3624 W BRUNSWICK AVE 90039
Certificate Information: 3624 W BRUNSWICK AVE 90039
- Application / Permit
- 14010-10000-02761
- Plan Check / Job No.
- B14LA11617
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW GARAGE W/ RECROOM ABOVE 478 SQ
- Permit Issued
- Issued on 4/1/2015
- Issuing Office
- Valley
- Current Status
- Issued on 4/1/2015
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2014 | MANUEL GARCIA |
| Corrections Issued | 9/16/2014 | MANUEL GARCIA |
| Quality Review Completed | 9/18/2014 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/22/2014 | APPLICANT |
| Green Plans Picked Up | 9/22/2014 | APPLICANT |
| Plan Check Approved | 3/9/2015 | MANUEL GARCIA |
| Issued | 4/1/2015 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 1/8/2015 | MARCUS LEVIAS |
| Roof/Waste drainage to street | Cleared | 1/21/2015 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2015 | JAMES MORALEZ |
| ZI | Cleared | 2/10/2015 | ANDY RODRIGUEZ |
| Low Impact Development | Cleared | 2/12/2015 | AMMAR ELTAWIL |
Contact Information
| Contractor | Murillo Sergio; Lic. No.: 860668-B | 8613 MILLERGROVE DRIVE WHITTIER, CA 90606 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2015 | Not Ready for Inspection | RONALD COWAN |
| Deputy Drilled-In Anchors | 5/18/2015 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 5/22/2015 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2015 | No Access for Inspection | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2015 | Approved | DOMINIC DANERI |
| BUILDING-Rough-Frame | 8/26/2015 | Corrections Issued | RONALD COWAN |
| Green Building Rough | 8/26/2015 | Approved | RONALD COWAN |
| Rough-Elec/Plmb/HVAC | 8/26/2015 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 10/2/2015 | Not Ready for Inspection | RONALD COWAN |
| Interior/Exterior Lathing | 10/7/2015 | Approved | RONALD COWAN |
| Drywall Nailing | 10/13/2015 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 4/21/2017 | No Access for Inspection | LUIS ALVAREZ |
| Final | 4/21/2017 | Not Ready for Inspection | LUIS ALVAREZ |
| Green Building Final | 4/21/2017 | No Access for Inspection | LUIS ALVAREZ |
| SGSOV-Seismic Gas S/O Valve | 4/21/2017 | SGSOV Not Ready | LUIS ALVAREZ |
| Smoke Detectors | 4/21/2017 | No Access for Inspection | LUIS ALVAREZ |
| Pre-Inspection | 3/12/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Special/Order Compliance | 5/22/2024 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | THOMAS LOGRASSO |
| Final | 9/20/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 9/20/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 9/20/2024 | Approved | THOMAS LOGRASSO |