444 N MUSEUM DR 90065

Certificate Information: 444 N MUSEUM DR 90065

Application / Permit
14010-10000-01236
Plan Check / Job No.
B14LA05073
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE PER MT. WASHINGTON/GLASSELL PARK S.P. SEE PERMIT 14020-10000-00968 FOR SITE RETAINING WALLS, 15020-10000-01700 FOR SHORING AND 14030-10000-02190 FOR GRADING WORK.
Permit Issued
Issued on 9/14/2015
Issuing Office
Valley
Current Status
CofO Issued on 6/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2014 APPLICANT
Assigned to Plan Check Engineer 5/9/2014 LAWRENCE QUIRANTE
Corrections Issued 5/20/2014 ANKIT PATEL
Quality Review Completed 5/23/2014 GARO TELMI
Building Plans Picked Up 5/29/2014 APPLICANT
Green Plans Picked Up 5/29/2014 APPLICANT
Applicant returned to address corrections 1/28/2015 ANKIT PATEL
Applicant returned to address corrections 3/3/2015 ANKIT PATEL
Applicant returned to address corrections 6/23/2015 LAWRENCE QUIRANTE
Plan Check Approved 7/2/2015 LAWRENCE QUIRANTE
Issued 9/14/2015 LADBS
CofO in Progress 6/13/2024 OSVALDO PARAMO
Permit Finaled 6/17/2024 DEROLD HAUFF
CofO Issued 6/17/2024 DEROLD HAUFF
Permit Finaled 6/17/2024 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/14/2015 JOSHUA LOPEZ
BHO/Hillside ordinance Cleared 1/14/2015 JOSHUA LOPEZ
BHO/Hillside ordinance Cleared 1/14/2015 JOSHUA LOPEZ
BHO/Hillside ordinance Cleared 1/14/2015 JOSHUA LOPEZ
Green Code Cleared 1/26/2015 MARCUS LEVIAS
Eng Process Fee Ord 176,300 Cleared 1/28/2015 KARAN PATEL
Hydrant and Access approval Cleared 1/28/2015 JOHN DALLAS
Sewer availability Cleared 1/28/2015 KARAN PATEL
Mailing Labels Cleared 3/3/2015 LAWRENCE QUIRANTE
Low Impact Development Cleared 4/6/2015 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 6/5/2015 JAMES MORALEZ
Miscellaneous Cleared 6/10/2015 ANDY RODRIGUEZ
Specific Plan Cleared 6/10/2015 ANDY RODRIGUEZ
ZA Case Cleared 6/10/2015 ANDY RODRIGUEZ
BHO/Hillside ordinance Cleared 6/11/2015 RICHARD SOUTHERLAND
Address approval Cleared 6/23/2015 RICHARD SOUTHERLAND

Contact Information

Contractor Qualified Builders; Lic. No.: 636722-B 335 E ALBERTONI ST STE 200-617      CARSON, CA 90746
Engineer Simonian, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205
Engineer Tsai, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/17/2015 Partial Inspection RONALD COWAN
Piling/Pier/Caisson 1/12/2016 Not Ready for Inspection RONALD COWAN
Piling/Pier/Caisson 5/11/2016 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 9/23/2016 Partial Approval SALVADOR GONZALEZ
Excavation/Setback/Form/Re-Bar 11/30/2016 Partial Approval LUIS ALVAREZ
Green Building Rough 11/30/2016 Not Ready for Inspection LUIS ALVAREZ
Masonry Wall/Backfill 11/30/2016 Not Ready for Inspection LUIS ALVAREZ
Pre-Inspection 11/30/2016 Approved LUIS ALVAREZ
Structural Steel Frame 11/30/2016 Not Ready for Inspection LUIS ALVAREZ
Verify Sprinkler Sign Off 11/30/2016 Not Ready for Inspection LUIS ALVAREZ
Pre-Inspection 1/30/2017 Approved LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 3/17/2017 Partial Approval LUIS ALVAREZ
Footing/Foundation/Slab 3/17/2017 Partial Approval LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 4/18/2017 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 4/18/2017 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/20/2017 Partial Approval LUIS ALVAREZ
Footing/Foundation/Slab 4/20/2017 Partial Approval LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 5/12/2017 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/12/2017 Partial Approval SCOTT FINNILA
PLUMBING-Rough 6/16/2017 Partial Approval LUIS ALVAREZ
PLUMBING-Rough 6/27/2017 Partial Approval LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 7/17/2017 Partial Approval MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 10/13/2017 Approved LUIS ALVAREZ
Structural Steel Frame 10/13/2017 Not Ready for Inspection LUIS ALVAREZ
Wood Frame 10/13/2017 Partial Approval LUIS ALVAREZ
Excavation/Setback/Form/Re-Bar 1/25/2018 Not Ready for Inspection OSVALDO PARAMO
Special/Order Compliance 4/4/2019 Partial Inspection RUBEN SALAS
Deputy Wood Construction 5/20/2019 Approved OSVALDO PARAMO
Special/Order Compliance 6/14/2019 Partial Inspection RUBEN SALAS
BUILDING-Rough-Frame 7/2/2019 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/2/2019 Partial Inspection OSVALDO PARAMO
Green Building Rough 7/2/2019 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 7/2/2019 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 8/26/2019 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 10/15/2019 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 10/30/2019 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 11/5/2019 Corrections Issued OSVALDO PARAMO
Green Building Rough 11/5/2019 Approved OSVALDO PARAMO
PLUMBING-Rough 11/5/2019 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 11/5/2019 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/17/2019 Approved OSVALDO PARAMO
Insulation 12/17/2019 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/3/2020 Approved OSVALDO PARAMO
Special/Order Compliance 8/11/2020 Approved DAVID MATSON
Drywall Nailing 10/5/2020 Partial Inspection RUBEN SALAS
Final 10/5/2020 Partial Inspection RUBEN SALAS
Footing/Foundation/Slab 10/5/2020 Partial Inspection RUBEN SALAS
Green Building Final 10/5/2020 Partial Inspection RUBEN SALAS
Reinforced Concrete Frame 10/5/2020 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 10/5/2020 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 10/5/2020 Partial Inspection RUBEN SALAS
Drywall Nailing 6/2/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 6/2/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/2/2021 Approved CRAIG VAUGHAN
Green Building Final 6/2/2021 Partial Approval CRAIG VAUGHAN
Reinforced Concrete Frame 6/2/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 6/2/2021 Not Ready for Inspection CRAIG VAUGHAN
Drywall Nailing 5/21/2024 Approved OSVALDO PARAMO
Final 5/21/2024 Corrections Issued OSVALDO PARAMO
Green Building Final 5/21/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/21/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/21/2024 Approved OSVALDO PARAMO
Final 6/7/2024 Conditional Approval OSVALDO PARAMO
Final 6/11/2024 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 6/11/2024 Approved OSVALDO PARAMO