14500 W SHERMAN CIR 91405
Certificate Information: 14500 W SHERMAN CIR 91405
- Application / Permit
- 13044-20000-07836
- Plan Check / Job No.
- M13VN01409
- Group
- Mechanical
- Type
- HVAC
- Sub-Type
- Apartment
- Primary Use
- ()
- Work Description
- INSTALLATION OF GENERAL HVAC IN A 4-STORY APT. BUILDING + 2 LEVEL GARAGES. T-24 PERFORMANCE.
- Permit Issued
- Issued on 2/18/2014
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/18/2015
Permit Application Status History
Submitted | 7/29/2013 | APPLICANT |
Assigned to Plan Check Engineer | 8/22/2013 | CALVEN HSU |
Corrections Issued | 8/28/2013 | CALVEN HSU |
Quality Review Completed | 8/29/2013 | DOMENICO BARBATO |
Mechanical Plans Picked Up | 9/24/2013 | APPLICANT |
Applicant returned to address corrections | 2/4/2014 | CALVEN HSU |
Plan Check Approved | 2/10/2014 | CALVEN HSU |
Issued | 2/18/2014 | LADBS |
Permit Finaled | 12/17/2015 | STEVEN PALCHANIS |
Permit Application Clearance Information
No Data Available. |
Contact Information
Contractor | Imt Residential; Lic. No.: 766199-B | 15303 VENTURA BLVD STE. 200 SHERMAN OAKS, CA 91403 |
Engineer | Hovaguimian, George Vahe; Lic. No.: M22114 | 11517 BURBANK BLVD NORTH HOLLYWOOD, CA 91601 |
Inspector Information
KEVIN BROWN, (818) 374-1153 | Office Hours: 7:00-8:00 AM MON-FRI |
ANTHONY DE SANTIS, (818) 374-1153 | Office Hours: 7:00-8:00 AM MON-FRI |
SALVADOR PINEDO, (818) 374-1153 | Office Hours: 7:00-8:00 AM MON-FRI |
VAHIK OROJIAN, (818) 374-1153 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Rough-A/C and Heating | 5/20/2014 | Not Ready for Inspection | RALPH VILLALOBOS |
Rough-A/C and Heating | 8/7/2014 | Partial Approval | RALPH VILLALOBOS |
Rough-A/C and Heating | 9/25/2014 | Not Ready for Inspection | RALPH VILLALOBOS |
Rough-Appliance Vents | 11/7/2014 | Partial Inspection | KEVIN BROWN |
Rough-Appliance Vents | 11/10/2014 | Partial Approval | CHRISTOPHE NORRIS |
Rough-Ventilation | 11/10/2014 | Partial Approval | CHRISTOPHE NORRIS |
Rough-Ventilation | 11/13/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 11/25/2014 | Not Ready for Inspection | STEVEN PALCHANIS |
Rough-A/C and Heating | 12/4/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 12/4/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 12/10/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 12/10/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 12/23/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 12/23/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 12/23/2014 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 1/8/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 1/8/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 1/8/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 1/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 1/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 1/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 1/16/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 1/16/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 1/22/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 1/22/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 1/27/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 1/27/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 2/12/2015 | Partial Approval | BERNARD GRANT |
Rough-Ventilation | 2/12/2015 | Partial Approval | BERNARD GRANT |
Rough-Ventilation | 2/18/2015 | Partial Approval | BERNARD GRANT |
Rough-A/C and Heating | 2/19/2015 | Partial Approval | BERNARD GRANT |
Rough-A/C and Heating | 3/2/2015 | Partial Approval | BERNARD GRANT |
Rough-Ventilation | 3/2/2015 | Partial Approval | BERNARD GRANT |
Rough-Appliance Vents | 3/6/2015 | Partial Approval | BERNARD GRANT |
Rough-Ventilation | 3/6/2015 | Partial Approval | BERNARD GRANT |
Rough-Appliance Vents | 3/24/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 3/24/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 4/3/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 4/17/2015 | Order to Comply Issued | ROY TIKKA |
Rough-Appliance Vents | 4/17/2015 | Not Ready for Inspection | ROY TIKKA |
Rough-Grease Duct | 4/17/2015 | Order to Comply Issued | ROY TIKKA |
Rough-Ventilation | 4/17/2015 | Not Ready for Inspection | ROY TIKKA |
Rough-A/C and Heating | 4/20/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 4/20/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Grease Duct | 4/20/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 4/20/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 4/24/2015 | Partial Inspection | STEVEN PALCHANIS |
Rough-Appliance Vents | 4/24/2015 | Partial Inspection | STEVEN PALCHANIS |
Rough-Grease Duct | 4/24/2015 | Partial Inspection | STEVEN PALCHANIS |
Rough-Ventilation | 4/24/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 5/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 5/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Grease Duct | 5/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 5/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 5/22/2015 | Partial Approval | BERNARD GRANT |
Rough-A/C and Heating | 6/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Appliance Vents | 6/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Grease Duct | 6/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-Ventilation | 6/12/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 6/24/2015 | Approved | STEVEN PALCHANIS |
Rough-Appliance Vents | 6/24/2015 | Approved | STEVEN PALCHANIS |
Rough-Grease Duct | 6/24/2015 | Approved | STEVEN PALCHANIS |
Rough-Ventilation | 6/24/2015 | Approved | STEVEN PALCHANIS |
Rough-A/C and Heating | 7/28/2015 | Not Ready for Inspection | LOUIE WARNASURIYA |
Final | 8/18/2015 | Partial Approval | LOUIE WARNASURIYA |
HEATING-Final | 8/18/2015 | Partial Approval | LOUIE WARNASURIYA |
VENTILATION-Final | 8/18/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 8/20/2015 | Partial Approval | LOUIE WARNASURIYA |
HEATING-Final | 8/20/2015 | Partial Approval | LOUIE WARNASURIYA |
VENTILATION-Final | 8/20/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 8/26/2015 | Partial Approval | LOUIE WARNASURIYA |
HEATING-Final | 8/26/2015 | Partial Approval | LOUIE WARNASURIYA |
VENTILATION-Final | 8/26/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 8/28/2015 | Partial Approval | LOUIE WARNASURIYA |
HEATING-Final | 8/28/2015 | Partial Approval | LOUIE WARNASURIYA |
VENTILATION-Final | 8/28/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 8/31/2015 | Partial Approval | LOUIE WARNASURIYA |
HEATING-Final | 8/31/2015 | Partial Approval | LOUIE WARNASURIYA |
VENTILATION-Final | 8/31/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 9/2/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 9/8/2015 | Partial Approval | STEVEN PALCHANIS |
HEATING-Final | 9/8/2015 | Partial Approval | STEVEN PALCHANIS |
VENTILATION-Final | 9/8/2015 | Partial Approval | STEVEN PALCHANIS |
Rough-A/C and Heating | 9/16/2015 | Partial Approval | LOUIE WARNASURIYA |
Rough-Ventilation | 9/16/2015 | Partial Approval | LOUIE WARNASURIYA |
Rough-A/C and Heating | 10/14/2015 | Partial Approval | LOUIE WARNASURIYA |
Rough-Ventilation | 10/14/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 10/15/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 10/16/2015 | Partial Approval | LOUIE WARNASURIYA |
HEATING-Final | 10/16/2015 | Partial Approval | LOUIE WARNASURIYA |
VENTILATION-Final | 10/16/2015 | Partial Approval | LOUIE WARNASURIYA |
Final | 10/19/2015 | Partial Approval | STEVEN PALCHANIS |
Final | 10/21/2015 | Partial Approval | STEVEN PALCHANIS |
Final | 12/10/2015 | Not Ready for Inspection | STEVEN PALCHANIS |
Final | 12/11/2015 | Not Ready for Inspection | STEVEN PALCHANIS |
HEATING-Final | 12/11/2015 | Not Ready for Inspection | STEVEN PALCHANIS |
VENTILATION-Final | 12/11/2015 | Partial Approval | STEVEN PALCHANIS |
Final | 12/17/2015 | Permit Finaled | STEVEN PALCHANIS |