9000 W 3RD ST 90048

Certificate Information: 9000 W 3RD ST 90048

Application / Permit
14010-10003-01638
Plan Check / Job No.
B15LA09255
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING FOR (N) HIGH RISE APARTMENT BLDG (UNDER 14010-10000-01638)
Permit Issued
Issued on 4/28/2017
Issuing Office
Metro
Current Status
Permit Finaled on 9/14/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2015 APPLICANT
Assigned to Plan Check Engineer 7/9/2015 SUEN LIEU
Corrections Issued 7/15/2015 SUEN LIEU
Quality Review Completed 7/21/2015 CHARLES CHANG
Building Plans Picked Up 7/22/2015 APPLICANT
Applicant returned to address corrections 12/17/2015 SUEN LIEU
Plan Check Approved 4/11/2017 SUEN LIEU
Issued 4/28/2017 LADBS
Permit Finaled 9/14/2020 LARRY ARNICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/15/2017 PAMELA TENEZA
Work Adjacent to Public Way Cleared 4/4/2017 DAVID PEREZ
Encroachment in public way Cleared 4/5/2017 JACOB BIGLER
Stormwater Pollution Mitigatn Cleared 4/5/2017 RYAN HUDSON
Excavation more than 5-ft deep Cleared 4/11/2017 CALOSHA APPROVED

Contact Information

Engineer Contreras, Rene Daniel; Lic. No.: C59858 50 RACING WIND      IRVINE, CA 92614

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 6/5/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/6/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/7/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/8/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/9/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/12/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/13/2017 Conditional Approval GREGORY POMISH
Deputy Grading 6/14/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 6/14/2017 Conditional Approval GREGORY POMISH
Deputy Grading 6/15/2017 Conditional Approval DAVID BURKHEAD
Deputy Other (see comments) 6/15/2017 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 6/15/2017 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 6/15/2017 Conditional Approval DAVID BURKHEAD
Deputy Grading 6/16/2017 Conditional Approval DAVID BURKHEAD
Deputy Other (see comments) 6/16/2017 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 6/16/2017 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 6/16/2017 Conditional Approval DAVID BURKHEAD
Deputy Grading 6/19/2017 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 6/19/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/19/2017 Conditional Approval GREGORY POMISH
Deputy Grading 6/20/2017 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 6/20/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/20/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/5/2017 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 7/5/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/6/2017 Conditional Approval JEFFREY FULTON
Deputy Other (see comments) 7/6/2017 Conditional Approval JEFFREY FULTON
Deputy Grading 7/7/2017 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 7/7/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/10/2017 Conditional Approval GREGORY POMISH
Deputy Other (see comments) 7/10/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/17/2017 No Access for Inspection JONATHAN QUACH
Deputy Grading 7/18/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/19/2017 Partial Approval JONATHAN QUACH
Deputy Grading 7/20/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/21/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/25/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/26/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/27/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/28/2017 Conditional Approval GREGORY POMISH
Deputy Grading 7/31/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/1/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/2/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/3/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/4/2017 Conditional Approval ERNESTO CORRAL
Deputy Grading 8/14/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/15/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/16/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/16/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/17/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/17/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/18/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/21/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/21/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/22/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/22/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/23/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/24/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/24/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/25/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/25/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/28/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/28/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/28/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/29/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/29/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/29/2017 Conditional Approval GREGORY POMISH
Deputy Grading 8/30/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 8/30/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/30/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/31/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/1/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/6/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/6/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/7/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/7/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/8/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/8/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/11/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/11/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/12/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/12/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/12/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/13/2017 Conditional Approval NICK DANERI
Deputy Grading 9/14/2017 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 9/14/2017 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 9/14/2017 Conditional Approval DAVID BURKHEAD
Deputy Grading 9/15/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/15/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/15/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/18/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/18/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/19/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/19/2017 Conditional Approval GREGORY POMISH
Deputy Grading 9/20/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/20/2017 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 9/21/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/4/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/4/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/5/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/5/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/6/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/6/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/10/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/18/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/18/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/20/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/20/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/23/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/23/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/24/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/24/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/25/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/25/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/26/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/26/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/27/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/27/2017 Conditional Approval GREGORY POMISH
Deputy Grading 10/30/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/30/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/2/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/2/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/6/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/6/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/7/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/7/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/8/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/8/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/15/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/15/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/16/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/16/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/17/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/17/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/28/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/28/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/29/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/29/2017 Conditional Approval GREGORY POMISH
Deputy Grading 11/30/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/30/2017 Conditional Approval GREGORY POMISH
Deputy Grading 12/1/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/1/2017 Conditional Approval GREGORY POMISH
Deputy Grading 12/4/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 12/4/2017 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/8/2018 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 12/18/2018 Partial Approval GREGORY POMISH
Deputy Shotcrete 1/31/2020 Conditional Approval LARRY ARNICK