11258 W LAURIE DR 91604

Certificate Information: 11258 W LAURIE DR 91604

Application / Permit
14010-20000-03864
Plan Check / Job No.
B14VN14991
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED GARAGE - BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 4/24/2017
Issuing Office
Valley
Current Status
CofO Corrected on 12/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2014 APPLICANT
Assigned to Plan Check Engineer 1/15/2015 DAWN MC NULTY
Corrections Issued 2/4/2015 DAWN MC NULTY
Quality Review Completed 2/5/2015 BINH PHAN
Building Plans Picked Up 2/11/2015 APPLICANT
Applicant returned to address corrections 4/29/2015 DAWN MC NULTY
Applicant returned to address corrections 5/15/2015 DAWN MC NULTY
Applicant returned to address corrections 9/30/2015 DAWN MC NULTY
Applicant returned to address corrections 11/4/2015 DAWN MC NULTY
Applicant returned to address corrections 2/5/2016 DAWN MC NULTY
Applicant returned to address corrections 3/22/2016 DAWN MC NULTY
Applicant returned to address corrections 4/11/2016 DAWN MC NULTY
Applicant returned to address corrections 10/24/2016 DAWN MC NULTY
Applicant returned to address corrections 12/1/2016 DAWN MC NULTY
Plan Check Approved 2/1/2017 DAWN MC NULTY
Issued 4/24/2017 LADBS
CofO in Progress 10/18/2021 MICHAEL PELHAM
No Progress 10/18/2021 MICHAEL PELHAM
CofO in Progress 11/29/2021 ARAM AVEDISIAN
Re-Activate Permit 12/22/2021 MICHAEL SMITH
CofO Issued-Status Void 12/22/2021 MICHAEL SMITH
Permit Finaled-Status Void 12/22/2021 MICHAEL SMITH
Permit Finaled 12/22/2021 MICHAEL SMITH
CofO Corrected 12/22/2021 MICHAEL SMITH
Permit Finaled 12/22/2021 MICHAEL SMITH

Permit Application Clearance Information

GPI Written Notices Cleared 1/27/2015 DAWN MC NULTY
Grading Pre-Inspection Cleared 1/27/2015 DAWN MC NULTY
Miscellaneous Cleared 1/27/2015 DAWN MC NULTY
Address approval Cleared 2/23/2015 SANDRA FIGUEROA
BHO/Hillside ordinance Cleared 2/23/2015 SANDRA FIGUEROA
BHO/Hillside ordinance Cleared 2/23/2015 SANDRA FIGUEROA
BHO/Hillside ordinance Cleared 2/23/2015 SANDRA FIGUEROA
Eng Process Fee Ord 176,300 Cleared 2/23/2015 SANDRA FIGUEROA
Permit Cleared 2/23/2015 SANDRA FIGUEROA
Sewer availability Cleared 2/23/2015 SANDRA FIGUEROA
Work Adjacent to Public Way Cleared 2/23/2015 SANDRA FIGUEROA
Hydrant and Access approval Cleared 2/24/2015 JOSEPH JACKSON
Miscellaneous Cleared 2/24/2015 DENNIS CHEW
Miscellaneous Cleared 2/24/2015 DENNIS CHEW
BHO/Hillside ordinance Cleared 3/6/2015 CHRISTINE KEUSHGUERIAN
Highway dedication Cleared 3/6/2015 CHRISTINE KEUSHGUERIAN
Green Code Cleared 3/25/2015 MICKEY YAMASHITA
BHO/Hillside ordinance Cleared 3/31/2015 RICHARD SOUTHERLAND
Low Impact Development Cleared 3/31/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/31/2015 RICHARD SOUTHERLAND
Frnt yard landscape/Water mgmt Cleared 4/30/2015 DENNIS CHEW
Miscellaneous Cleared 4/30/2015 DENNIS CHEW
Specific Plan Cleared 4/30/2015 DENNIS CHEW
Miscellaneous Cleared 12/1/2016 WILLIAM HUGHEN
Specific Plan Cleared 12/1/2016 WILLIAM HUGHEN

Contact Information

Architect Keller, Andrea Marie; Lic. No.: C28707 724 S SPRING STREET # 701      LOS ANGELES, CA 90014
Contractor Peterberg Construction Inc; Lic. No.: 914754-B 3401 GRANDE VISTA DR #672      NEWBURY PARK, CA 91319
Engineer Hollingsworth, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Wirthlin, Jonathan Daniel; Lic. No.: C73259 9340 WOODLEY AVE      NORTH HILLS, CA 91343

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/21/2017 Not Ready for Inspection CHRISTOPHE COCHRAN
Piling/Pier/Caisson 6/21/2017 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Steel/Welding 12/6/2017 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 12/7/2017 Conditional Approval CHRISTOPHE COCHRAN
Deputy Other (see comments) 12/11/2017 No Access for Inspection ROBERT SHELLY
Deputy Steel/Welding 12/15/2017 Conditional Approval CHRISTOPHE COCHRAN
Deputy Steel/Welding 12/18/2017 Approved TIP WHITING
Excavation/Setback/Form/Re-Bar 3/5/2018 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 3/5/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 3/6/2018 Conditional Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 3/6/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 3/8/2018 No Access for Inspection ROBERT SHELLY
Piling/Pier/Caisson 3/9/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Grading 3/12/2018 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 3/12/2018 Conditional Approval CHRISTOPHE COCHRAN
Deputy Grading 3/13/2018 Partial Approval ROBERT SHELLY
Piling/Pier/Caisson 3/13/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Grading 3/14/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 3/14/2018 No Access for Inspection ROBERT SHELLY
Piling/Pier/Caisson 3/14/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Grading 3/15/2018 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 3/15/2018 Approved CHRISTOPHE COCHRAN
Deputy Grading 3/16/2018 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 3/16/2018 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 3/19/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 3/20/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 3/29/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 3/30/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 4/2/2018 Approved ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 4/12/2018 Not Ready for Inspection MICHAEL YOUNG
Piling/Pier/Caisson 4/12/2018 Not Ready for Inspection MICHAEL YOUNG
Excavation/Setback/Form/Re-Bar 4/16/2018 Partial Approval MICHAEL YOUNG
Footing/Foundation/Slab 4/16/2018 Partial Approval MICHAEL YOUNG
Deputy Reinf. Concrete 4/18/2018 Partial Approval MICHAEL YOUNG
Piling/Pier/Caisson 4/18/2018 Partial Approval MICHAEL YOUNG
Deputy Reinf. Concrete 4/19/2018 Partial Approval MICHAEL YOUNG
Footing/Foundation/Slab 5/1/2018 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 5/10/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/10/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 5/14/2018 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/14/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/15/2018 Conditional Approval ROBERT SHELLY
Deputy Drilled-In Anchors 5/24/2018 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/22/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/22/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/25/2018 Conditional Approval CHRISTOPHE COCHRAN
Deputy Shotcrete 6/25/2018 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/25/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Shotcrete 6/29/2018 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/29/2018 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/29/2018 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 7/3/2018 No Access for Inspection ROBERT SHELLY
Deputy Shotcrete 7/3/2018 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 7/13/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/13/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 7/27/2018 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/27/2018 Partial Approval CHRISTOPHE COCHRAN
Deputy Shotcrete 7/30/2018 Approved PIERRE VEGA
Deputy Reinf. Concrete 7/31/2018 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 8/7/2018 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/17/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 8/27/2018 Approved JEFFREY PARD
Deputy Drilled-In Anchors 8/28/2018 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 8/29/2018 Partial Approval JEFFREY PARD
Piling/Pier/Caisson 8/29/2018 Partial Approval JEFFREY PARD
Deputy Reinf. Concrete 9/6/2018 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 9/6/2018 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 9/6/2018 Partial Approval JEFFREY PARD
Deputy Reinf. Concrete 9/7/2018 Approved JEFFREY PARD
Deputy Reinf. Concrete 9/10/2018 Approved JEFFREY PARD
Deputy Reinf. Concrete 9/11/2018 Approved ROBERT SHELLY
Deputy Shotcrete 9/11/2018 Approved ROBERT SHELLY
Deputy Grading 9/12/2018 Approved JEFFREY PARD
Deputy Reinf. Concrete 9/12/2018 Approved JEFFREY PARD
Deputy Drilled-In Anchors 9/13/2018 No Access for Inspection ROBERT SHELLY
Deputy Grading 9/13/2018 No Access for Inspection ROBERT SHELLY
Deputy Other (see comments) 9/13/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 9/13/2018 No Access for Inspection ROBERT SHELLY
Deputy Reinf. Concrete 9/14/2018 Approved ROBERT SHELLY
Footing/Foundation/Slab 9/28/2018 Approved RAYMOND KEHOE
Deputy Drilled-In Anchors 10/18/2018 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 10/25/2018 Partial Approval JEFFREY PARD
Deputy Reinf. Concrete 10/29/2018 Approved ROBERT SHELLY
Deputy Steel/Welding 1/11/2019 Approved JEFFREY PARD
Deputy Reinf. Concrete 8/26/2019 Conditional Approval DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 8/29/2019 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Partial Approval RAYMOND KEHOE
PLUMBING-Rough 10/11/2019 Partial Approval RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 11/5/2019 Partial Approval RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 11/15/2019 Partial Approval RAYMOND KEHOE
Green Building Rough 11/15/2019 Not Ready for Inspection RAYMOND KEHOE
Verify Sprinkler Sign Off 11/15/2019 Not Ready for Inspection RAYMOND KEHOE
Wood Frame 12/23/2019 Not Ready for Inspection RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Partial Approval ARAM AVEDISIAN
HVAC-Rough 5/20/2020 Partial Approval ARAM AVEDISIAN
Deputy Wood Construction 5/22/2020 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/29/2020 Approved TROY SANDERS
Gas Test 5/29/2020 Approved TROY SANDERS
HVAC-Rough 5/29/2020 Partial Approval TROY SANDERS
Interior/Exterior Lathing 5/29/2020 Approved TROY SANDERS
PLUMBING-Rough 5/29/2020 Approved TROY SANDERS
Insulation 6/4/2020 Corrections Issued ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 6/4/2020 Approved ARAM AVEDISIAN
Drywall Nailing 6/11/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/31/2020 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 7/31/2020 Corrections Issued ARAM AVEDISIAN
Pool Piping 8/19/2020 Not Ready for Inspection ARAM AVEDISIAN
Underground Mechanical 8/20/2020 Partial Approval ARAM AVEDISIAN
Deck 11/16/2020 Not Ready for Inspection ARAM AVEDISIAN
Grounding or Bonding 11/16/2020 Not Ready for Inspection ARAM AVEDISIAN
Special/Order Compliance 1/27/2021 Partial Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 4/26/2021 Approved ARAM AVEDISIAN
Final 4/26/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/26/2021 Approved ARAM AVEDISIAN
Green Building Rough 4/26/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 4/26/2021 Approved ARAM AVEDISIAN
Smoke Detectors 4/26/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 4/26/2021 Approved ARAM AVEDISIAN
Final 4/30/2021 Partial Approval CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 4/30/2021 SGSOV Approved CHARLES POWELL
Special/Order Compliance 6/8/2021 Corrections Issued DANIEL ORRANTE
Final 6/15/2021 Corrections Issued ARAM AVEDISIAN
Final 6/18/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 6/25/2021 Not Ready for Inspection ARAM AVEDISIAN
Special/Order Compliance 7/22/2021 Partial Inspection ARAM AVEDISIAN
Special/Order Compliance 10/18/2021 Corrections Issued MICHAEL PELHAM
Final 11/29/2021 OK to Issue CofO ARAM AVEDISIAN