107 N GUNSTON DR 90049
Certificate Information: 107 N GUNSTON DR 90049
- Application / Permit
- 14010-20000-02415
- Plan Check / Job No.
- B14VN09111
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRREGULAR 81'-0" X 133'-6" 2-STORY SFD W/ ATTACHED 3-CAR GARAGE PER ENGINEERING
- Permit Issued
- Issued on 11/13/2014
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2014 | JENNIFER LEE |
| Corrections Issued | 8/12/2014 | JENNIFER LEE |
| Quality Review Completed | 8/13/2014 | TAMERA SVETICH |
| Building Plans Picked Up | 9/2/2014 | APPLICANT |
| Green Plans Picked Up | 9/2/2014 | APPLICANT |
| Applicant returned to address corrections | 10/23/2014 | JENNIFER LEE |
| Applicant returned to address corrections | 10/29/2014 | JENNIFER LEE |
| Plan Check Approved | 11/13/2014 | JENNIFER LEE |
| Issued | 11/13/2014 | LADBS |
| CofO in Progress | 5/26/2021 | CARLOS MATAMOROS |
| CofO Issued | 6/8/2021 | VINCENT COTTON |
| Permit Finaled | 6/8/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2014 | SANDRA FIGUEROA |
| Grading Pre-Inspection | Cleared | 10/21/2014 | JENNIFER LEE |
| Mailing Labels | Cleared | 10/21/2014 | JENNIFER LEE |
| Miscellaneous | Cleared | 10/21/2014 | RICK TORRES |
| Private street | Cleared | 10/21/2014 | RICK TORRES |
| ZA Case | Cleared | 10/21/2014 | RICK TORRES |
| Low Impact Development | Cleared | 11/5/2014 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2014 | JOHN LIN |
| Green Code | Cleared | 11/6/2014 | RICHARD DOCKUS |
| Hydrant and Access approval | Cleared | 11/6/2014 | JOSEPH JACKSON |
| Permit | Cleared | 11/6/2014 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 11/6/2014 | JOHN LIN |
| Sewer availability | Cleared | 11/6/2014 | JOHN LIN |
Contact Information
| Contractor | Just Construction & Management; Lic. No.: 594992-B | 16767 BOLLINGER DRIVE PACIFIC PALISADES, CA 90272 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Yenjai, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
| Geologist | Van, Meter James L.; Lic. No.: EG2031 | 7702 CAPISTRANO AVE WEST HILLS, CA 91304 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/6/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 4/6/2015 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 4/6/2015 | Partial Approval | DANIEL ORRANTE |
| PLUMBING-Rough | 4/6/2015 | Partial Approval | DANIEL ORRANTE |
| Underground Mechanical | 4/6/2015 | Approved | DANIEL ORRANTE |
| PLUMBING-Rough | 4/7/2015 | Approved | DANIEL ORRANTE |
| Underground Mechanical | 4/7/2015 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 4/10/2015 | Partial Approval | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 4/13/2015 | Corrections Issued | ERWIN LARRANAGA |
| Footing/Foundation/Slab | 4/14/2015 | Approved | DANIEL ORRANTE |
| PLUMBING-Rough | 4/23/2015 | Partial Approval | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2015 | Approved | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2015 | Corrections Issued | DAVID JAMES |
| PLUMBING-Rough | 2/23/2016 | Partial Approval | DAVID JAMES |
| ELECTRICAL-Rough | 3/23/2016 | Partial Inspection | DAVID JAMES |
| ELECTRICAL-Rough | 3/30/2016 | Partial Approval | DAVID JAMES |
| ELECTRICAL-Rough | 4/12/2016 | Approved | DAVID JAMES |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2016 | Partial Approval | DAVID JAMES |
| PLUMBING-Rough | 4/12/2016 | Approved | DAVID JAMES |
| Interior/Exterior Lathing | 5/12/2016 | Partial Approval | DAVID JAMES |
| HVAC-Rough | 10/18/2016 | Partial Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/4/2017 | Partial Inspection | THOMAS FINNILA |
| Green Building Rough | 1/4/2017 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 1/4/2017 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 1/4/2017 | Approved | THOMAS FINNILA |
| Wood Frame | 1/4/2017 | Partial Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/15/2017 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 2/15/2017 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/19/2017 | Approved | THOMAS FINNILA |
| Green Building Rough | 4/19/2017 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/29/2018 | Approved | JOHN LUMB |
| HVAC-Rough | 6/29/2018 | Partial Approval | JOHN LUMB |
| PLUMBING-Rough | 6/29/2018 | Approved | JOHN LUMB |
| Special/Order Compliance | 1/15/2019 | No Access for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2019 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2019 | Conditional Approval | ANTHONY MCDOWALL |
| Wood Frame | 11/23/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 11/26/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 12/6/2019 | Approved | TIM CHRISTENSEN |
| PLUMBING-Rough | 12/6/2019 | Approved | TIM CHRISTENSEN |
| HVAC-Rough | 12/10/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Wood Frame | 12/10/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2019 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 12/13/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 12/17/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 12/17/2019 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 12/18/2019 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 12/19/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Wood Frame | 12/19/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Wood Frame | 12/24/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| Wood Frame | 1/8/2020 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 1/9/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 1/9/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/14/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 1/14/2020 | Approved | CARLOS MATAMOROS |
| Wood Frame | 1/16/2020 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 1/24/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/24/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/30/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/21/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/22/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/18/2020 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 5/20/2020 | Approved | CARLOS MATAMOROS |
| Final | 9/16/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 9/16/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 9/16/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/5/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 10/7/2020 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 10/7/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 4/1/2021 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 4/1/2021 | Approved | CARLOS MATAMOROS |
| Sewer | 4/6/2021 | Approved | CARLOS MATAMOROS |
| Sewer | 4/13/2021 | Approved | CARLOS MATAMOROS |
| Sewer | 4/15/2021 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/20/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 4/22/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Green Building Final | 4/23/2021 | Approved | CARLOS MATAMOROS |
| Final | 4/30/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 4/30/2021 | Approved | CARLOS MATAMOROS |
| Final | 5/26/2021 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 5/26/2021 | Approved | CARLOS MATAMOROS |