5875 W INTERCEPTOR ST 1-61 90045

Certificate Information: 5875 W INTERCEPTOR ST 1-61 90045

Application / Permit
14010-10000-01651
Plan Check / Job No.
B14LA07237
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4-story 61 unit apartment over 2 levels of subterranean parking.
Permit Issued
Issued on 2/23/2016
Issuing Office
Valley
Current Status
CofO Issued on 8/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2014 APPLICANT
Assigned to Plan Check Engineer 6/5/2014 ALLEN MANALANSAN
Disabled Access Plans Picked Up 6/11/2014 APPLICANT
Green Plans Picked Up 6/12/2014 APPLICANT
Corrections Issued 6/26/2014 ALLEN MANALANSAN
Quality Review Completed 7/11/2014 CHARLES CHANG
Building Plans Picked Up 7/11/2014 APPLICANT
Applicant returned to address corrections 9/15/2014 ALLEN MANALANSAN
Applicant returned to address corrections 11/14/2014 ALLEN MANALANSAN
Applicant returned to address corrections 11/24/2014 ALLEN MANALANSAN
Applicant returned to address corrections 12/2/2014 ALLEN MANALANSAN
Applicant returned to address corrections 12/11/2014 ALLEN MANALANSAN
Applicant returned to address corrections 7/10/2015 ALLEN MANALANSAN
Plan Check Approved 8/3/2015 ALLEN MANALANSAN
Issued 2/23/2016 LADBS
TCO Issued (Expire Date: 01-10-2021) 7/14/2020 NICK LAROCCA
TCO Issued (Expire Date: 06-15-2021) 12/17/2020 NICK LAROCCA
TCO Issued (Expire Date: 12-12-2021) 6/15/2021 NICK LAROCCA
CofO in Progress 8/18/2021 NICK LAROCCA
Permit Finaled 8/18/2021 HENRY BAGHDASSARIAN
CofO Issued 8/18/2021 HENRY BAGHDASSARIAN
Permit Finaled 8/18/2021 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 7/22/2014 AVALYN KAMACHI
Permit Cleared 7/22/2014 AVALYN KAMACHI
Site Plan review Cleared 11/5/2014 HERMAN VAN BUREN
ZA Case Cleared 11/5/2014 HERMAN VAN BUREN
ZI Cleared 11/5/2014 HERMAN VAN BUREN
Sewer availability Cleared 11/24/2014 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 11/25/2014 ARMENIA HERNANDEZ
Green Code Cleared 11/25/2014 ALDO UBAU
Highway dedication Cleared 11/25/2014 ARMENIA HERNANDEZ
Miscellaneous Cleared 1/21/2015 VANESSA SOTO
Opn space landscape/Water mgmt Cleared 1/21/2015 VANESSA SOTO
Construction within easement Cleared 2/12/2015 LUCIO FERRER
Specific Plan Cleared 2/27/2015 CLIVE GRAWE
Hydrant and Access approval Cleared 3/18/2015 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 3/24/2015 ANDREW KO
Work Adjacent to Public Way Cleared 3/31/2015 OSCAR GUTIERREZ
DAS Clearance Cleared 4/9/2015 WAI LAU
Low Impact Development Cleared 6/24/2015 IDA MEISAMI-FARD
Stormwater Pollution Mitigatn Cleared 6/24/2015 IDA MEISAMI-FARD
Miscellaneous Cleared 6/25/2015 PHONG NGUYEN
Roof/Waste drainage to street Cleared 6/25/2015 PHONG NGUYEN
Building over 3-story or 36-ft Cleared 8/3/2015 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/3/2015 CALOSHA APPROVED

Contact Information

Architect Moses, Jacob; Lic. No.: C15827 5103 ALDEA AVENUE      ENCINO, CA 91316
Contractor Frymer Construction; Lic. No.: 860661-B 2461 SANTA MONICA BLVD 134      SANTA MONICA, CA 90404
Engineer Cazeneuve, Michael Allan; Lic. No.: C71490 235 E FOOTHILLL BL J      MONROVIA, CA 91016
Engineer Horning, Joshua David; Lic. No.: C81664 6111 DREXEL AVENUE      LOS ANGELES, CA 90036
Engineer Mehta, Babubhai Mohanlal; Lic. No.: S1924 19617 PINE VALLEY AVE      NORTHRIDGE, CA 91326
Engineer Mino, Gregory Isamu; Lic. No.: C65337 2108 CORSON ST      PASADENA, CA 91107

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 8/22/2016 Approved DERRICK SPENCER
Deputy Grading 8/23/2016 Approved DERRICK SPENCER
Deputy Reinf. Concrete 10/24/2016 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/24/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 10/25/2016 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 11/3/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 11/4/2016 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/7/2016 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/8/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 11/8/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 11/9/2016 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 11/9/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 11/21/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 11/21/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 11/22/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 11/28/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 11/29/2016 Approved NICK LAROCCA
Deputy Reinf. Concrete 11/30/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/1/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 12/1/2016 Not Ready for Inspection NICK LAROCCA
Deputy Shotcrete 12/2/2016 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 12/2/2016 Partial Approval NICK LAROCCA
Deputy Shotcrete 12/5/2016 Approved DERRICK SPENCER
Footing/Foundation/Slab 12/5/2016 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 12/6/2016 Approved NICK LAROCCA
Deputy Reinf. Concrete 12/7/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 12/7/2016 Partial Approval NICK LAROCCA
Deputy Shotcrete 12/8/2016 Approved DERRICK SPENCER
Deputy Shotcrete 12/9/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 12/9/2016 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 12/12/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/12/2016 Approved NICK LAROCCA
Deputy Reinf. Masonry 12/13/2016 Approved NICK LAROCCA
Deputy Reinf. Masonry 12/14/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 12/14/2016 Partial Approval NICK LAROCCA
Deputy Shotcrete 12/15/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/16/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/19/2016 Approved NICK LAROCCA
Masonry Wall/Backfill 12/19/2016 Partial Inspection NICK LAROCCA
Deputy Shotcrete 12/20/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/21/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/22/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 12/22/2016 Partial Approval NICK LAROCCA
Deputy Shotcrete 12/23/2016 Conditional Approval JONATHAN ALLEN
Deputy Shotcrete 12/27/2016 Approved NICK LAROCCA
Deputy Shotcrete 12/28/2016 Approved NICK LAROCCA
Footing/Foundation/Slab 1/18/2017 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 1/20/2017 Partial Inspection NICK LAROCCA
Deputy Reinf. Concrete 1/30/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 1/31/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/3/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/6/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/7/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/8/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/9/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/9/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/10/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/13/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 2/14/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/15/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/15/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/16/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/16/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/17/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/17/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/21/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/21/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/22/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/22/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/23/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/23/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/24/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/24/2017 Approved NICK LAROCCA
Deputy Shotcrete 2/27/2017 Approved NICK LAROCCA
Deputy Reinf. Masonry 2/28/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/9/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/20/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/21/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/22/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/23/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/24/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 3/28/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/7/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/10/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/11/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/12/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 4/24/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/9/2017 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/23/2017 Approved NICK LAROCCA
Deputy Wood Construction 6/6/2017 Approved NICK LAROCCA
Deputy Wood Construction 7/20/2017 Approved NICK LAROCCA
Deputy Wood Construction 7/25/2017 Conditional Approval JONATHAN ALLEN
Deputy Wood Construction 8/10/2017 Conditional Approval JONATHAN ALLEN
Verify Sprinkler Sign Off 8/14/2017 Not Ready for Inspection NICK LAROCCA
Wood Frame 8/14/2017 Corrections Issued NICK LAROCCA
Green Building Rough 8/15/2017 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/17/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/18/2017 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/25/2017 Partial Inspection NICK LAROCCA
Deputy Wood Construction 8/28/2017 Approved NICK LAROCCA
Deputy Wood Construction 8/29/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/29/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 8/30/2017 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/7/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/12/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/13/2017 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/19/2017 Partial Approval NICK LAROCCA
Insulation 9/19/2017 Partial Approval NICK LAROCCA
Deputy Wood Construction 9/20/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/21/2017 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/22/2017 Not Ready for Inspection NICK LAROCCA
Verify Sprinkler Sign Off 9/26/2017 Not Ready for Inspection NICK LAROCCA
Wood Frame 9/26/2017 Not Ready for Inspection NICK LAROCCA
Wood Frame 9/27/2017 Corrections Issued NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/28/2017 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 9/29/2017 Approved NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 9/29/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/2/2017 Not Ready for Inspection NICK LAROCCA
Deputy Wood Construction 10/3/2017 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/4/2017 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/4/2017 Partial Inspection NICK LAROCCA
Deputy Wood Construction 10/5/2017 Approved NICK LAROCCA
Insulation 10/5/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/10/2017 Partial Approval JONATHAN ALLEN
Drywall Nailing 10/16/2017 Partial Inspection NICK LAROCCA
Insulation 10/16/2017 Not Ready for Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/17/2017 Partial Approval NICK LAROCCA
Insulation 10/17/2017 Partial Approval NICK LAROCCA
Insulation 10/18/2017 Partial Approval NICK LAROCCA
Insulation 10/26/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 10/27/2017 Partial Inspection NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 11/1/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 11/3/2017 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 11/6/2017 Partial Approval NICK LAROCCA
Insulation 11/21/2017 Partial Approval NICK LAROCCA
Insulation 12/5/2017 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 12/8/2017 Partial Approval DERRICK SPENCER
Green Building Rough 12/19/2017 Approved NICK LAROCCA
Interior/Exterior Lathing 12/19/2017 Approved NICK LAROCCA
Verify Sprinkler Sign Off 12/19/2017 Approved NICK LAROCCA
Wood Frame 12/19/2017 Not Ready for Inspection NICK LAROCCA
Wood Frame 12/22/2017 Partial Approval JONATHAN ALLEN
Wood Frame 12/27/2017 Partial Approval NICK LAROCCA
Insulation 1/3/2018 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 1/23/2018 Partial Approval NICK LAROCCA
Insulation 1/23/2018 Partial Approval NICK LAROCCA
Drywall Nailing 1/26/2018 Partial Approval NICK LAROCCA
Wood Frame 1/26/2018 Not Ready for Inspection NICK LAROCCA
Drywall Nailing 1/30/2018 Partial Approval NICK LAROCCA
Wood Frame 2/12/2018 Partial Approval NICK LAROCCA
Wood Frame 3/19/2018 Not Ready for Inspection JONATHAN ALLEN
Wood Frame 3/28/2018 Not Ready for Inspection DAVID TSAU
Wood Frame 4/2/2018 Partial Approval NICK LAROCCA
Wood Frame 4/4/2018 Not Ready for Inspection NICK LAROCCA
Insulation 4/19/2018 Not Ready for Inspection NICK LAROCCA
Deputy Drilled-In Anchors 4/27/2018 Approved NICK LAROCCA
Deputy Drilled-In Anchors 5/15/2018 Approved NICK LAROCCA
Masonry Wall/Backfill 5/17/2018 Not Ready for Inspection NICK LAROCCA
Reinforced Masonry Frame 5/21/2018 Partial Inspection NICK LAROCCA
Deputy Reinf. Concrete 6/5/2018 Approved NICK LAROCCA
Footing/Foundation/Slab 6/6/2018 Partial Approval NICK LAROCCA
Reinforced Masonry Frame 6/6/2018 Partial Approval NICK LAROCCA
Reinforced Masonry Frame 7/5/2018 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/12/2018 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 7/16/2018 Partial Approval NICK LAROCCA
Insulation 8/2/2018 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 8/3/2018 Conditional Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 8/6/2018 Partial Inspection NICK LAROCCA
Masonry Wall/Backfill 8/6/2018 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 8/17/2018 Partial Approval DERRICK SPENCER
Drywall Nailing 8/22/2018 Partial Approval DERRICK SPENCER
Drywall Nailing 8/23/2018 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 8/29/2018 Approved NICK LAROCCA
Deputy Reinf. Masonry 9/7/2018 Conditional Approval NICK LAROCCA
Masonry Wall/Backfill 9/7/2018 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 9/10/2018 Conditional Approval NICK LAROCCA
Wood Frame 9/10/2018 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 9/17/2018 Conditional Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 9/17/2018 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 9/17/2018 Partial Inspection NICK LAROCCA
Footing/Foundation/Slab 9/18/2018 Corrections Issued NICK LAROCCA
Deputy Reinf. Concrete 9/19/2018 Approved NICK LAROCCA
Special/Order Compliance 9/20/2018 Approved NICK LAROCCA
Deputy Reinf. Masonry 9/24/2018 Conditional Approval NICK LAROCCA
Masonry Wall/Backfill 9/24/2018 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 9/25/2018 Approved NICK LAROCCA
Insulation 9/27/2018 Partial Approval NICK LAROCCA
Drywall Nailing 10/1/2018 Partial Approval NICK LAROCCA
Deputy Reinf. Masonry 10/2/2018 Approved NICK LAROCCA
Deputy Reinf. Masonry 10/3/2018 Approved DERRICK SPENCER
Masonry Wall/Backfill 10/3/2018 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 10/4/2018 Approved DERRICK SPENCER
Deputy Reinf. Masonry 10/5/2018 Approved NICK LAROCCA
Deputy Reinf. Masonry 10/9/2018 Approved NICK LAROCCA
Masonry Wall/Backfill 10/9/2018 Partial Approval NICK LAROCCA
Deputy Steel/Welding 10/30/2018 Approved NICK LAROCCA
Insulation 10/31/2018 Partial Approval NICK LAROCCA
Deputy Steel/Welding 11/1/2018 Approved NICK LAROCCA
Deputy Steel/Welding 11/5/2018 Approved NICK LAROCCA
Drywall Nailing 11/7/2018 Partial Approval NICK LAROCCA
Insulation 11/20/2018 Partial Approval NICK LAROCCA
Light Gage Steel Frame 11/26/2018 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 11/29/2018 Not Ready for Inspection NICK LAROCCA
Drywall Nailing 11/30/2018 Partial Approval NICK LAROCCA
Insulation 11/30/2018 Not Ready for Inspection NICK LAROCCA
Insulation 12/3/2018 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 12/4/2018 Partial Approval NICK LAROCCA
Insulation 12/6/2018 Partial Approval NICK LAROCCA
Insulation 12/7/2018 Partial Approval NICK LAROCCA
Insulation 12/12/2018 Partial Approval NICK LAROCCA
Drywall Nailing 12/13/2018 Partial Approval NICK LAROCCA
Insulation 12/17/2018 Approved NICK LAROCCA
Drywall Nailing 12/20/2018 Partial Approval DERRICK SPENCER
Insulation 1/4/2019 Approved NICK LAROCCA
Drywall Nailing 1/9/2019 Approved NICK LAROCCA
Light Gage Steel Frame 3/5/2019 Not Ready for Inspection NICK LAROCCA
Light Gage Steel Frame 3/7/2019 Partial Approval NICK LAROCCA
Interior/Exterior Lathing 3/18/2019 Approved NICK LAROCCA
Light Gage Steel Frame 3/19/2019 Approved NICK LAROCCA
Drywall Nailing 3/26/2019 Approved NICK LAROCCA
Light Gage Steel Frame 3/29/2019 Approved NICK LAROCCA
Footing/Foundation/Slab 5/10/2019 Partial Approval NICK LAROCCA
Deputy Shotcrete 5/21/2019 Approved NICK LAROCCA
Deputy Drilled-In Anchors 3/12/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/13/2020 Approved NICK LAROCCA
Deputy Reinf. Masonry 3/16/2020 Approved DERRICK SPENCER
Final 6/10/2020 OK to Issue CofO NICK LAROCCA
Footing/Foundation/Slab 6/10/2020 Approved NICK LAROCCA
Green Building Final 6/10/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 6/10/2020 Approved NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Approved NICK LAROCCA
Smoke Detectors 6/10/2020 Approved NICK LAROCCA
Structural Steel Frame 6/10/2020 Approved NICK LAROCCA
Wood Frame 6/10/2020 Approved NICK LAROCCA
Special/Order Compliance 12/16/2020 Approved NICK LAROCCA
Special/Order Compliance 5/19/2021 Approved NICK LAROCCA