2806 N ASHLAND AVE 90031

Certificate Information: 2806 N ASHLAND AVE 90031

Application / Permit
14010-10000-04164
Plan Check / Job No.
B14LA17787
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 2/23/2017
Issuing Office
Metro
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2014 APPLICANT
Green Plans Picked Up 2/5/2015 APPLICANT
Assigned to Plan Check Engineer 2/12/2015 ERIC WONG
Corrections Issued 2/20/2015 ERIC WONG
Quality Review Completed 3/9/2015 BILL STUTSMAN
Building Plans Picked Up 3/12/2015 APPLICANT
Applicant returned to address corrections 4/9/2015 ERIC WONG
Applicant returned to address corrections 5/15/2015 ERIC WONG
Applicant returned to address corrections 6/5/2015 ERIC WONG
Applicant returned to address corrections 6/19/2015 ERIC WONG
Applicant returned to address corrections 5/20/2016 ERIC WONG
Plan Check Approved 5/25/2016 ERIC HUANG
Plan Check Approved 7/8/2016 ERIC HUANG
Plan Check Approved 2/23/2017 ERIC WONG
Issued 2/23/2017 LADBS
CofO in Progress 4/28/2022 OSVALDO PARAMO
CofO in Progress 4/28/2022 OSVALDO PARAMO
Permit Finaled 4/28/2022 DEROLD HAUFF
CofO Issued 4/28/2022 DEROLD HAUFF
Permit Finaled 4/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/31/2015 ARMENIA HERNANDEZ
Green Code Cleared 5/8/2015 MARTHA DIAZ
"D" conditions Cleared 6/19/2015 MARY RICHARDSON
"Q" conditions Cleared 6/19/2015 MARY RICHARDSON
Excavation more than 5-ft deep Cleared 8/3/2015 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 8/6/2015 KARAN PATEL
Hydrant and Access approval Cleared 9/4/2015 JOHN CONNEALLY
Low Impact Development Cleared 9/4/2015 VIJAY DESAI
Eng Process Fee Ord 176,300 Cleared 11/4/2015 JAMES MORALEZ
Roof/Waste drainage to street Cleared 11/4/2015 JAMES MORALEZ
Sewer availability Cleared 11/4/2015 JAMES MORALEZ
BHO/Hillside ordinance Cleared 1/13/2016 CHRISTINE SOTELO
BHO/Hillside ordinance Cleared 5/3/2016 CHRISTINE SOTELO
BHO/Hillside ordinance Cleared 5/3/2016 CHRISTINE SOTELO
BHO/Hillside ordinance Cleared 5/3/2016 CHRISTINE SOTELO
BHO/Hillside ordinance Cleared 5/3/2016 CHRISTINE SOTELO
Permit Cleared 5/3/2016 CHRISTINE SOTELO
Grading Pre-Inspection Cleared 5/20/2016 ERIC HUANG

Contact Information

Architect Herron, Elizabeth Anne; Lic. No.: C15167 935 W AVE 37      LOS ANGELES, CA 900653241
Contractor Owner-Builder       ,
Engineer Valencia, Leon; Lic. No.: S2107 5220 SANTA MONICA BLVD   SUITE 202    LOS ANGELES, CA 90029
Geologist Robles, Gustavo; Lic. No.: EG2422 981 W. ARROW HIGHWAY #191      SAN DIMAS, CA 91773

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/16/2017 Conditional Approval SALVADOR GONZALEZ
Footing/Foundation/Slab 4/26/2017 Approved OSVALDO PARAMO
Pre-Inspection 4/26/2017 Approved DOMINIC DANERI
Masonry Wall/Backfill 5/16/2017 Approved OSVALDO PARAMO
Pre-Inspection 5/17/2017 Partial Inspection DOMINIC DANERI
Excavation/Setback/Form/Re-Bar 5/26/2017 Approved OSVALDO PARAMO
Masonry Wall/Backfill 5/26/2017 Approved OSVALDO PARAMO
Masonry Wall/Backfill 6/5/2017 Not Ready for Inspection OSVALDO PARAMO
Masonry Wall/Backfill 6/6/2017 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/24/2017 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 9/1/2017 Approved OSVALDO PARAMO
HVAC-Rough 9/1/2017 Approved OSVALDO PARAMO
PLUMBING-Rough 9/1/2017 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/6/2017 Not Ready for Inspection OSVALDO PARAMO
Pre-Inspection 9/6/2017 Partial Inspection DOMINIC DANERI
PLUMBING-Rough 9/13/2017 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 9/15/2017 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 9/19/2017 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 9/19/2017 Partial Inspection OSVALDO PARAMO
Pre-Inspection 9/19/2017 Partial Inspection DOMINIC DANERI
BUILDING-Rough-Frame 1/8/2018 Partial Inspection OSVALDO PARAMO
Green Building Rough 1/8/2018 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 1/8/2018 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/17/2018 Partial Inspection OSVALDO PARAMO
Insulation 2/9/2018 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/12/2018 Approved OSVALDO PARAMO
Drywall Nailing 2/28/2018 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/22/2018 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 3/23/2018 Approved OSVALDO PARAMO
ELECTRICAL-Final 5/8/2020 Partial Inspection HAMIK HARTOUNIAN
PLUMBING-Final 5/8/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/28/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/28/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 8/28/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 8/28/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 10/7/2020 Not Ready for Inspection OSVALDO PARAMO
Sewer 10/7/2020 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Final 7/1/2021 Corrections Issued DAVID FEILER
PLUMBING-Final 7/1/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Final 7/16/2021 Partial Inspection OSVALDO PARAMO
PLUMBING-Final 7/16/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 8/23/2021 Partial Approval OSVALDO PARAMO
HVAC-Final 8/23/2021 Partial Approval OSVALDO PARAMO
Pre-Inspection 11/29/2021 Corrections Issued OSVALDO PARAMO
Final 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 12/1/2021 Not Ready for Inspection OSVALDO PARAMO
Final 12/13/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 12/13/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved OSVALDO PARAMO
Service/Power Release 12/13/2021 Partial Inspection OSVALDO PARAMO
Smoke Detectors 12/13/2021 Approved OSVALDO PARAMO
Final 4/18/2022 Not Ready for Inspection OSVALDO PARAMO
Final 4/26/2022 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 4/26/2022 Approved OSVALDO PARAMO