Piling/Pier/Caisson
|
3/21/2016
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
3/30/2016
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
3/30/2016
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
4/13/2016
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
5/24/2016
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
5/26/2016
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
6/14/2016
|
Corrections Issued
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
6/22/2016
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Piling/Pier/Caisson
|
7/25/2016
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Underground Mechanical
|
11/9/2016
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
2/15/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
2/21/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
2/24/2017
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
3/3/2017
|
Corrections Issued
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
3/10/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
3/10/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
3/28/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
3/28/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
4/13/2017
|
Approved
|
DANIEL ORRANTE
|
|
Piling/Pier/Caisson
|
4/13/2017
|
Approved
|
DANIEL ORRANTE
|
|
Footing/Foundation/Slab
|
4/18/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
5/5/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/9/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
5/11/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Special/Order Compliance
|
5/22/2017
|
Partial Inspection
|
DANIEL ORRANTE
|
|
Green Building Rough
|
5/30/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Reinforced Concrete Frame
|
5/30/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Verify Sprinkler Sign Off
|
5/30/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
5/31/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
6/1/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Shotcrete
|
6/2/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
6/26/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
6/26/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Green Building Rough
|
6/26/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Verify Sprinkler Sign Off
|
6/26/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
6/27/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
7/13/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
7/13/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
7/14/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Drilled-In Anchors
|
7/19/2017
|
Approved
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
7/19/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
7/20/2017
|
Approved
|
ANTHONY ANDERSON
|
|
Deputy Shotcrete
|
7/24/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Steel/Welding
|
8/11/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
8/17/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
8/17/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
8/18/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Steel/Welding
|
8/21/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Green Building Rough
|
8/30/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Reinforced Concrete Frame
|
8/30/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Verify Sprinkler Sign Off
|
8/30/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
9/1/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
9/6/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Pre-Gunite
|
9/6/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
9/7/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
9/8/2017
|
Approved
|
ANTHONY ANDERSON
|
|
Pre-Gunite
|
9/8/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Green Building Rough
|
10/6/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Reinforced Concrete Frame
|
10/6/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Verify Sprinkler Sign Off
|
10/6/2017
|
Partial Inspection
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
10/11/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
10/13/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Special/Order Compliance
|
10/21/2017
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/26/2017
|
Conditional Approval
|
JOEL LAUNCHBAUGH
|
|
Deputy Steel/Welding
|
10/26/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Underground Mechanical
|
10/31/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
11/2/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
11/2/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
11/3/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
11/6/2017
|
Approved
|
ANTHONY ANDERSON
|
|
Deputy Reinf. Concrete
|
11/7/2017
|
Conditional Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
11/9/2017
|
Corrections Issued
|
ANTHONY ANDERSON
|
|
Green Building Rough
|
11/13/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
|
Reinforced Concrete Frame
|
11/13/2017
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Verify Sprinkler Sign Off
|
11/13/2017
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
|
Special/Order Compliance
|
11/18/2017
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
1/17/2018
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Structural Steel Frame
|
1/17/2018
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Verify Sprinkler Sign Off
|
1/17/2018
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/9/2018
|
Partial Approval
|
ANTHONY ANDERSON
|
|
Footing/Foundation/Slab
|
2/26/2018
|
Corrections Issued
|
ANTHONY ANDERSON
|
|
Green Building Rough
|
2/28/2018
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
|
Structural Steel Frame
|
2/28/2018
|
Corrections Issued
|
ANTHONY ANDERSON
|
|
Verify Sprinkler Sign Off
|
2/28/2018
|
Not Ready for Inspection
|
ANTHONY ANDERSON
|
|
Special/Order Compliance
|
3/17/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
3/31/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
5/26/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
6/9/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
6/16/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
7/13/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
|
Structural Steel Frame
|
7/13/2018
|
Conditional Approval
|
JOEL LAUNCHBAUGH
|
|
Verify Sprinkler Sign Off
|
7/13/2018
|
Partial Inspection
|
JOEL LAUNCHBAUGH
|
|
PLUMBING-Rough
|
7/16/2018
|
Corrections Issued
|
JOEL LAUNCHBAUGH
|
|
PLUMBING-Rough
|
7/18/2018
|
Partial Approval
|
JOEL LAUNCHBAUGH
|
|
PLUMBING-Rough
|
7/23/2018
|
Corrections Issued
|
MATT KELLERMAN
|
|
Special/Order Compliance
|
7/28/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
7/30/2018
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
PLUMBING-Rough
|
8/2/2018
|
Corrections Issued
|
JOEL LAUNCHBAUGH
|
|
HVAC-Rough
|
8/6/2018
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
8/9/2018
|
Corrections Issued
|
JOEL LAUNCHBAUGH
|
|
HVAC-Rough
|
8/20/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/29/2018
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/31/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
9/6/2018
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
9/10/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
10/5/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
10/5/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/5/2018
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
10/12/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
10/12/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/12/2018
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
10/12/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
10/12/2018
|
Approved
|
CHRISTOPHER WILSON
|
|
Gas Test
|
10/16/2018
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
10/16/2018
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
10/19/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
11/2/2018
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/7/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
11/7/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Insulation
|
11/8/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
11/8/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/8/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
11/9/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/9/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/15/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
11/15/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
11/15/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
11/20/2018
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
11/20/2018
|
Approved
|
CARLOS MATAMOROS
|
|
Shower Pan
|
11/20/2018
|
Approved
|
CARLOS MATAMOROS
|
|
Insulation
|
11/27/2018
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Drywall Nailing
|
12/4/2018
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Insulation
|
12/4/2018
|
Approved
|
CARLOS MATAMOROS
|
|
Insulation
|
12/24/2018
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Insulation
|
12/28/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
12/28/2018
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
1/7/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
1/7/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
1/10/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
1/14/2019
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
1/15/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
1/15/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Insulation
|
1/31/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
2/6/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
2/22/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
2/27/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
2/27/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Sewer
|
2/27/2019
|
Approved
|
ANTHONY MCDOWALL
|
|
Drywall Nailing
|
3/4/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
3/4/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
5/8/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
5/14/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
5/23/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
6/6/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
6/14/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
8/27/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
10/2/2019
|
Approved
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Final
|
12/16/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
12/19/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
12/24/2019
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
1/22/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pool Piping
|
1/22/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
1/28/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
2/11/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Gas Test
|
2/11/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
2/11/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
2/13/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
ELECTRICAL-Final
|
2/19/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
HVAC-Final
|
2/19/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
PLUMBING-Final
|
2/19/2020
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
HVAC-Final
|
2/21/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
2/22/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
2/22/2020
|
Off-Hour Fees Due
|
|
|
HVAC-Final
|
2/22/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
2/22/2020
|
Off-Hour Fees Due
|
|
|
PLUMBING-Final
|
2/22/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/22/2020
|
Off-Hour Fees Due
|
|
|
Special/Order Compliance
|
5/9/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
SUSMP-Std. Urban Storm Water
|
6/3/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
6/25/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
6/25/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
6/25/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
6/25/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
6/25/2020
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
6/25/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
6/25/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
6/29/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
7/6/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
7/6/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
7/6/2020
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
7/6/2020
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
8/5/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
8/5/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
8/5/2020
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
Final
|
8/13/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
8/13/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
10/6/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
10/13/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
10/13/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
10/20/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
10/20/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
10/23/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
10/23/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Final
|
10/28/2020
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
10/28/2020
|
Approved
|
CHRISTOPHER WILSON
|