7537 N VINELAND AVE 91352
Certificate Information: 7537 N VINELAND AVE 91352
- Application / Permit
- 14010-20000-03887
- Plan Check / Job No.
- B14VN15146
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Fully sprinklered 43' x 94' three story apartment with parking garage
- Permit Issued
- Issued on 5/22/2015
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/9/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 12/9/2014 | APPLICANT |
Disabled Access Plans Picked Up | 1/8/2015 | APPLICANT |
Assigned to Plan Check Engineer | 1/22/2015 | STEVEN KIM |
Corrections Issued | 2/4/2015 | STEVEN KIM |
Quality Review Completed | 2/6/2015 | BINH PHAN |
Building Plans Picked Up | 2/11/2015 | APPLICANT |
Applicant returned to address corrections | 5/15/2015 | STEVEN KIM |
Plan Check Approved | 5/19/2015 | STEVEN KIM |
Issued | 5/22/2015 | LADBS |
CofO in Progress | 5/9/2017 | JOHN KITCKO |
Permit Finaled | 5/9/2017 | ANDREW CROMER |
CofO Issued | 5/9/2017 | ANDREW CROMER |
Permit Finaled | 5/9/2017 | ANDREW CROMER |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 2/27/2015 | CHRISTINE KEUSHGUERIAN |
Hydrant and Access approval | Cleared | 3/10/2015 | ROBERT DUFF |
Certificate of Compliance | Cleared | 3/21/2015 | SUSAN ZERMENO |
Driveway location | Cleared | 4/9/2015 | COLLINS ALLAN |
Permit | Cleared | 4/13/2015 | SANDRA FIGUEROA |
Sewer availability | Cleared | 4/13/2015 | SANDRA FIGUEROA |
Frnt yard landscape/Water mgmt | Cleared | 4/14/2015 | ANNA VIDAL |
Green Code | Cleared | 4/21/2015 | MICKEY YAMASHITA |
DAS Clearance | Cleared | 4/28/2015 | NORLITO MEDRANO |
Fire Marshall Fire Life Safety | Cleared | 4/28/2015 | ANDREW KO |
Low Impact Development | Cleared | 5/12/2015 | AMMAR ELTAWIL |
Highway dedication | Cleared | 5/13/2015 | SANDRA FIGUEROA |
Roof/Waste drainage to street | Cleared | 5/13/2015 | SANDRA FIGUEROA |
Contact Information
Contractor | Aram G Construction Inc; Lic. No.: 961066-B | 441 E SAN JOSE AVENUE #301 BURBANK, CA 91501 |
Engineer | Babakhanian, Oksen; Lic. No.: S3500 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
JOHN KITCKO, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 8/13/2015 | Partial Approval | DANNY RODRIGUEZ |
Footing/Foundation/Slab | 8/20/2015 | Corrections Issued | DANNY RODRIGUEZ |
Excavation/Setback/Form/Re-Bar | 8/21/2015 | Approved | STEPHEN REED |
Structural Steel Frame | 10/2/2015 | Approved | TIMOTHY KEY |
Deputy Wood Construction | 10/15/2015 | Conditional Approval | TIMOTHY KEY |
Floor/Roof Diaphrgm/Shear Wall | 10/15/2015 | Partial Inspection | TIMOTHY KEY |
Floor/Roof Diaphrgm/Shear Wall | 11/17/2015 | Partial Inspection | TIMOTHY KEY |
Floor/Roof Diaphrgm/Shear Wall | 1/12/2016 | Partial Inspection | TIMOTHY KEY |
Interior/Exterior Lathing | 1/26/2016 | Partial Inspection | TIMOTHY KEY |
Interior/Exterior Lathing | 4/7/2016 | Partial Inspection | ROBERT COLE |
Insulation | 4/14/2016 | Partial Approval | JAMES STEPHENS |
SGSOV-Seismic Gas S/O Valve | 4/21/2016 | SGSOV Not Ready | JAMES STEPHENS |
Floor/Roof Diaphrgm/Shear Wall | 4/26/2016 | Conditional Approval | CAMERON CHABAN |
Special/Order Compliance | 5/31/2016 | Corrections Issued | CAMERON CHABAN |
Interior/Exterior Lathing | 7/15/2016 | Approved | CAMERON CHABAN |
Insulation | 7/27/2016 | Partial Inspection | CAMERON CHABAN |
Green Building Rough | 7/28/2016 | Approved | RUSSELL KELLY |
Insulation | 7/29/2016 | Approved | CAMERON CHABAN |
Verify Sprinkler Sign Off | 7/29/2016 | Conditional Approval | CAMERON CHABAN |
Wood Frame | 7/29/2016 | Partial Inspection | CAMERON CHABAN |
Drywall Nailing | 8/9/2016 | Approved | CAMERON CHABAN |
Interior/Exterior Lathing | 8/9/2016 | Conditional Approval | CAMERON CHABAN |
Interior/Exterior Lathing | 9/9/2016 | Approved | CAMERON CHABAN |
Pre-Inspection | 12/5/2016 | Not Ready for Inspection | JOHN KITCKO |
Final | 3/29/2017 | Not Ready for Inspection | JOHN KITCKO |
Footing/Foundation/Slab | 3/29/2017 | Not Ready for Inspection | JOHN KITCKO |
Green Building Final | 3/29/2017 | Partial Approval | MICKEY YAMASHITA |
SGSOV-Seismic Gas S/O Valve | 3/29/2017 | SGSOV Not Ready | JOHN KITCKO |
Smoke Detectors | 3/29/2017 | Partial Inspection | JOHN KITCKO |
Verify Sprinkler Sign Off | 3/29/2017 | Not Ready for Inspection | JOHN KITCKO |
Wood Frame | 3/29/2017 | Partial Inspection | JOHN KITCKO |
Final | 4/21/2017 | Not Ready for Inspection | JOHN KITCKO |
Footing/Foundation/Slab | 4/21/2017 | Approved | JOHN KITCKO |
Green Building Final | 4/21/2017 | Not Ready for Inspection | ROLLIN GETTLE III |
SGSOV-Seismic Gas S/O Valve | 4/21/2017 | SGSOV Approved | JOHN KITCKO |
Smoke Detectors | 4/21/2017 | Approved | JOHN KITCKO |
Verify Sprinkler Sign Off | 4/21/2017 | Approved | JOHN KITCKO |
Wood Frame | 4/21/2017 | Approved | JOHN KITCKO |
Final | 5/1/2017 | OK to Issue CofO | JOHN KITCKO |
Green Building Final | 5/1/2017 | Approved | MICKEY YAMASHITA |