1645 W LANDA ST 90039
Certificate Information: 1645 W LANDA ST 90039
- Application / Permit
- 14010-20000-01768
- Plan Check / Job No.
- B14VN07109
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY 22'9" X 53'4" SFD W/ATT 18'11" X 20'7" GAR
- Permit Issued
- Issued on 12/12/2017
- Issuing Office
- Metro
- Current Status
- Issued on 12/12/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2014 | CHON CHIO KUO |
| Corrections Issued | 7/30/2014 | CHON CHIO KUO |
| Quality Review Completed | 7/31/2014 | TAMERA SVETICH |
| Building Plans Picked Up | 8/14/2014 | APPLICANT |
| Green Plans Picked Up | 8/14/2014 | APPLICANT |
| Applicant returned to address corrections | 5/28/2015 | CHON CHIO KUO |
| Applicant returned to address corrections | 10/5/2017 | CHON CHIO KUO |
| Plan Check Approved | 12/11/2017 | CHON CHIO KUO |
| Issued | 12/12/2017 | LADBS |
| Permit Expired-Status Void | 5/3/2021 | RUBEN SALAS |
| Re-Activate Permit | 5/27/2021 | RUBEN SALAS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/20/2014 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2014 | JAMES MORALEZ |
| Permit | Cleared | 8/20/2014 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 8/22/2014 | JOHN DALLAS |
| BHO/Hillside ordinance | Cleared | 8/28/2014 | RICHARD SOUTHERLAND |
| BHO/Hillside ordinance | Cleared | 8/28/2014 | RICHARD SOUTHERLAND |
| BHO/Hillside ordinance | Cleared | 8/28/2014 | RICHARD SOUTHERLAND |
| BHO/Hillside ordinance | Cleared | 8/28/2014 | RICHARD SOUTHERLAND |
| ZA Case | Cleared | 8/28/2014 | ANDY RODRIGUEZ |
| Sewer availability | Cleared | 9/5/2014 | DAVID PEREZ |
| Green Code | Cleared | 11/19/2015 | ROLLIN GETTLE III |
| Low Impact Development | Cleared | 1/21/2016 | IDA MEISAMI-FARD |
| Encroachment in public way | Cleared | 6/22/2016 | NATALIE MOORE |
| Roof/Waste drainage to street | Cleared | 7/1/2016 | ROBERT SAMONTE |
| Disturb/Remove Protected Trees | Cleared | 4/5/2017 | LUIS TORRES |
| Excavation more than 5-ft deep | Cleared | 7/27/2017 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 8/22/2017 | CHON-CHIO KUO |
| Miscellaneous | Cleared | 11/17/2017 | CHON-CHIO KUO |
| Work Adjacent to Public Way | Cleared | 12/6/2017 | WARREN LIU |
Contact Information
| Architect | Murnane, R Mcshane; Lic. No.: C34176 | 2898 ROWENA AVENUE UNIT 102 LOS ANGELES, CA 90039 |
| Contractor | Owner-Builder | , |
| Engineer | Khoury, Nader Bulos; Lic. No.: C61402 | 3406 LINDA VISTA TER FALLBROOK, CA 92028 |
| Engineer | Tsai, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/4/2018 | Partial Approval | DAVID CHAN |
| Special/Order Compliance | 4/10/2019 | Approved | DAVID CHAN |
| Special/Order Compliance | 10/8/2019 | Approved | ELMER BLAND |
| Special/Order Compliance | 10/8/2019 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 10/31/2019 | Not Ready for Inspection | DAVID CHAN |
| Special/Order Compliance | 11/20/2019 | Approved | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 4/22/2020 | Conditional Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 4/24/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 5/18/2020 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 5/19/2020 | Corrections Issued | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 6/5/2020 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 6/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 6/18/2020 | Partial Approval | OSVALDO PARAMO |
| Pre-Inspection | 7/23/2020 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Inspection | 8/4/2020 | Approved | DAVID CHAN |
| Pre-Inspection | 8/19/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 8/25/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 8/25/2020 | Partial Inspection | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 2/22/2021 | Partial Inspection | ROBERT VORHIS |
| Special/Order Compliance | 3/4/2021 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 4/14/2021 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 4/14/2021 | Partial Inspection | RUBEN SALAS |
| Special/Order Compliance | 5/3/2021 | Permit Expired-Status Void | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Corrections Issued | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 6/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 7/5/2022 | No Access for Inspection | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 7/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 3/28/2023 | Approved | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 5/9/2023 | Corrections Issued | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 9/10/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 1/3/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 6/6/2025 | Conditional Approval | ALEX COLIN |