2823 N THOMAS ST 90031
Certificate Information: 2823 N THOMAS ST 90031
- Application / Permit
- 14010-20000-03032
- Plan Check / Job No.
- B14VN11584
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY SFD WITH ATT. 2-CAR GARAGE & 660 SF ROOF DECK. <SPRINKLERS REQ'D THROUGHOUT>, NOTE : ZI-2399 (NORTHEAST HILLSIDE ZONE CHANGE) THE "RFA" LIMITED TO 1,658.30 SF & MAX HEIGHT TO 26.0'.
- Permit Issued
- Issued on 2/7/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2014 | APPLICANT |
| Green Plans Picked Up | 9/23/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2014 | ABDUL CHEGENI |
| Corrections Issued | 10/6/2014 | ABDUL CHEGENI |
| Quality Review Completed | 10/7/2014 | SHAHEN AKELYAN |
| Applicant returned to address corrections | 3/31/2015 | ABDUL CHEGENI |
| Applicant returned to address corrections | 4/22/2015 | ABDUL CHEGENI |
| Applicant returned to address corrections | 12/2/2015 | ABDUL CHEGENI |
| Plan Check Approved | 5/19/2016 | ABDUL CHEGENI |
| Issued | 2/7/2017 | LADBS |
| CofO in Progress | 5/24/2022 | OSVALDO PARAMO |
| CofO in Progress | 5/24/2022 | OSVALDO PARAMO |
| CofO Issued | 6/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/11/2015 | MARY RICHARDSON |
| "Q" conditions | Cleared | 2/11/2015 | MARY RICHARDSON |
| CPC | Cleared | 2/11/2015 | MARY RICHARDSON |
| Miscellaneous | Cleared | 2/11/2015 | MARY RICHARDSON |
| ZI | Cleared | 2/11/2015 | MARY RICHARDSON |
| Landscape for retaining wall | Cleared | 3/6/2015 | HERMINIGILDO AGUSTIN |
| Excavation more than 5-ft deep | Cleared | 3/31/2015 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 3/31/2015 | ABDUL CHEGENI |
| Mailing Labels | Cleared | 3/31/2015 | ABDUL CHEGENI |
| Miscellaneous | Cleared | 3/31/2015 | ABDUL CHEGENI |
| Address approval | Cleared | 4/13/2015 | MIKE KOUYOUMDJIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2015 | MIKE KOUYOUMDJIAN |
| Green Code | Cleared | 4/23/2015 | BRYAN MEYER |
| Hydrant and Access approval | Cleared | 4/27/2015 | JOHN DALLAS |
| CPC | Cleared | 5/6/2015 | MARY RICHARDSON |
| Low Impact Development | Cleared | 10/2/2015 | MICHAEL SCADUTO |
| Permit | Cleared | 10/20/2015 | JAMES KHO |
| Sewer availability | Cleared | 11/20/2015 | ARNULFO NUNO |
| BHO/Hillside ordinance | Cleared | 12/4/2015 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 1/26/2016 | CHRISTINE SOTELO |
| Roof/Waste drainage to street | Cleared | 2/2/2016 | CHRISTINE SOTELO |
| BHO/Hillside ordinance | Cleared | 5/19/2016 | ARMEN DERMENJIAN |
Contact Information
| Architect | Dolinsky, John Colman; Lic. No.: C5339 | 6381 HOLLYWOOD BLVD SUITE 510 LOS ANGELES, CA 90028 |
| Contractor | Owner-Builder | , |
| Engineer | Parmar, Raksha Narendra; Lic. No.: C35246 | 4335 VAN NUYS BLVD 135 SHERMAN OAKS, CA 91403 |
| Engineer | Robles, Gustavo; Lic. No.: C66797 | 981 W ARROW HWY 191 SAN DIMAS, CA 91773 |
| Engineer | Silverman, David Isaac; Lic. No.: C58650 | 9040 INDEPENDENCE AVE CANOGA PARK, CA 91304 |
| Engineer | Silverman, Joel Casper; Lic. No.: C16844 | 5727 CANOGA AVENUE 255 WOODLAND HILLS, CA 92367 |
| Geologist | Robles, Gustavo; Lic. No.: EG2422 | 981 W. ARROW HIGHWAY #191 SAN DIMAS, CA 91773 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 2/28/2017 | Approved | SALVADOR GONZALEZ |
| Pre-Inspection | 2/28/2017 | Approved | DOMINIC DANERI |
| Footing/Foundation/Slab | 3/10/2017 | Conditional Approval | SALVADOR GONZALEZ |
| Footing/Foundation/Slab | 3/13/2017 | Not Ready for Inspection | SALVADOR GONZALEZ |
| Pre-Inspection | 3/14/2017 | Approved | DOMINIC DANERI |
| Footing/Foundation/Slab | 3/15/2017 | Partial Approval | SALVADOR GONZALEZ |
| Footing/Foundation/Slab | 3/28/2017 | Partial Approval | SALVADOR GONZALEZ |
| PLUMBING-Rough | 4/5/2017 | Partial Approval | SALVADOR GONZALEZ |
| Footing/Foundation/Slab | 4/6/2017 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2017 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/5/2017 | Approved | OSVALDO PARAMO |
| Masonry Wall/Backfill | 6/15/2017 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2017 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/21/2017 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2017 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/30/2017 | Partial Inspection | OSVALDO PARAMO |
| Green Building Rough | 6/30/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 6/30/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 7/7/2017 | No Access for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 7/12/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 7/13/2017 | Approved | OSVALDO PARAMO |
| Masonry Wall/Backfill | 7/13/2017 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/14/2017 | Approved | OSVALDO PARAMO |
| Green Building Rough | 7/14/2017 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 7/14/2017 | Approved | OSVALDO PARAMO |
| Insulation | 7/18/2017 | Partial Inspection | OSVALDO PARAMO |
| Insulation | 7/20/2017 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/20/2017 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/21/2017 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 8/1/2017 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/21/2017 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 12/20/2017 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 4/13/2018 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/20/2018 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/20/2018 | Approved | OSVALDO PARAMO |
| Masonry Wall/Backfill | 7/5/2018 | Partial Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 7/11/2018 | Partial Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 7/17/2018 | Partial Inspection | OSVALDO PARAMO |
| Sewer | 8/15/2018 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/21/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Masonry Wall/Backfill | 9/6/2018 | Corrections Issued | OSVALDO PARAMO |
| Special/Order Compliance | 8/26/2019 | Corrections Issued | RUBEN SALAS |
| Pre-Inspection | 2/8/2021 | Approved | OSVALDO PARAMO |
| Grading Pre-Inspection | 6/8/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 7/30/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/30/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Grading Pre-Inspection | 8/2/2021 | Partial Approval | ROBERT HUGHES |
| Final | 12/6/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 5/16/2022 | Approved | OSVALDO PARAMO |
| Final | 5/19/2022 | Partial Approval | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 5/19/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/19/2022 | Approved | OSVALDO PARAMO |
| Final | 5/23/2022 | OK to Issue CofO | OSVALDO PARAMO |