28/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 4/13/2017 Approved DANIEL ORRANTE
Piling/Pier/Caisson 4/13/2017 Approved DANIEL ORRANTE
Footing/Foundation/Slab 4/18/2017 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 5/5/2017 Partial Inspection ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 5/9/2017 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 5/11/2017 Partial Inspection ANTHONY ANDERSON
Special/Order Compliance 5/22/2017 Partial Inspection DANIEL ORRANTE
Green Building Rough 5/30/2017 Partial Inspection ANTHONY ANDERSON
Reinforced Concrete Frame 5/30/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 5/30/2017 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 5/31/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 6/1/2017 Conditional Approval ANTHONY ANDERSON
Deputy Shotcrete 6/2/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 6/26/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 6/26/2017 Partial Approval ANTHONY ANDERSON
Green Building Rough 6/26/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 6/26/2017 Partial Inspection ANTHONY ANDERSON
Deputy Reinf. Concrete 6/27/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 7/13/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 7/13/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 7/14/2017 Conditional Approval ANTHONY ANDERSON
Deputy Drilled-In Anchors 7/19/2017 Approved ANTHONY ANDERSON
Footing/Foundation/Slab 7/19/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 7/20/2017 Approved ANTHONY ANDERSON
Deputy Shotcrete 7/24/2017 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 8/11/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 8/17/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 8/17/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 8/18/2017 Conditional Approval ANTHONY ANDERSON
Deputy Steel/Welding 8/21/2017 Conditional Approval ANTHONY ANDERSON
Green Building Rough 8/30/2017 Partial Inspection ANTHONY ANDERSON
Reinforced Concrete Frame 8/30/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 8/30/2017 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 9/1/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 9/6/2017 Conditional Approval ANTHONY ANDERSON
Pre-Gunite 9/6/2017 Partial Inspection ANTHONY ANDERSON
Deputy Reinf. Concrete 9/7/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 9/8/2017 Approved ANTHONY ANDERSON
Pre-Gunite 9/8/2017 Partial Approval ANTHONY ANDERSON
Green Building Rough 10/6/2017 Partial Inspection ANTHONY ANDERSON
Reinforced Concrete Frame 10/6/2017 Partial Inspection ANTHONY ANDERSON
Verify Sprinkler Sign Off 10/6/2017 Partial Inspection ANTHONY ANDERSON
Footing/Foundation/Slab 10/11/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 10/13/2017 Conditional Approval ANTHONY ANDERSON
Special/Order Compliance 10/21/2017 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/26/2017 Conditional Approval JOEL LAUNCHBAUGH
Deputy Steel/Welding 10/26/2017 Conditional Approval ANTHONY ANDERSON
Underground Mechanical 10/31/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 11/2/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/2/2017 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/3/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 11/6/2017 Approved ANTHONY ANDERSON
Deputy Reinf. Concrete 11/7/2017 Conditional Approval ANTHONY ANDERSON
Footing/Foundation/Slab 11/9/2017 Corrections Issued ANTHONY ANDERSON
Green Building Rough 11/13/2017 Not Ready for Inspection ANTHONY ANDERSON
Reinforced Concrete Frame 11/13/2017 Partial Approval ANTHONY ANDERSON
Verify Sprinkler Sign Off 11/13/2017 Not Ready for Inspection ANTHONY ANDERSON
Special/Order Compliance 11/18/2017 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 1/17/2018 Not Ready for Inspection MATT KELLERMAN
Structural Steel Frame 1/17/2018 Not Ready for Inspection MATT KELLERMAN
Verify Sprinkler Sign Off 1/17/2018 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2018 Partial Approval ANTHONY ANDERSON
Footing/Foundation/Slab 2/26/2018 Corrections Issued ANTHONY ANDERSON
Green Building Rough 2/28/2018 Not Ready for Inspection ANTHONY ANDERSON
Structural Steel Frame 2/28/2018 Corrections Issued ANTHONY ANDERSON
Verify Sprinkler Sign Off 2/28/2018 Not Ready for Inspection ANTHONY ANDERSON
Special/Order Compliance 3/17/2018 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 3/31/2018 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 5/26/2018 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/9/2018 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/16/2018 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 7/13/2018 Partial Inspection JOEL LAUNCHBAUGH
Structural Steel Frame 7/13/2018 Conditional Approval JOEL LAUNCHBAUGH
Verify Sprinkler Sign Off 7/13/2018 Partial Inspection JOEL LAUNCHBAUGH
PLUMBING-Rough 7/16/2018 Corrections Issued JOEL LAUNCHBAUGH
PLUMBING-Rough 7/18/2018 Partial Approval JOEL LAUNCHBAUGH
PLUMBING-Rough 7/23/2018 Corrections Issued MATT KELLERMAN
Special/Order Compliance 7/28/2018 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 7/30/2018 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 8/2/2018 Corrections Issued JOEL LAUNCHBAUGH
HVAC-Rough 8/6/2018 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/9/2018 Corrections Issued JOEL LAUNCHBAUGH
HVAC-Rough 8/20/2018 Partial Inspection CHRISTOPHER WILSON
HVAC-Rough 8/29/2018 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 8/31/2018 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/6/2018 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/10/2018 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/5/2018 Partial Approval CHRISTOPHER WILSON
Insulation 10/5/2018 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/5/2018 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/12/2018 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/12/2018 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/12/2018 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 10/12/2018 Partial Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/12/2018 Approved CHRISTOPHER WILSON
Gas Test 10/16/2018 Conditional Approval CHRISTOPHER WILSON
HVAC-Rough 10/16/2018 Corrections Issued CHRISTOPHER WILSON
Wood Frame 10/19/2018 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/2/2018 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/7/2018 Partial Approval CHRISTOPHER WILSON
Green Building Rough 11/7/2018 Partial Inspection CHRISTOPHER WILSON
Insulation 11/8/2018 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 11/8/2018 Partial Inspection CHRISTOPHER WILSON
Shower Pan 11/8/2018 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 11/9/2018 Partial Approval CHRISTOPHER WILSON
Shower Pan 11/9/2018 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/15/2018 Partial Approval CHRISTOPHER WILSON
Green Building Rough 11/15/2018 Partial Approval CHRISTOPHER WILSON
Shower Pan 11/15/2018 Partial Approval CHRISTOPHER WILSON
Insulation 11/20/2018 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 11/20/2018 Approved CARLOS MATAMOROS
Shower Pan 11/20/2018 Approved CARLOS MATAMOROS
Insulation 11/27/2018 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 12/4/2018 Partial Approval CARLOS MATAMOROS
Insulation 12/4/2018 Approved CARLOS MATAMOROS
Insulation 12/24/2018 Partial Inspection CHRISTOPHER WILSON
Insulation 12/28/2018 Partial Approval CHRISTOPHER WILSON
Shower Pan 12/28/2018 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 1/7/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/7/2019 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 1/10/2019 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 1/14/2019 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/15/2019 Partial Inspection CHRISTOPHER WILSON
Green Building Rough 1/15/2019 Partial Inspection CHRISTOPHER WILSON
Insulation 1/31/2019 Partial Approval CHRISTOPHER WILSON
Insulation 2/6/2019 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/22/2019 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/27/2019 Approved ANTHONY MCDOWALL
Green Building Rough 2/27/2019 Approved ANTHONY MCDOWALL
Sewer 2/27/2019 Approved ANTHONY MCDOWALL
Drywall Nailing 3/4/2019 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/4/2019 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/8/2019 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/14/2019 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 5/23/2019 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 6/6/2019 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 6/14/2019 Partial Inspection CHRISTOPHER WILSON
Structural Steel Frame 8/27/2019 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 10/2/2019 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/16/2019 Partial Inspection CHRISTOPHER WILSON
Service/Power Release 12/19/2019 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 12/24/2019 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 1/22/2020 Corrections Issued CHRISTOPHER WILSON
Pool Piping 1/22/2020 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Final 1/28/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 2/11/2020 Partial Inspection CHRISTOPHER WILSON
Gas Test 2/11/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Final 2/11/2020 Partial Inspection CHRISTOPHER WILSON
HVAC-Final 2/13/2020 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Final 2/19/2020 Not Ready for Inspection MATT KELLERMAN
HVAC-Final 2/19/2020 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Final 2/19/2020 Not Ready for Inspection MATT KELLERMAN
HVAC-Final 2/21/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 2/22/2020 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 2/22/2020 Off-Hour Fees Due
HVAC-Final 2/22/2020 Approved CHRISTOPHER WILSON
HVAC-Rough 2/22/2020 Off-Hour Fees Due
PLUMBING-Final 2/22/2020 Approved CHRISTOPHER WILSON
PLUMBING-Rough 2/22/2020 Off-Hour Fees Due
Special/Order Compliance 5/9/2020 Partial Inspection CHRISTOPHER WILSON
SUSMP-Std. Urban Storm Water 6/3/2020 Approved CHRISTOPHER WILSON
Final 6/25/2020 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/25/2020 Approved CHRISTOPHER WILSON
Green Building Final 6/25/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 6/25/2020 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 6/25/2020 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 6/25/2020 Corrections Issued CHRISTOPHER WILSON
Structural Steel Frame 6/25/2020 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 6/29/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Final 7/6/2020 Approved CHRISTOPHER WILSON
Green Building Final 7/6/2020 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 7/6/2020 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 7/6/2020 Approved CHRISTOPHER WILSON
Final 8/5/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 8/5/2020 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/5/2020 SGSOV Approved CHRISTOPHER WILSON
Final 8/13/2020 Corrections Issued CHRISTOPHER WILSON
Green Building Final 8/13/2020 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 10/6/2020 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/13/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 10/13/2020 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/20/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 10/20/2020 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/23/2020 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 10/23/2020 Not Ready for Inspection CHRISTOPHER WILSON
Final 10/28/2020 OK to Issue CofO CHRISTOPHER WILSON
Green Building Final 10/28/2020 Approved CHRISTOPHER WILSON