3624 W BRUNSWICK AVE 90039

Certificate Information: 3624 W BRUNSWICK AVE 90039

Application / Permit
14010-10000-02761
Plan Check / Job No.
B14LA11617
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW GARAGE W/ RECROOM ABOVE 478 SQ
Permit Issued
Issued on 4/1/2015
Issuing Office
Valley
Current Status
Issued on 4/1/2015
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/26/2014 APPLICANT
Assigned to Plan Check Engineer 9/11/2014 MANUEL GARCIA
Corrections Issued 9/16/2014 MANUEL GARCIA
Quality Review Completed 9/18/2014 LAWRENCE QUIRANTE
Building Plans Picked Up 9/22/2014 APPLICANT
Green Plans Picked Up 9/22/2014 APPLICANT
Plan Check Approved 3/9/2015 MANUEL GARCIA
Issued 4/1/2015 LADBS

Permit Application Clearance Information

Green Code Cleared 1/8/2015 MARCUS LEVIAS
Roof/Waste drainage to street Cleared 1/21/2015 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 1/23/2015 JAMES MORALEZ
ZI Cleared 2/10/2015 ANDY RODRIGUEZ
Low Impact Development Cleared 2/12/2015 AMMAR ELTAWIL

Contact Information

Contractor Murillo Sergio; Lic. No.: 860668-B 8613 MILLERGROVE DRIVE      WHITTIER, CA 90606

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/16/2015 Not Ready for Inspection RONALD COWAN
Deputy Drilled-In Anchors 5/18/2015 Approved RONALD COWAN
Footing/Foundation/Slab 5/22/2015 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 6/2/2015 No Access for Inspection RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 8/20/2015 Approved DOMINIC DANERI
BUILDING-Rough-Frame 8/26/2015 Corrections Issued RONALD COWAN
Green Building Rough 8/26/2015 Approved RONALD COWAN
Rough-Elec/Plmb/HVAC 8/26/2015 Approved RONALD COWAN
ELECTRICAL-Rough 10/2/2015 Not Ready for Inspection RONALD COWAN
Interior/Exterior Lathing 10/7/2015 Approved RONALD COWAN
Drywall Nailing 10/13/2015 Approved RONALD COWAN
BUILDING-Rough-Frame 4/21/2017 No Access for Inspection LUIS ALVAREZ
Final 4/21/2017 Not Ready for Inspection LUIS ALVAREZ
Green Building Final 4/21/2017 No Access for Inspection LUIS ALVAREZ
SGSOV-Seismic Gas S/O Valve 4/21/2017 SGSOV Not Ready LUIS ALVAREZ
Smoke Detectors 4/21/2017 No Access for Inspection LUIS ALVAREZ
Pre-Inspection 3/12/2024 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 5/22/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 9/20/2024 Approved THOMAS LOGRASSO
Final 9/20/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 9/20/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 9/20/2024 Approved THOMAS LOGRASSO