726 N ECHO PARK AVE 90026

Certificate Information: 726 N ECHO PARK AVE 90026

Application / Permit
14010-20000-00003
Plan Check / Job No.
B14VN00020
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD W/ ATTACHED 2 CAR GARAGE.
Permit Issued
Issued on 4/18/2024
Issuing Office
Metro
Current Status
Issued on 4/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2014 APPLICANT
Assigned to Plan Check Engineer 2/20/2014 HERNAN ARREOLA
Corrections Issued 2/28/2014 HERNAN ARREOLA
Quality Review Completed 2/28/2014 TAMERA SVETICH
Building Plans Picked Up 3/11/2014 APPLICANT
Applicant returned to address corrections 7/12/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/19/2021 HERNAN ARREOLA
Plan Check Approved 4/18/2024 HERNAN ARREOLA
Issued 4/18/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/23/2014 HOWARD COOPER
BHO/Hillside ordinance Cleared 10/23/2014 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 10/23/2014 HOWARD COOPER
Sewer availability Cleared 10/23/2014 HOWARD COOPER
Work Adjacent to Public Way Cleared 10/23/2014 HOWARD COOPER
Low Impact Development Cleared 12/10/2020 ANDRES COVARRUBIAS
Hydrant and Access approval Cleared 5/19/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 7/29/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 11/11/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 11/11/2023 TREVOR QUAN
Building over 3-story or 36-ft Cleared 1/19/2024 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/19/2024 CALOSHA APPROVED
City Hist. Cultural Monument Cleared 2/27/2024 SUKI GERSHENHORN
HPOZ Cleared 2/27/2024 SUKI GERSHENHORN
Historic monument Cleared 2/27/2024 SUKI GERSHENHORN
Miscellaneous Cleared 2/27/2024 SUKI GERSHENHORN
Disturb/Remove Protected Trees Cleared 4/1/2024 ADALBERTO VERA
BHO/Hillside ordinance Cleared 4/4/2024 ALBERT TAM
BHO/Hillside ordinance Cleared 4/4/2024 ALBERT TAM
Grading Pre-Inspection Cleared 4/18/2024 HERNAN ARREOLA
Mailing Labels Cleared 4/18/2024 HERNAN ARREOLA

Contact Information

Contractor Owner-Builder       ,
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Esmaily-Radvar,, Shahrokh; Lic. No.: GE2742 5 HODGENVILLE      IRVINE, CA 92620

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/23/2024 Corrections Issued THOMAS LOGRASSO
Piling/Pier/Caisson 5/1/2024 Corrections Issued THOMAS LOGRASSO
Deputy Other (see comments) 7/23/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/26/2024 Corrections Issued HAMIK HARTOUNIAN
Deputy Grading 7/30/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/31/2024 Corrections Issued HAMIK HARTOUNIAN
METHANE-Barrier 7/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Subgrade 7/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 8/6/2024 Partial Approval HAMIK HARTOUNIAN
METHANE-Barrier 8/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Subgrade 8/8/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 8/8/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 8/15/2024 Conditional Approval BRENDAN MORELLI
Deputy Reinf. Concrete 9/6/2024 Conditional Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 9/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval HAMIK HARTOUNIAN
METHANE-Barrier 9/18/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Shotcrete 9/27/2024 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 4/30/2025 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/9/2025 Corrections Issued HAMIK HARTOUNIAN
METHANE-Barrier 6/9/2025 Corrections Issued HAMIK HARTOUNIAN
METHANE-Subgrade 6/9/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/8/2025 Corrections Issued OSVALDO PARAMO
METHANE-Barrier 8/8/2025 No Access for Inspection OSVALDO PARAMO
METHANE-Subgrade 8/8/2025 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 8/13/2025 Partial Approval HAMIK HARTOUNIAN
Reinforced Concrete Frame 9/18/2025 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 9/18/2025 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/22/2025 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Barrier 12/22/2025 Not Ready for Inspection HAMIK HARTOUNIAN
METHANE-Subgrade 12/22/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 12/22/2025 Not Ready for Inspection HAMIK HARTOUNIAN