3315 N TWO TREE AVE 90031
Certificate Information: 3315 N TWO TREE AVE 90031
- Application / Permit
- 14010-20000-03035
- Plan Check / Job No.
- B14VN11589
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONSTRUCT NEW SINGLE FAMILY DWELLING W/ ATTACHED GARAGE AND ROOF DECK, FULLY SPRINKLER, NFPA-13D
- Permit Issued
- Issued on 3/15/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2014 | SAM CHANG |
| Corrections Issued | 10/7/2014 | SAM CHANG |
| Quality Review Completed | 10/8/2014 | BINH PHAN |
| Building Plans Picked Up | 10/8/2014 | APPLICANT |
| Green Plans Picked Up | 10/8/2014 | APPLICANT |
| Applicant returned to address corrections | 5/4/2015 | SAM CHANG |
| Applicant returned to address corrections | 5/12/2015 | SAM CHANG |
| Applicant returned to address corrections | 8/4/2015 | SAM CHANG |
| Applicant returned to address corrections | 8/14/2015 | SAM CHANG |
| Plan Check Approved | 4/7/2016 | SAM CHANG |
| Plan Check Approved | 2/7/2017 | SAM CHANG |
| Issued | 3/15/2017 | LADBS |
| CofO in Progress | 8/5/2022 | OSVALDO PARAMO |
| CofO in Progress | 8/5/2022 | OSVALDO PARAMO |
| Permit Finaled | 8/8/2022 | DEROLD HAUFF |
| CofO Issued | 8/8/2022 | DEROLD HAUFF |
| Permit Finaled | 8/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/7/2014 | SAM CHANG |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2015 | MIKE KOUYOUMDJIAN |
| "D" conditions | Cleared | 4/15/2015 | MARY RICHARDSON |
| "Q" conditions | Cleared | 4/15/2015 | MARY RICHARDSON |
| ZI | Cleared | 4/15/2015 | MARY RICHARDSON |
| Hydrant and Access approval | Cleared | 4/27/2015 | JOHN DALLAS |
| Low Impact Development | Cleared | 10/2/2015 | MICHAEL SCADUTO |
| Stormwater Pollution Mitigatn | Cleared | 10/2/2015 | MICHAEL SCADUTO |
| Green Code | Cleared | 10/8/2015 | RICHARD DOCKUS |
| Sewer availability | Cleared | 11/20/2015 | ARNULFO NUNO |
| Permit | Cleared | 11/24/2015 | CARLOS CUEVA |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| Roof/Waste drainage to street | Cleared | 2/2/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 2/26/2016 | CHRISTINE SOTELO |
| Miscellaneous | Cleared | 3/21/2016 | ARMEN DERMENJIAN |
| Excavation more than 5-ft deep | Cleared | 3/15/2017 | CALOSHA APPROVED |
Contact Information
| Architect | Dolinsky, John Colman; Lic. No.: C5339 | 6381 HOLLYWOOD BLVD SUITE 510 LOS ANGELES, CA 90028 |
| Contractor | Owner-Builder | , |
| Engineer | Valencia, Leon; Lic. No.: S2107 | 5220 SANTA MONICA BLVD SUITE 202 LOS ANGELES, CA 90029 |
| Geologist | Robles, Gustavo; Lic. No.: EG2422 | 981 W. ARROW HIGHWAY #191 SAN DIMAS, CA 91773 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/26/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/28/2017 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/5/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/6/2017 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/12/2017 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 7/17/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 7/21/2017 | Partial Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 7/27/2017 | Partial Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 8/3/2017 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 8/18/2017 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/21/2017 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/11/2017 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 9/11/2017 | Partial Inspection | OSVALDO PARAMO |
| Pre-Inspection | 9/13/2017 | Partial Inspection | DOMINIC DANERI |
| Footing/Foundation/Slab | 9/29/2017 | Partial Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2017 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/16/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 11/16/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 11/16/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/21/2017 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 11/21/2017 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/21/2017 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 11/21/2017 | Partial Inspection | DOMINIC DANERI |
| ELECTRICAL-Rough | 12/1/2017 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/7/2017 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 12/7/2017 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 12/7/2017 | Approved | OSVALDO PARAMO |
| Insulation | 12/11/2017 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/11/2017 | Partial Inspection | OSVALDO PARAMO |
| Drywall Nailing | 12/20/2017 | Approved | OSVALDO PARAMO |
| Shower Pan | 1/23/2018 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/1/2018 | Approved | ENRIQUE MIRELES |
| Sewer | 8/15/2018 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/21/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 9/6/2018 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/7/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 12/13/2021 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 12/13/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/7/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 2/7/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | OSVALDO PARAMO |
| Final | 3/3/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/3/2022 | Approved | OSVALDO PARAMO |
| Green Building Final | 3/3/2022 | Approved | OSVALDO PARAMO |
| HVAC-Final | 3/3/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 3/3/2022 | Approved | OSVALDO PARAMO |
| Final | 5/20/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 5/20/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/29/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | OSVALDO PARAMO |
| SUSMP-Std. Urban Storm Water | 7/29/2022 | Approved | OSVALDO PARAMO |
| Service/Power Release | 7/29/2022 | Approved | OSVALDO PARAMO |
| Final | 8/4/2022 | OK to Issue CofO | OSVALDO PARAMO |