1839 S PANDORA AVE 1-4 90025
Certificate Information: 1839 S PANDORA AVE 1-4 90025
- Application / Permit
- 14010-10000-02207
- Plan Check / Job No.
- B14LA08898
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment House
- Work Description
- NEW FIVE- STORY TYPE III-B APARTMENT BUILDING OVER ONE LEVEL , TYPE 1-B , SUBTERRANEAN PARKING GARAGE .
- Permit Issued
- Issued on 4/27/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2014 | APPLICANT |
| Green Plans Picked Up | 8/19/2014 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2014 | JESSE CARDOZA |
| Corrections Issued | 9/4/2014 | JESSE CARDOZA |
| Disabled Access Plans Picked Up | 9/11/2014 | APPLICANT |
| Quality Review Completed | 9/18/2014 | BILL STUTSMAN |
| Building Plans Picked Up | 9/24/2014 | APPLICANT |
| Plan Check Approved | 4/27/2017 | GEORGE BANNING |
| Issued | 4/27/2017 | LADBS |
| CofO in Progress | 11/1/2021 | DERRICK SPENCER |
| Permit Finaled | 2/15/2022 | DAVID TSAU |
| CofO Issued | 2/15/2022 | DAVID TSAU |
| Permit Finaled | 2/15/2022 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2016 | VALENTINO PUEBLOS |
| Building over 3-story or 36-ft | Cleared | 9/29/2016 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 9/29/2016 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 10/3/2016 | JESSE CARDOZA |
| Miscellaneous | Cleared | 11/30/2016 | JESSE CARDOZA |
| Low Impact Development | Cleared | 12/27/2016 | SAM NAVID |
| Hydrant and Access approval | Cleared | 12/28/2016 | ROBERT DUFF |
| DAS Clearance | Cleared | 4/7/2017 | EDDIE GARIN |
| Fire Marshall Fire Life Safety | Cleared | 4/11/2017 | ANDREW KO |
| Green Code | Cleared | 4/18/2017 | ALDO UBAU |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2017 | JACOB BIGLER |
| Roof/Waste drainage to street | Cleared | 4/19/2017 | JACOB BIGLER |
| Sewer availability | Cleared | 4/19/2017 | JACOB BIGLER |
| Frnt yard landscape/Water mgmt | Cleared | 4/20/2017 | JUSTIN BILOW |
| Miscellaneous | Cleared | 4/25/2017 | JESSE CARDOZA |
| Miscellaneous | Cleared | 4/25/2017 | JESSE CARDOZA |
| Specific Plan | Cleared | 4/25/2017 | EDER ROMERO |
Contact Information
| Architect | Poindexter, John Roger; Lic. No.: C9744 | 1059 ONEONTA DR LOS ANGELES, CA 90065 |
| Contractor | Owner-Builder | , |
| Engineer | Lee, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
| Engineer | Tzeng, Charles Chau-Jyi; Lic. No.: C34005 | PO BOX 5044 PASADENA, CA 91117 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/17/2017 | Not Ready for Inspection | SORIN CIRSTOIU |
| Deputy Grading | 5/22/2017 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 5/22/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/23/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/24/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/25/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/26/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/30/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/2/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/5/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/6/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/7/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/15/2017 | Approved | TONY HARTONO |
| Deputy Reinf. Concrete | 6/23/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/24/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/25/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/30/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/5/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/6/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/7/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 9/8/2017 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 11/16/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/27/2017 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 1/30/2018 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 1/31/2018 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 2/1/2018 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/18/2018 | Approved | DERRICK SPENCER |
| Green Building Rough | 8/7/2018 | Not Ready for Inspection | DERRICK SPENCER |
| METHANE-Rough | 8/7/2018 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 8/7/2018 | Approved | DERRICK SPENCER |
| Wood Frame | 8/7/2018 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/10/2018 | Partial Approval | DERRICK SPENCER |
| METHANE-Barrier | 8/10/2018 | Approved | DERRICK SPENCER |
| METHANE-Subgrade | 8/10/2018 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2018 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 9/13/2018 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 9/13/2018 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2018 | Conditional Approval | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2018 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 10/16/2018 | Approved | DERRICK SPENCER |
| Insulation | 10/16/2018 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 10/16/2018 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 10/16/2018 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 10/16/2018 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 10/23/2018 | Not Ready for Inspection | DERRICK SPENCER |
| Insulation | 10/23/2018 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 10/23/2018 | Approved | DERRICK SPENCER |
| Pre-Inspection | 11/2/2018 | Approved | DERRICK SPENCER |
| Wood Frame | 11/2/2018 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 11/5/2018 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 11/27/2018 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/7/2018 | Approved | DERRICK SPENCER |
| Insulation | 12/10/2018 | Partial Approval | SORIN CIRSTOIU |
| Pre-Inspection | 12/12/2018 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 12/19/2018 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2018 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/20/2018 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/24/2018 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/2/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/14/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/17/2019 | Approved | DERRICK SPENCER |
| Insulation | 1/18/2019 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 1/22/2019 | Approved | DERRICK SPENCER |
| Deputy Wood Construction | 1/23/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/24/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/28/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 2/6/2019 | Approved | DERRICK SPENCER |
| Drywall Nailing | 2/14/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 2/21/2019 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 3/11/2019 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 3/19/2019 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 3/21/2019 | Approved | DERRICK SPENCER |
| Drywall Nailing | 3/27/2019 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 3/27/2019 | Approved | DERRICK SPENCER |
| Drywall Nailing | 4/9/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 4/23/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 5/30/2019 | Approved | DERRICK SPENCER |
| Final | 6/14/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/14/2019 | Approved | DERRICK SPENCER |
| Green Building Final | 6/14/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Reinforced Concrete Frame | 6/14/2019 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 6/14/2019 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 6/14/2019 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 6/14/2019 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 6/14/2019 | Approved | DERRICK SPENCER |
| Wood Frame | 6/14/2019 | Approved | DERRICK SPENCER |
| Final | 6/19/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 6/19/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Special/Order Compliance | 6/19/2020 | Approved | DERRICK SPENCER |
| Final | 12/3/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 12/3/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Verify Rec and Parks Fee Memo | 12/30/2020 | Approved | DERRICK SPENCER |
| Final | 2/5/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 2/5/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 5/25/2021 | OK to Issue CofO | DERRICK SPENCER |
| Green Building Final | 5/25/2021 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 5/25/2021 | Approved | DERRICK SPENCER |