4418 S SLAUSON AVE 90230
Certificate Information: 4418 S SLAUSON AVE 90230
- Application / Permit
- 13030-10000-07347
- Plan Check / Job No.
- B13LA16113
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR SUBTERRANEAN GARAGE OF APARTMENT BUILDING.
- Permit Issued
- Issued on 6/26/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/22/2024
Permit Application Status History
| Submitted | 12/23/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2014 | MOHAMMAD FIROUZBAKHT |
| Corrections Issued | 2/6/2014 | MOHAMMAD FIROUZBAKHT |
| Disabled Access Plans Picked Up | 2/7/2014 | APPLICANT |
| Green Plans Picked Up | 2/13/2014 | APPLICANT |
| Quality Review Completed | 2/14/2014 | GARO TELMI |
| Building Plans Picked Up | 2/18/2014 | APPLICANT |
| Applicant returned to address corrections | 4/11/2019 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 3/4/2020 | TEODORO DIAZ RODRIGUEZ |
| Issued | 6/26/2020 | APPLICANT |
| Permit Finaled | 8/21/2024 | VASIL MIHALEV |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | A T Construction & Consultant; Lic. No.: 671011-B | 73 PORTUGUESE BEND ROAD ROLLING HILLS, CA 90274 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/25/2022 | Approved | AL GAMBLE |
| Excavation | 4/20/2022 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation | 4/28/2022 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 4/28/2022 | Partial Inspection | JONATHAN HOM |
| Excavation | 5/5/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 5/5/2022 | Partial Approval | AL GAMBLE |
| Bottom/Toe | 5/9/2022 | Partial Inspection | JONATHAN HOM |
| Fill/Backfill | 5/25/2022 | Partial Inspection | AL GAMBLE |
| Sub-Drain | 5/25/2022 | Approved | AL GAMBLE |
| Irrigation/Landscape | 6/12/2023 | Partial Inspection | MATTHEW JENKINS |
| Irrigation/Landscape | 6/15/2023 | Partial Inspection | AL GAMBLE |
| Irrigation/Landscape | 7/6/2023 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 7/14/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 7/14/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 7/14/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 7/18/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 7/18/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 7/18/2023 | Partial Inspection | MATTHEW JENKINS |
| Special/Order Compliance | 1/24/2024 | Corrections Issued | VASIL MIHALEV |
| Bottom/Toe | 7/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Final | 7/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Rough | 7/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 8/21/2024 | Approved | VASIL MIHALEV |
| Final | 8/21/2024 | Permit Finaled | VASIL MIHALEV |
| Rough | 8/21/2024 | Approved | VASIL MIHALEV |