6100 N TOPANGA CANYON BLVD 91367
Certificate Information: 6100 N TOPANGA CANYON BLVD 91367
- Application / Permit
- 14010-20000-03336
- Plan Check / Job No.
- B14VN12869
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (26) Temporary Structure
- Work Description
- TEMPORARY 40' X 100' TENT OVER ICE SKATING RINK (14020-20000-02279)
- Permit Issued
- Issued on 12/11/2014
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 12/11/2014
Permit Application Status History
Submitted | 10/16/2014 | APPLICANT |
Assigned to Plan Check Engineer | 10/30/2014 | HERNAN ARREOLA |
Corrections Issued | 11/5/2014 | HERNAN ARREOLA |
Disabled Access Plans Picked Up | 11/5/2014 | APPLICANT |
Quality Review Completed | 11/6/2014 | BINH PHAN |
Building Plans Picked Up | 11/6/2014 | APPLICANT |
Plan Check Approved | 12/11/2014 | HERNAN ARREOLA |
Issued | 12/11/2014 | LADBS |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 11/17/2014 | JOHN LIN |
Sewer availability | Cleared | 11/17/2014 | JOHN LIN |
Title 19 building approval | Cleared | 11/17/2014 | KORY CLARK |
Miscellaneous | Cleared | 11/20/2014 | TOM GLICK |
Miscellaneous | Cleared | 11/20/2014 | TOM GLICK |
Miscellaneous | Cleared | 11/20/2014 | TOM GLICK |
Miscellaneous | Cleared | 11/20/2014 | TOM GLICK |
Specific Plan | Cleared | 11/20/2014 | TOM GLICK |
ZA Case | Cleared | 11/20/2014 | TOM GLICK |
DAS Clearance | Cleared | 12/11/2014 | NORLITO MEDRANO |
Contact Information
Contractor | Dawson J C Construction; Lic. No.: 942504-B | 31915 RANCHO CALIFORNIA ROAD STE 200-321 TEMECULA, CA 92591 |
Engineer | Hendershot, Robert Clay; Lic. No.: C48318 | 17150 VIA DEL CAMPO 306 SAN DIEGO, CA 92127 |
Inspector Information
JASON BORUTA, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
FELIX CEBALLOS, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Final | 10/19/2016 | Not Ready for Inspection | REID DAUB |
Footing/Foundation/Slab | 10/19/2016 | Approved | REID DAUB |
SGSOV-Seismic Gas S/O Valve | 10/19/2016 | SGSOV Not Required | REID DAUB |
Smoke Detectors | 10/19/2016 | Approved | REID DAUB |
Verify Sprinkler Sign Off | 10/19/2016 | Approved | REID DAUB |
Wood Frame | 10/19/2016 | Approved | REID DAUB |