13919 W VICTORY BLVD 91401

Certificate Information: 13919 W VICTORY BLVD 91401

Application / Permit
14010-20000-03114
Plan Check / Job No.
B14VN11858
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
2 STORY 18 UNIT APT WITH SUBTERRANIAN GARAGE. 2 UNITS SET ASIDE FOR VERY LOW INCOME
Permit Issued
Issued on 1/22/2016
Issuing Office
Valley
Current Status
CofO Corrected on 4/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2014 APPLICANT
Assigned to Plan Check Engineer 10/30/2014 HERNAN ARREOLA
Green Plans Picked Up 11/5/2014 APPLICANT
Disabled Access Plans Picked Up 11/18/2014 APPLICANT
Corrections Issued 12/4/2014 HERNAN ARREOLA
Quality Review Completed 12/17/2014 BINH PHAN
Building Plans Picked Up 12/17/2014 APPLICANT
Applicant returned to address corrections 2/17/2015 HERNAN ARREOLA
Plan Check Approved 1/22/2016 HERNAN ARREOLA
Issued 1/22/2016 LADBS
TCO Issued (Expire Date: 04-12-2022) 10/14/2021 JEFFREY DURAN
CofO in Progress 12/22/2021 JEFFREY DURAN
CofO Issued-Status Void 12/22/2021 JEFFREY DURAN
Permit Finaled-Status Void 12/22/2021 JEFFREY DURAN
Re-Activate Permit 3/31/2022 RICKEY JACKSON
Permit Finaled 4/4/2022 RICKEY JACKSON
CofO Corrected 4/4/2022 RICKEY JACKSON
Permit Finaled 4/4/2022 RICKEY JACKSON

Permit Application Clearance Information

"Q" conditions Cleared 1/6/2015 HERMINIGILDO AGUSTIN
Address approval Cleared 1/6/2015 HOWARD COOPER
Work Adjacent to Public Way Cleared 1/6/2015 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/28/2015 HOWARD COOPER
Frnt yard landscape/Water mgmt Cleared 2/25/2015 HERMINIGILDO AGUSTIN
Opn space landscape/Water mgmt Cleared 2/25/2015 HERMINIGILDO AGUSTIN
Green Code Cleared 3/4/2015 MICHAEL AYERS
DAS Clearance Cleared 3/17/2015 NORLITO MEDRANO
Housing density bonus Cleared 6/15/2015 REX LEE
Low Impact Development Cleared 9/17/2015 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 9/17/2015 ARMENIA HERNANDEZ
Stormwater Pollution Mitigatn Cleared 9/17/2015 IDA MEISAMI-FARD
Permit Cleared 9/23/2015 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/23/2015 ROBERT DUFF
Sewer availability Cleared 12/28/2015 RICHARD SOUTHERLAND
Fire Marshall Fire Life Safety Cleared 1/14/2016 DOMINIQUE MEDINA
Highway dedication Cleared 1/22/2016 MIKE KOUYOUMDJIAN

Contact Information

Architect Alajajian, Aram Movses; Lic. No.: C14897 1412 NORTH LOUISE STREET      GLENDALE, CA 91207
Contractor Atlantis Construction Services Inc; Lic. No.: 960125-B 1200 N SAN FERNANDO RD      LOS ANGELES, CA 90065
Engineer , ; Lic. No.: C49916       ,
Engineer Martirosian, Hayk Sam; Lic. No.: C52563 537 NOLAN AVE      GLENDALE, CA 91202

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2016 Partial Inspection CAMERON CHABAN
Pre-Inspection 11/9/2016 Approved JOHN KITCKO
Pre-Inspection 2/3/2017 No Access for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/14/2017 Corrections Issued CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 1/22/2018 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 7/18/2018 Conditional Approval CAMERON CHABAN
Green Building Rough 9/5/2018 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 9/5/2018 Not Ready for Inspection CAMERON CHABAN
Wood Frame 9/5/2018 Partial Inspection CAMERON CHABAN
Special/Order Compliance 1/24/2019 Conditional Approval CAMERON CHABAN
Drywall Nailing 3/26/2019 Partial Inspection CAMERON CHABAN
Green Building Rough 3/26/2019 Approved CAMERON CHABAN
Interior/Exterior Lathing 3/26/2019 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 3/29/2019 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 5/16/2019 Not Ready for Inspection JOHN KITCKO
Wood Frame 5/16/2019 No Access for Inspection JOHN KITCKO
Drywall Nailing 1/28/2021 Approved CAMERON CHABAN
Final 1/28/2021 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 1/28/2021 Approved CAMERON CHABAN
Green Building Final 1/28/2021 No Access for Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 1/28/2021 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 1/28/2021 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 1/28/2021 Not Ready for Inspection CAMERON CHABAN
Wood Frame 1/28/2021 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 4/12/2021 Approved CAMERON CHABAN
Final 7/21/2021 Conditional Approval CAMERON CHABAN
Green Building Final 7/21/2021 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved CAMERON CHABAN
Verify Sprinkler Sign Off 7/21/2021 Approved CAMERON CHABAN
Wood Frame 7/21/2021 Approved CAMERON CHABAN
Final 11/24/2021 Not Ready for Inspection DANIEL VARNUM