1521 N KILLARNEY AVE 90065
Certificate Information: 1521 N KILLARNEY AVE 90065
- Application / Permit
- 14010-10000-01519
- Plan Check / Job No.
- B14LA06488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 2/9/2017
- Issuing Office
- Metro
- Current Status
- Issued on 2/9/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 5/19/2014 | APPLICANT |
Assigned to Plan Check Engineer | 5/22/2014 | ERIC WONG |
Corrections Issued | 5/30/2014 | ERIC WONG |
Quality Review Completed | 6/6/2014 | GARO TELMI |
Building Plans Picked Up | 6/6/2014 | APPLICANT |
Green Plans Picked Up | 6/12/2014 | APPLICANT |
Applicant returned to address corrections | 9/29/2016 | ERIC WONG |
Applicant returned to address corrections | 12/14/2016 | ERIC WONG |
Plan Check Approved | 1/30/2017 | ERIC WONG |
Issued | 2/9/2017 | LADBS |
Permit Application Clearance Information
Address approval | Cleared | 12/9/2015 | HOWARD COOPER |
Permit | Cleared | 12/10/2015 | ARMENIA AGUILAR |
Green Code | Cleared | 4/14/2016 | RUSSELL KELLY |
Low Impact Development | Cleared | 4/20/2016 | MICHAEL SCADUTO |
Mailing Labels | Cleared | 4/22/2016 | ERIC HUANG |
Stormwater Pollution Mitigatn | Cleared | 5/12/2016 | SAM NAVID |
Hydrant and Access approval | Cleared | 9/13/2016 | ROBERT DUFF |
Sewer availability | Cleared | 9/13/2016 | RAVIL MANAPOV |
Specific Plan | Cleared | 9/23/2016 | MARITZA PRZEKOP |
ZA Case | Cleared | 9/23/2016 | MARITZA PRZEKOP |
Miscellaneous | Cleared | 9/30/2016 | CARLOS CUEVA |
BHO/Hillside ordinance | Cleared | 10/7/2016 | ALFREDO JARA |
BHO/Hillside ordinance | Cleared | 10/7/2016 | ALFREDO JARA |
BHO/Hillside ordinance | Cleared | 10/7/2016 | ARMENIA AGUILAR |
Eng Process Fee Ord 176,300 | Cleared | 10/7/2016 | ALFREDO JARA |
Grading Pre-Inspection | Cleared | 10/11/2016 | ERIC HUANG |
Roof/Waste drainage to street | Cleared | 10/11/2016 | ARMENIA AGUILAR |
BHO/Hillside ordinance | Cleared | 11/14/2016 | RAVIL MANAPOV |
Contact Information
Architect | Grist, John Kenneth; Lic. No.: C4295 | 91 EAST GRAND VIEW AVENUE SIERRA MADRE, CA 91024 |
Contractor | Owner-Builder | , |
Engineer | Robles, Gustavo; Lic. No.: C66797 | 981 W ARROW HWY 191 SAN DIMAS, CA 91773 |
Geologist | Robles, Gustavo; Lic. No.: EG2422 | 981 W. ARROW HIGHWAY #191 SAN DIMAS, CA 91773 |
Inspector Information
ALIZAH MAYAGOITIA, (213) 202-3124 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 5/25/2017 | Partial Approval | LUIS ALVAREZ |
Excavation/Setback/Form/Re-Bar | 6/19/2017 | Partial Approval | LUIS ALVAREZ |
Excavation/Setback/Form/Re-Bar | 9/11/2017 | Partial Approval | LUIS BARRALES |
Masonry Wall/Backfill | 9/27/2017 | Partial Approval | LUIS BARRALES |
Excavation/Setback/Form/Re-Bar | 11/22/2017 | Partial Approval | LUIS BARRALES |
Footing/Foundation/Slab | 11/22/2017 | Partial Approval | LUIS BARRALES |
Excavation/Setback/Form/Re-Bar | 12/15/2017 | Partial Inspection | OSVALDO PARAMO |
Footing/Foundation/Slab | 2/23/2018 | Partial Inspection | OSVALDO PARAMO |
PLUMBING-Rough | 3/29/2018 | Partial Inspection | OSVALDO PARAMO |
Deputy Steel/Welding | 4/30/2018 | Conditional Approval | LUIS ALVAREZ |
Footing/Foundation/Slab | 5/1/2018 | Partial Approval | LUIS ALVAREZ |
Masonry Wall/Backfill | 5/31/2018 | Approved | LUIS ALVAREZ |
Floor/Roof Diaphrgm/Shear Wall | 9/27/2018 | Not Ready for Inspection | FRANCISCO MORADO |
Floor/Roof Diaphrgm/Shear Wall | 10/4/2018 | Partial Approval | OSVALDO PARAMO |
Floor/Roof Diaphrgm/Shear Wall | 10/5/2018 | Partial Approval | OSVALDO PARAMO |
ELECTRICAL-Rough | 11/7/2018 | Partial Approval | FRANCISCO MORADO |
HVAC-Rough | 11/7/2018 | Partial Approval | FRANCISCO MORADO |
PLUMBING-Rough | 11/13/2018 | Approved | FRANCISCO MORADO |
Deputy Wood Construction | 1/16/2019 | Partial Approval | SCOTT FINNILA |
BUILDING-Rough-Frame | 1/18/2019 | Partial Approval | CRAIG VAUGHAN |
Green Building Rough | 1/18/2019 | Approved | CRAIG VAUGHAN |
Verify Sprinkler Sign Off | 1/18/2019 | Partial Approval | CRAIG VAUGHAN |
Insulation | 3/4/2019 | Approved | CRAIG VAUGHAN |
Drywall Nailing | 5/2/2019 | Partial Inspection | OSVALDO PARAMO |
Drywall Nailing | 9/12/2019 | Corrections Issued | OSVALDO PARAMO |
Drywall Nailing | 10/25/2019 | Corrections Issued | OSVALDO PARAMO |
BUILDING-Rough-Frame | 2/18/2020 | Approved | OSVALDO PARAMO |
Drywall Nailing | 2/18/2020 | Approved | OSVALDO PARAMO |
Verify Sprinkler Sign Off | 2/18/2020 | Approved | OSVALDO PARAMO |
Shower Pan | 2/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
Interior/Exterior Lathing | 3/21/2023 | Partial Approval | OSVALDO PARAMO |
Sewer | 8/28/2023 | Approved | BRENDAN MORELLI |
Final | 11/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
Footing/Foundation/Slab | 11/22/2023 | Approved | OSVALDO PARAMO |
Green Building Final | 11/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Not Ready | OSVALDO PARAMO |
Smoke Detectors | 11/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
ELECTRICAL-Final | 11/29/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
HVAC-Final | 11/29/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
PLUMBING-Final | 11/29/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
ELECTRICAL-Final | 12/1/2023 | Corrections Issued | OSVALDO PARAMO |
HVAC-Final | 12/1/2023 | Corrections Issued | OSVALDO PARAMO |
PLUMBING-Final | 12/1/2023 | Corrections Issued | OSVALDO PARAMO |
Special/Order Compliance | 5/1/2024 | Partial Inspection | OSVALDO PARAMO |