9410 W SIERRA MAR PL 90069

Certificate Information: 9410 W SIERRA MAR PL 90069

Application / Permit
14010-20000-03324
Plan Check / Job No.
B14VN12717
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 STORY SFD W/ ATTACHED GARAGE AND BASEMENT
Permit Issued
Issued on 4/4/2016
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 4/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/15/2014 APPLICANT
Green Plans Picked Up 10/28/2014 APPLICANT
Assigned to Plan Check Engineer 10/30/2014 HERNAN ARREOLA
Corrections Issued 11/7/2014 HERNAN ARREOLA
Quality Review Completed 11/14/2014 BINH PHAN
Building Plans Picked Up 11/18/2014 APPLICANT
Plan Check Approved 3/30/2016 HERNAN ARREOLA
Issued 4/4/2016 LADBS
CofO in Progress 4/2/2026 DAVID WILLIAMS

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/17/2015 ROBERT DUFF
Address approval Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/23/2015 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/23/2015 LEE GUILBEAUX
Permit Cleared 2/23/2015 LEE GUILBEAUX
Sewer availability Cleared 2/23/2015 LEE GUILBEAUX
Green Code Cleared 10/22/2015 MICHAEL AYERS
Low Impact Development Cleared 12/8/2015 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 12/8/2015 AVALYN KAMACHI
Miscellaneous Cleared 3/15/2016 ARMENIA HERNANDEZ
Work Adjacent to Public Way Cleared 3/15/2016 DAVID PEREZ
ZI Cleared 3/17/2016 VINCENT QUITORIANO
Building over 3-story or 36-ft Cleared 3/30/2016 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/30/2016 CALOSHA APPROVED
Grading Pre-Inspection Cleared 3/30/2016 HERNAN ARREOLA
Mailing Labels Cleared 3/30/2016 HERNAN ARREOLA

Contact Information

Contractor Boswell Construction Inc; Lic. No.: 934480-B 17071 VENTURA BLVD STE 201      ENCINO, CA 91316
Engineer Padilla, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2016 Approved BRAD BESCOS
PLUMBING-Rough 5/1/2017 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 5/9/2017 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 5/25/2017 Not Ready for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 5/26/2017 Partial Approval BRAD BESCOS
Deputy Steel/Welding 7/10/2017 Approved BRAD BESCOS
Grading Pre-Inspection 12/5/2017 Partial Inspection DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 1/23/2018 Corrections Issued DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2018 Partial Approval DANIEL GONZALEZ
Green Building Rough 2/21/2018 Not Ready for Inspection DANIEL GONZALEZ
Verify Sprinkler Sign Off 2/21/2018 Not Ready for Inspection DANIEL GONZALEZ
PLUMBING-Rough 3/8/2018 Approved DANIEL GONZALEZ
HVAC-Rough 3/15/2018 Corrections Issued DANIEL GONZALEZ
Deputy Wood Construction 4/24/2018 No Access for Inspection DANIEL GONZALEZ
Wood Frame 5/29/2018 No Access for Inspection DANIEL GONZALEZ
Wood Frame 5/31/2018 Partial Approval DANIEL GONZALEZ
HVAC-Rough 6/6/2018 Corrections Issued DANIEL GONZALEZ
ELECTRICAL-Rough 6/13/2018 Approved DANIEL GONZALEZ
HVAC-Rough 6/15/2018 Approved DANIEL GONZALEZ
Wood Frame 6/15/2018 Not Ready for Inspection DANIEL GONZALEZ
Wood Frame 6/20/2018 Corrections Issued DANIEL GONZALEZ
BUILDING-Rough-Frame 6/27/2018 Corrections Issued DANNY TOLENTINO
Green Building Rough 6/27/2018 Not Ready for Inspection DANNY TOLENTINO
Verify Sprinkler Sign Off 6/27/2018 Not Ready for Inspection DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 7/31/2018 Partial Approval DANIEL GONZALEZ
Green Building Rough 7/31/2018 Not Ready for Inspection DANIEL GONZALEZ
Verify Sprinkler Sign Off 7/31/2018 Not Ready for Inspection DANIEL GONZALEZ
Insulation 8/3/2018 Corrections Issued ROBERT MINASSIANS
Light Gage Steel Frame 8/3/2018 Corrections Issued ROBERT MINASSIANS
BUILDING-Rough-Frame 8/21/2018 No Access for Inspection DANIEL GONZALEZ
Green Building Rough 8/21/2018 Not Ready for Inspection DANIEL GONZALEZ
Insulation 8/21/2018 No Access for Inspection DANIEL GONZALEZ
Verify Sprinkler Sign Off 8/21/2018 No Access for Inspection DANIEL GONZALEZ
BUILDING-Rough-Frame 8/22/2018 Conditional Approval DANIEL GONZALEZ
Green Building Rough 8/22/2018 Approved DANIEL GONZALEZ
Verify Sprinkler Sign Off 8/22/2018 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 8/30/2018 Approved DANIEL GONZALEZ
Insulation 8/30/2018 Approved DANIEL GONZALEZ
Drywall Nailing 9/17/2018 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 9/17/2018 Partial Approval DANIEL GONZALEZ
Interior/Exterior Lathing 1/28/2019 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 5/8/2019 Approved RAUL BARAJAS
Deputy Reinf. Concrete 5/10/2019 Conditional Approval DANNY TOLENTINO
Footing/Foundation/Slab 7/2/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 7/8/2019 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 8/14/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 12/4/2019 Partial Approval RICHARD STEINBACH
Pre-Inspection 11/13/2020 Partial Approval JOSEPH MCGARRY
Pre-Inspection 11/24/2020 Partial Inspection RAUL BARAJAS
Service/Power Release 11/24/2020 Not Ready for Inspection RAUL BARAJAS
Sewer 11/24/2020 Not Ready for Inspection RAUL BARAJAS
Special/Order Compliance 1/6/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Final 1/13/2021 Not Ready for Inspection RAUL BARAJAS
Pool/Spa Cover 1/14/2021 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 1/14/2021 Corrections Issued RAUL BARAJAS
Final 3/2/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 3/2/2021 Approved RAUL BARAJAS
Green Building Final 3/2/2021 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 3/2/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/2/2021 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 3/2/2021 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 3/2/2021 Approved RAUL BARAJAS
Final 6/17/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Final 6/17/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 6/17/2021 Partial Inspection RAUL BARAJAS
Sewer 6/17/2021 Approved RAUL BARAJAS
Final 7/29/2021 Not Ready for Inspection RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Approved RICHARD STEINBACH
Service/Power Release 7/29/2021 Not Ready for Inspection RICHARD STEINBACH
Final 8/30/2021 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 8/30/2021 Not Ready for Inspection RAUL BARAJAS
Final 9/23/2021 Corrections Issued SCOTT FINNILA
Service/Power Release 9/23/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 1/13/2026 Corrections Issued DAVID WILLIAMS
HVAC-Final 1/13/2026 Corrections Issued DAVID WILLIAMS
PLUMBING-Final 1/13/2026 Corrections Issued DAVID WILLIAMS
Final 3/6/2026 Corrections Issued DAVID WILLIAMS
Service/Power Release 3/6/2026 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Final 4/1/2026 Approved DAVID WILLIAMS
Final 4/1/2026 OK to Issue CofO DAVID WILLIAMS
HVAC-Final 4/1/2026 Approved DAVID WILLIAMS
PLUMBING-Final 4/1/2026 Approved DAVID WILLIAMS
Service/Power Release 4/1/2026 Approved DAVID WILLIAMS