519 N HARPER AVE 90048
Certificate Information: 519 N HARPER AVE 90048
- Application / Permit
- 14010-20000-01087
- Plan Check / Job No.
- B14VN04067
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD W/ATT. GARAGE AND 1265 SF BASEMENT LIV. SPACE, (authomatic fire sprinkler system req'd throughout).
- Permit Issued
- Issued on 10/14/2014
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2014 | ABDUL CHEGENI |
| Corrections Issued | 4/14/2014 | ABDUL CHEGENI |
| Green Plans Picked Up | 4/14/2014 | APPLICANT |
| Quality Review Completed | 4/18/2014 | TAMERA SVETICH |
| Building Plans Picked Up | 4/22/2014 | APPLICANT |
| Applicant returned to address corrections | 6/24/2014 | ABDUL CHEGENI |
| Applicant returned to address corrections | 8/4/2014 | ABDUL CHEGENI |
| Applicant returned to address corrections | 8/19/2014 | ABDUL CHEGENI |
| Plan Check Approved | 9/17/2014 | ABDUL CHEGENI |
| Issued | 10/14/2014 | LADBS |
| CofO in Progress | 12/27/2024 | JOSE MACIAS |
| Permit Finaled | 1/8/2025 | DEROLD HAUFF |
| CofO Issued | 1/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/24/2014 | ABDUL CHEGENI |
| ZI | Cleared | 7/15/2014 | MARITZA PRZEKOP |
| Low Impact Development | Cleared | 7/29/2014 | IDA MEISAMI-FARD |
| Address approval | Cleared | 8/1/2014 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2014 | JOHN LIN |
| Hydrant and Access approval | Cleared | 8/1/2014 | JOSEPH JACKSON |
| Permit | Cleared | 8/1/2014 | JOHN LIN |
| Sewer availability | Cleared | 8/1/2014 | JOHN LIN |
| Green Code | Cleared | 8/4/2014 | PETER FOLLING |
| Roof/Waste drainage to street | Cleared | 8/4/2014 | LEE GUILBEAUX |
| Disturb/Remove Protected Trees | Cleared | 9/4/2014 | TROY CALLEROS |
Contact Information
| Architect | Mac, Laren Michael Bruce; Lic. No.: C29858 | 23705 VANOWEN # 309 WEST HILLS, CA 91307 |
| Contractor | Owner-Builder | , |
| Engineer | Jahanpour-Burke, Hooshmand; Lic. No.: L8230 | 7728 ANTERO CR LAS VEGAS, NV 89128 |
| Engineer | Nester, Melvin Russell Jr; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Vidal, Juan Alonso; Lic. No.: GE861 | 15331 DOGWOOD ST WESTMINSTER, CA 92683 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/18/2015 | Approved | RUBEN SALAS |
| Footing/Foundation/Slab | 3/6/2015 | Partial Approval | PIERRE VEGA |
| METHANE-Barrier | 3/6/2015 | Not Ready for Inspection | PIERRE VEGA |
| METHANE-Subgrade | 3/6/2015 | Not Ready for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 3/18/2015 | Completed-MF (special insp) | TIMOTHY O CONNER |
| METHANE-Barrier | 3/18/2015 | Not Ready for Inspection | TIMOTHY O CONNER |
| METHANE-Subgrade | 3/18/2015 | Not Ready for Inspection | TIMOTHY O CONNER |
| Excavation/Setback/Form/Re-Bar | 3/19/2015 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 3/19/2015 | Corrections Issued | PIERRE VEGA |
| Deputy Reinf. Concrete | 3/20/2015 | Approved | PIERRE VEGA |
| METHANE-Subgrade | 4/1/2015 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 4/1/2015 | Approved | PIERRE VEGA |
| Footing/Foundation/Slab | 4/8/2015 | Partial Approval | PIERRE VEGA |
| METHANE-Barrier | 4/8/2015 | Approved | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 4/9/2015 | Not Ready for Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 4/17/2015 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2015 | Partial Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 4/24/2015 | Partial Approval | PIERRE VEGA |
| Wood Frame | 4/30/2015 | Partial Approval | PIERRE VEGA |
| Special/Order Compliance | 2/2/2016 | No Access for Inspection | TIMOTHY O CONNER |
| Pre-Inspection | 8/19/2016 | No Access for Inspection | TIMOTHY O CONNER |
| Special/Order Compliance | 12/12/2016 | Approved | RONALD COWAN |
| Pre-Inspection | 6/16/2017 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 12/15/2017 | Partial Approval | LUIS BARRALES |
| Wood Frame | 1/12/2018 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2018 | Partial Inspection | RONALD COWAN |
| Deputy Steel/Welding | 10/10/2018 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 10/11/2018 | Approved | RONALD COWAN |
| PLUMBING-Rough | 12/26/2018 | Partial Approval | DANNY TOLENTINO |
| Special/Order Compliance | 5/2/2019 | No Access for Inspection | JOSEPH MCGARRY |
| Special/Order Compliance | 5/15/2019 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/29/2019 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 5/29/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 5/29/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/29/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/6/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 6/6/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/6/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Special/Order Compliance | 6/6/2019 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 6/6/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Special/Order Compliance | 6/2/2020 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/7/2020 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 8/12/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/14/2020 | Approved | ARTHUR SARGSYAN |
| Special/Order Compliance | 9/9/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/14/2020 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 10/14/2020 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 11/12/2020 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/9/2020 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 12/9/2020 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/16/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 3/10/2021 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/1/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/3/2021 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 5/19/2021 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 6/9/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 6/9/2021 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 6/9/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 7/16/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 7/16/2021 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 3/11/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 4/28/2022 | Partial Approval | ADAM ESCOTO |
| Special/Order Compliance | 8/8/2022 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 3/29/2023 | Corrections Issued | MICHAEL LEWIS |
| Pre-Inspection | 10/19/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 6/10/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 8/6/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 8/26/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 10/23/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 11/7/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 11/7/2024 | Approved | JOSE MACIAS |
| Final | 11/7/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 11/7/2024 | Approved | JOSE MACIAS |
| Green Building Final | 11/7/2024 | Approved | JOSE MACIAS |
| METHANE-Final | 11/7/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 11/7/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 11/7/2024 | Approved | JOSE MACIAS |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | JOSE MACIAS |
| Final | 12/20/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 1/9/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 1/9/2025 | Approved | JOSE MACIAS |