9416 W SIERRA MAR PL 90069

Certificate Information: 9416 W SIERRA MAR PL 90069

Application / Permit
14010-20000-03707
Plan Check / Job No.
B14VN14375
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED 3-CAR GARAGE & BASEMENT <NFPA-13D FIRE SPRINLERS THROUGHT>
Permit Issued
Issued on 4/8/2016
Issuing Office
West Los Angeles
Current Status
Issued on 4/8/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/19/2014 APPLICANT
Green Plans Picked Up 12/3/2014 APPLICANT
Assigned to Plan Check Engineer 12/4/2014 NILOOFAR MEHRAIN
Corrections Issued 12/8/2014 NILOOFAR MEHRAIN
Quality Review Completed 12/12/2014 BINH PHAN
Building Plans Picked Up 1/6/2015 APPLICANT
Applicant returned to address corrections 2/3/2015 NILOOFAR MEHRAIN
Plan Check Approved 4/4/2016 NILOOFAR MEHRAIN
Issued 4/8/2016 LADBS

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/17/2015 ROBERT DUFF
Address approval Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 NATALIE MOORE
Eng Process Fee Ord 176,300 Cleared 2/23/2015 LEE GUILBEAUX
Permit Cleared 2/23/2015 LEE GUILBEAUX
Sewer availability Cleared 2/23/2015 LEE GUILBEAUX
Green Code Cleared 9/14/2015 MICKEY YAMASHITA
Grading Pre-Inspection Cleared 10/6/2015 NILOOFAR MEHRAIN
Mailing Labels Cleared 10/6/2015 NILOOFAR MEHRAIN
Low Impact Development Cleared 10/19/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/19/2015 AVALYN KAMACHI
Certificate of Compliance Cleared 11/24/2015 ERIC CLAROS
ZI Cleared 11/24/2015 ERIC CLAROS
Miscellaneous Cleared 3/17/2016 VINCENT QUITORIANO
Excavation more than 5-ft deep Cleared 4/4/2016 CALOSHA APPROVED

Contact Information

Architect Rodrigues-Bidner, Theresa L; Lic. No.: C30331 9411 WYSTONE AVENUE      NORTHRIDGE, CA 91324
Contractor Boswell Construction Inc; Lic. No.: 934480-B 17071 VENTURA BLVD STE 201      ENCINO, CA 91316
Engineer Padilla, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2016 Approved BRAD BESCOS
Piling/Pier/Caisson 1/13/2017 Partial Approval BRAD BESCOS
Piling/Pier/Caisson 1/23/2017 Partial Approval BRAD BESCOS
Piling/Pier/Caisson 3/14/2017 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 4/13/2017 Not Ready for Inspection JOEL WILLIAMS
Footing/Foundation/Slab 4/26/2017 Not Ready for Inspection JOEL WILLIAMS
Footing/Foundation/Slab 5/18/2017 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 5/24/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 7/14/2017 Partial Approval DANNY TOLENTINO
Deputy Shotcrete 7/17/2017 No Access for Inspection JOEL WILLIAMS
Deputy Grading 8/2/2017 No Access for Inspection BRAD BESCOS
Footing/Foundation/Slab 9/29/2017 Not Ready for Inspection JOEL WILLIAMS
Footing/Foundation/Slab 10/10/2017 Not Ready for Inspection DANIEL GONZALEZ
PLUMBING-Rough 10/12/2017 Corrections Issued DANIEL GONZALEZ
PLUMBING-Rough 10/17/2017 Corrections Issued DANIEL GONZALEZ
PLUMBING-Rough 11/7/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 11/9/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 11/30/2017 Corrections Issued DANIEL GONZALEZ
Grading Pre-Inspection 12/5/2017 Partial Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 12/13/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 1/11/2018 Corrections Issued DANIEL GONZALEZ
Footing/Foundation/Slab 1/16/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 1/17/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 2/13/2018 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 2/28/2018 Partial Approval DANIEL GONZALEZ
Special/Order Compliance 6/9/2018 Partial Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/3/2018 Corrections Issued ROBERT MINASSIANS
BUILDING-Rough-Frame 10/9/2018 Not Ready for Inspection BRAD BESCOS
Green Building Rough 10/9/2018 Not Ready for Inspection BRAD BESCOS
Verify Sprinkler Sign Off 10/9/2018 Not Ready for Inspection BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 11/7/2018 Partial Approval DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 11/19/2018 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 12/14/2018 Partial Inspection ROBERT MINASSIANS
HVAC-Rough 1/14/2019 Corrections Issued DANNY TOLENTINO
HVAC-Rough 1/15/2019 Approved DANNY TOLENTINO
PLUMBING-Rough 1/15/2019 Approved DANNY TOLENTINO
ELECTRICAL-Rough 2/1/2019 Corrections Issued DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 2/7/2019 Partial Approval DANNY TOLENTINO
Insulation 2/13/2019 Partial Approval DANNY TOLENTINO
BUILDING-Rough-Frame 3/6/2019 Corrections Issued DANNY TOLENTINO
Green Building Rough 3/6/2019 Not Ready for Inspection DANNY TOLENTINO
Verify Sprinkler Sign Off 3/6/2019 Not Ready for Inspection DANNY TOLENTINO
Shower Pan 4/8/2019 Approved DANNY TOLENTINO
Piling/Pier/Caisson 5/8/2019 Approved RAUL BARAJAS
Deputy Reinf. Concrete 5/10/2019 Conditional Approval DANNY TOLENTINO
Interior/Exterior Lathing 5/13/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 7/2/2019 Approved DANNY TOLENTINO
Deputy Other (see comments) 10/7/2019 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 10/21/2019 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 10/24/2019 Not Ready for Inspection RICHARD STEINBACH
Green Building Rough 10/24/2019 Approved RICHARD STEINBACH
Verify Sprinkler Sign Off 10/24/2019 Approved RICHARD STEINBACH
Insulation 11/18/2019 Approved ROBERT CORNELL
Drywall Nailing 12/23/2019 Approved RICHARD STEINBACH
Interior/Exterior Lathing 10/14/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 9/3/2021 Not Ready for Inspection CRAIG DAVIS
Final 9/3/2021 Not Ready for Inspection CRAIG DAVIS
Green Building Final 9/3/2021 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 9/3/2021 Not Ready for Inspection CRAIG DAVIS
Service/Power Release 9/3/2021 Not Ready for Inspection CRAIG DAVIS
Smoke Detectors 9/3/2021 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 9/23/2021 No Access for Inspection SCOTT FINNILA
Final 9/23/2021 No Access for Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 9/23/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 2/1/2022 Partial Inspection RAUL BARAJAS
ELECTRICAL-Final 1/13/2026 Corrections Issued DAVID WILLIAMS
HVAC-Final 1/13/2026 Corrections Issued DAVID WILLIAMS
PLUMBING-Final 1/13/2026 Corrections Issued DAVID WILLIAMS
Service/Power Release 3/3/2026 Approved DAVID WILLIAMS