9137 W CORDELL DR 90069
Certificate Information: 9137 W CORDELL DR 90069
- Application / Permit
- 14010-30000-00328
- Plan Check / Job No.
- B14WL00477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR ALTERATION AND ADDITION TO EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 8/5/2015
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2014 | RUDOLF KINAR MELIKOFF |
| Corrections Issued | 2/18/2014 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 2/19/2014 | ARA SARGSYAN |
| Green Plans Picked Up | 2/27/2014 | APPLICANT |
| Applicant returned to address corrections | 3/19/2014 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 4/8/2014 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 3/31/2015 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/8/2015 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/3/2015 | KAMRAN GHOTBI RAVANDI |
| Issued | 8/5/2015 | LADBS |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| CofO in Progress | 11/17/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
| CofO Issued | 2/26/2022 | DEROLD HAUFF |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2014 | TAO YANG |
| Hydrant and Access approval | Cleared | 3/11/2014 | JOSEPH JACKSON |
| Permit | Cleared | 3/11/2014 | TAO YANG |
| Sewer availability | Cleared | 3/11/2014 | TAO YANG |
| ZI | Cleared | 4/23/2014 | MARITZA PRZEKOP |
| Green Code | Cleared | 7/15/2015 | RICHARD GARCIA |
| Address approval | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| Low Impact Development | Cleared | 7/20/2015 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/20/2015 | ARMENIA HERNANDEZ |
| Stormwater Pollution Mitigatn | Cleared | 7/20/2015 | MARTIN FRAGOSO |
| Excavation more than 5-ft deep | Cleared | 7/21/2015 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 7/21/2015 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cox, Steven Jeffrey; Lic. No.: C48940 | 130 MAGELLAN ST THOUSAND OAKS, CA 91360 |
| Engineer | Irvine, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD PASADENA, CA 91107 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/29/2016 | No Access for Inspection | BRAD BESCOS |
| Pre-Inspection | 6/13/2016 | Approved | BRAD BESCOS |
| Posting Pre-Inspection | 8/18/2016 | Approved | BRAD BESCOS |
| Special/Order Compliance | 6/30/2017 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 9/5/2017 | Partial Approval | BRAD BESCOS |
| Special/Order Compliance | 10/30/2017 | Partial Inspection | DANIEL GONZALEZ |
| Sewer | 11/3/2017 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 12/14/2017 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 4/3/2018 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/16/2018 | Not Ready for Inspection | DANIEL GONZALEZ |
| PLUMBING-Rough | 4/18/2018 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 6/18/2018 | Corrections Issued | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 9/19/2018 | Partial Approval | DANIEL GONZALEZ |
| Green Building Rough | 9/19/2018 | Not Ready for Inspection | DANIEL GONZALEZ |
| Verify Sprinkler Sign Off | 9/19/2018 | Not Ready for Inspection | DANIEL GONZALEZ |
| Deputy Steel/Welding | 10/12/2018 | Partial Approval | DANIEL GONZALEZ |
| Deputy Wood Construction | 10/26/2018 | Partial Approval | DANIEL GONZALEZ |
| HVAC-Rough | 2/26/2020 | Corrections Issued | RICHARD STEINBACH |
| Special/Order Compliance | 2/26/2020 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Rough | 2/27/2020 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Rough | 3/16/2020 | Partial Approval | RICHARD STEINBACH |
| HVAC-Rough | 3/16/2020 | Conditional Approval | RICHARD STEINBACH |
| Drywall Nailing | 6/23/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/23/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/23/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/29/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/29/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/29/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/27/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 7/14/2021 | Approved | RICHARD STEINBACH |
| Final | 7/14/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/14/2021 | Approved | RICHARD STEINBACH |
| Green Building Final | 7/14/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Green Building Rough | 7/14/2021 | Approved | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Not Ready | RICHARD STEINBACH |
| Smoke Detectors | 7/14/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 7/14/2021 | Approved | RICHARD STEINBACH |
| Gas Test | 8/5/2021 | Approved | RICHARD STEINBACH |
| Pre-Inspection | 8/13/2021 | Partial Inspection | RICHARD STEINBACH |
| Special/Order Compliance | 8/13/2021 | Partial Inspection | RAUL BARAJAS |
| Underground Mechanical | 8/18/2021 | Partial Approval | RICHARD STEINBACH |
| Service/Power Release | 8/24/2021 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 9/9/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Final | 9/28/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 9/28/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 9/28/2021 | Approved | RAUL BARAJAS |
| HVAC-Final | 9/30/2021 | Approved | RAUL BARAJAS |
| Green Building Final | 10/5/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 10/5/2021 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Not Ready | SCOTT FINNILA |
| ELECTRICAL-Final | 10/12/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 10/19/2021 | Approved | RAUL BARAJAS |
| Final | 10/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 10/27/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Approved | RAUL BARAJAS |
| Final | 11/2/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 11/16/2021 | OK to Issue CofO | ARTHUR SARGSYAN |