204 N COPERTO DR 90272

Certificate Information: 204 N COPERTO DR 90272

Application / Permit
14010-20000-03668
Plan Check / Job No.
B14VN14224
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ATT 2-CAR GARAGE. "FIRE SPRINKLER REQUIRED"; NFPA 13D.
Permit Issued
Issued on 6/28/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2014 APPLICANT
Assigned to Plan Check Engineer 12/4/2014 GUANG MIN TUNG
Corrections Issued 12/8/2014 GUANG MIN TUNG
Green Plans Picked Up 12/8/2014 APPLICANT
Quality Review Completed 12/10/2014 BINH PHAN
Building Plans Picked Up 12/12/2014 APPLICANT
Applicant returned to address corrections 1/13/2017 GUANG MIN TUNG
Plan Check Approved 6/28/2018 GUANG MIN TUNG
Issued 6/28/2018 LADBS
CofO in Progress 5/12/2023 DANIEL ORRANTE
Permit Finaled 5/12/2023 DANIEL ORRANTE
CofO Issued 5/12/2023 DANIEL ORRANTE
Permit Finaled 5/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/23/2014 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2014 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2014 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 12/23/2014 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/23/2014 HELEN FRANCISCO
Permit Cleared 12/23/2014 HELEN FRANCISCO
Sewer availability Cleared 12/23/2014 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 12/23/2014 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/28/2015 ROBERT DUFF
Low Impact Development Cleared 3/4/2016 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/10/2016 ARMEN DERMENJIAN
Grading Pre-Inspection Cleared 7/29/2016 GUANG MIN TUNG
Mailing Labels Cleared 7/29/2016 GUANG MIN TUNG
Green Code Cleared 9/29/2016 MICHAEL AYERS
Miscellaneous Cleared 9/29/2016 HUGO RICO
Miscellaneous Cleared 9/29/2016 HUGO RICO
Miscellaneous Cleared 1/13/2017 GUANG MIN TUNG
Miscellaneous Cleared 1/13/2017 GUANG MIN TUNG
Coastal Zone Cleared 6/4/2018 TREVOR MARTIN
Miscellaneous Cleared 6/28/2018 GUANG MIN TUNG

Contact Information

Contractor Owner-Builder       ,
Engineer Javadi-Koma, Shahram; Lic. No.: C69497 10349 MONTGOMERY AVE      GRANADA HILLS, CA 91403
Engineer Mirzadeh, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357
Geologist Lieurance, Martin Ellis; Lic. No.: EG1810 GROVER-HOLLINGSWORTH & ASSOCIATE   31129 VIA COLINAS STE 707    WESTLAKE VILLAGE, CA 91362

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2018 Partial Approval MICHAEL PELHAM
Deputy Reinf. Concrete 5/15/2019 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 5/21/2019 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 6/6/2019 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 6/10/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 7/9/2019 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 7/16/2019 Partial Approval ANDREW NAVE
Special/Order Compliance 8/5/2019 Approved ANDREW NAVE
Footing/Foundation/Slab 9/24/2019 Partial Approval ROBERT SHELLY
Deputy Drilled-In Anchors 1/16/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 3/24/2020 Approved ROBERT SHELLY
Footing/Foundation/Slab 4/20/2020 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 4/20/2020 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 4/29/2020 Corrections Issued ANDREW NAVE
Deputy Reinf. Concrete 5/6/2020 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 5/7/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 5/7/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 5/7/2020 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/8/2020 Conditional Approval ANDREW NAVE
Deputy Shotcrete 5/13/2020 Conditional Approval ANDREW NAVE
Deputy Shotcrete 5/14/2020 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/14/2020 Corrections Issued ANDREW NAVE
Deputy Shotcrete 5/15/2020 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/15/2020 Not Ready for Inspection ANDREW NAVE
Deputy Shotcrete 5/18/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 5/19/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 5/20/2020 Corrections Issued ROBERT SHELLY
Pre-Gunite 5/20/2020 Partial Approval ROBERT SHELLY
Deputy Drilled-In Anchors 5/29/2020 Conditional Approval ANDREW NAVE
Deputy Shotcrete 6/2/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 6/26/2020 Conditional Approval ANDREW NAVE
Special/Order Compliance 7/1/2020 Approved ANDREW NAVE
Deputy Drilled-In Anchors 7/9/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 7/10/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 7/22/2020 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 8/14/2020 Corrections Issued ROBERT SHELLY
Deputy Steel/Welding 8/17/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 8/26/2020 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 9/8/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 9/8/2020 Approved ANDREW NAVE
Deputy Reinf. Concrete 9/10/2020 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 9/24/2020 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Partial Approval ANDREW NAVE
Underground Mechanical 11/24/2020 Partial Approval ANDREW NAVE
Underground Mechanical 12/11/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 12/22/2020 Not Ready for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 12/29/2020 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 1/12/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 1/12/2021 Partial Approval ANDREW NAVE
Deputy Wood Construction 1/22/2021 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval ANDREW NAVE
HVAC-Rough 3/22/2021 Corrections Issued ANDREW NAVE
ELECTRICAL-Rough 3/25/2021 Corrections Issued ANDREW NAVE
HVAC-Rough 4/13/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 4/23/2021 Approved ANDREW NAVE
HVAC-Rough 4/23/2021 Approved ANDREW NAVE
PLUMBING-Rough 4/27/2021 Partial Approval ANDREW NAVE
Verify Sprinkler Sign Off 4/29/2021 Not Ready for Inspection ANDREW NAVE
Wood Frame 4/29/2021 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 6/1/2021 Partial Approval ANDREW NAVE
Green Building Rough 6/1/2021 Approved ANDREW NAVE
Verify Sprinkler Sign Off 6/1/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 6/4/2021 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 6/8/2021 Partial Approval ANDREW NAVE
Shower Pan 6/14/2021 Partial Approval ANDREW NAVE
Insulation 6/15/2021 Approved ANDREW NAVE
Drywall Nailing 7/2/2021 Partial Approval ANDREW NAVE
Drywall Nailing 7/6/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 7/6/2021 Approved ANDREW NAVE
Shower Pan 7/6/2021 Approved ANDREW NAVE
Service/Power Release 1/18/2022 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 2/1/2022 Approved ANDREW NAVE
PLUMBING-Final 2/4/2022 Corrections Issued ANDREW NAVE
Gas Test 2/16/2022 Approved ANDREW NAVE
PLUMBING-Final 2/16/2022 Corrections Issued ANDREW NAVE
Service/Power Release 3/10/2022 Approved ANDREW NAVE
Underground Mechanical 5/26/2022 Partial Inspection ANDREW NAVE
Gas Test 6/13/2022 Approved ANDREW NAVE
HVAC-Final 6/13/2022 Corrections Issued ANDREW NAVE
HVAC-Final 7/27/2022 Partial Approval BRENDAN LOONEY
Sewer 7/27/2022 Corrections Issued BRENDAN LOONEY
HVAC-Final 8/3/2022 Corrections Issued KENNETH NAGLE
HVAC-Final 8/12/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 8/12/2022 Conditional Approval BRENDAN LOONEY
Sewer 8/12/2022 Corrections Issued BRENDAN LOONEY
HVAC-Final 8/22/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 8/22/2022 Corrections Issued BRENDAN LOONEY
Sewer 8/22/2022 Partial Approval BRENDAN LOONEY
HVAC-Final 8/29/2022 Approved BRENDAN LOONEY
PLUMBING-Final 8/29/2022 Approved BRENDAN LOONEY
Special/Order Compliance 8/29/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 4/18/2023 Approved BRENDAN LOONEY
Final 4/18/2023 Corrections Issued BRENDAN LOONEY
Green Building Final 4/18/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 4/18/2023 Approved BRENDAN LOONEY
Structural Steel Frame 4/18/2023 Approved BRENDAN LOONEY
Final 5/3/2023 Conditional Approval BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved BRENDAN LOONEY