7225 LUCKY WAY 91042
Certificate Information: 7225 LUCKY WAY 91042
- Application / Permit
- 14010-10000-03565
- Plan Check / Job No.
- B14LA15277
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY, SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 5/4/2016
- Issuing Office
- Valley
- Current Status
- Issued on 5/4/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2014 | JESSE CARDOZA |
| Corrections Issued | 12/22/2014 | JESSE CARDOZA |
| Green Plans Picked Up | 12/30/2014 | APPLICANT |
| Quality Review Completed | 12/31/2014 | BILL STUTSMAN |
| Building Plans Picked Up | 1/13/2015 | APPLICANT |
| Applicant returned to address corrections | 5/20/2015 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/28/2015 | EUGENE BARBEAU |
| Plan Check Approved | 6/4/2015 | EUGENE BARBEAU |
| Issued | 5/4/2016 | LADBS |
| Permit Expired-Status Void | 7/20/2018 | ANTHONY GIANNINI |
| Re-Activate Permit | 10/11/2018 | ANTHONY GIANNINI |
Permit Application Clearance Information
| Private street | Cleared | 4/8/2015 | LAURA FRAZIN-STEELE |
| Tract Map conditions | Cleared | 4/8/2015 | LAURA FRAZIN-STEELE |
| Green Code | Cleared | 5/1/2015 | MARCUS LEVIAS |
| Grading Pre-Inspection | Cleared | 5/6/2015 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 5/6/2015 | ROBERT DUFF |
| Address approval | Cleared | 5/8/2015 | KARAN PATEL |
| Low Impact Development | Cleared | 5/8/2015 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/8/2015 | KARAN PATEL |
| Sewer availability | Cleared | 5/8/2015 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2015 | VALENTINO PUEBLOS |
| Miscellaneous | Cleared | 5/28/2015 | JESSE CARDOZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Henderson, Allan Phillip; Lic. No.: GE391 | 1965 AIRPORT DR BAKERSFIELD, CA 93308 |
| Engineer | Mnatsakanyan, Arthur; Lic. No.: C74802 | 409 W BROADWAY GLENDALE, CA 91204 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/11/2016 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 11/2/2016 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 11/3/2016 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 11/16/2016 | Partial Approval | COREY HUPP |
| Green Building Rough | 11/16/2016 | Not Ready for Inspection | COREY HUPP |
| Verify Sprinkler Sign Off | 11/16/2016 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2016 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2017 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 2/9/2018 | Partial Inspection | BEAU COLLINS |
| Interior/Exterior Lathing | 3/16/2018 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 6/4/2018 | No Access for Inspection | ROLLIN GETTLE III |
| Green Building Rough | 6/4/2018 | No Access for Inspection | ROLLIN GETTLE III |
| Verify Sprinkler Sign Off | 6/4/2018 | No Access for Inspection | ROLLIN GETTLE III |
| Special/Order Compliance | 7/20/2018 | Permit Expired-Status Void | ANTHONY GIANNINI |
| Pre-Inspection | 10/15/2018 | Partial Inspection | BEAU COLLINS |
| Wood Frame | 12/7/2018 | Conditional Approval | BEAU COLLINS |
| PLUMBING-Rough | 3/8/2019 | Corrections Issued | BEAU COLLINS |
| Special/Order Compliance | 8/6/2019 | Partial Inspection | ROBERT MINASSIANS |
| Masonry Wall/Backfill | 9/11/2019 | Partial Approval | BRIAN MILLER |
| PLUMBING-Rough | 9/25/2019 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/1/2019 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/1/2019 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/1/2019 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/1/2019 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 10/1/2019 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/1/2019 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/1/2019 | Approved | MATTHEW NELSON |
| Insulation | 10/23/2019 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/18/2019 | Corrections Issued | BEAU COLLINS |
| Drywall Nailing | 9/8/2020 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/8/2020 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Not Ready | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Drywall Nailing | 3/24/2022 | Partial Approval | MATTHEW NELSON |
| Final | 3/24/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/24/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 3/24/2022 | Partial Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 3/24/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 3/24/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 8/12/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 8/12/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 8/12/2022 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 8/12/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 8/12/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 5/28/2024 | Not Ready for Inspection | DAVID MATSON |
| Final | 5/28/2024 | Corrections Issued | DAVID MATSON |
| Green Building Final | 5/28/2024 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Not Ready | DAVID MATSON |
| Service/Power Release | 5/28/2024 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 5/28/2024 | Not Ready for Inspection | DAVID MATSON |
| Special/Order Compliance | 6/27/2024 | Corrections Issued | WILLIAM WREN |
| Special/Order Compliance | 7/30/2024 | Approved | DAVID MATSON |
| Special/Order Compliance | 8/15/2024 | Partial Inspection | WILLIAM WREN |