1221 S HOPE ST 90015
Certificate Information: 1221 S HOPE ST 90015
- Application / Permit
- 13016-20000-20225
- Plan Check / Job No.
- B13VN11467
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- Remodel existing building. Provide steel moment frames and braced frames to support the lateral and gravity loading, in lieu of existing URM walls. Remove the existing roof and raise the ceiling to 29'-0" high.
- Permit Issued
- Issued on 4/9/2014
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/8/2016
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 9/30/2013 | APPLICANT |
Assigned to Plan Check Engineer | 10/17/2013 | ABDUL CHEGENI |
Corrections Issued | 10/29/2013 | ABDUL CHEGENI |
Quality Review Completed | 11/1/2013 | TAMERA SVETICH |
Building Plans Picked Up | 11/4/2013 | APPLICANT |
Disabled Access Plans Picked Up | 11/4/2013 | APPLICANT |
Applicant returned to address corrections | 11/25/2013 | ABDUL CHEGENI |
Applicant returned to address corrections | 1/7/2014 | ABDUL CHEGENI |
Plan Check Approved | 1/9/2014 | ABDUL CHEGENI |
Issued | 4/9/2014 | LADBS |
CofO in Progress | 2/3/2016 | NICK DANERI |
CofO Issued | 2/8/2016 | RICKEY JACKSON |
Permit Finaled | 2/8/2016 | RICKEY JACKSON |
Permit Application Clearance Information
"Q" conditions | Cleared | 11/4/2013 | HERMINIGILDO AGUSTIN |
CPC | Cleared | 11/4/2013 | HERMINIGILDO AGUSTIN |
Miscellaneous | Cleared | 11/4/2013 | HERMINIGILDO AGUSTIN |
ZA Case | Cleared | 11/4/2013 | HERMINIGILDO AGUSTIN |
Address approval | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
Eng Process Fee Ord 176,300 | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
Green Code | Cleared | 12/11/2013 | ABDUL CHEGENI |
Roof/Waste drainage to street | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
Sewer availability | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
Public Works-Highway Ded. | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
Public Works-Open Permits | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
Public Works-Sewers | Cleared | 12/11/2013 | MIKE KOUYOUMDJIAN |
DAS Clearance | Cleared | 12/18/2013 | NORLITO MEDRANO |
Project located in CRA area | Cleared | 12/19/2013 | JIM URQUHART |
Contact Information
Contractor | Fico Construction; Lic. No.: 757096-B | 1250 SO LOS ANGELES STREET 205 LOS ANGELES, CA 90015 |
Engineer | Au, Chi-Ming; Lic. No.: C44491 | 8857 ARDENDALE AVE SAN GABRIEL, CA 91775 |
Inspector Information
KATY RAMIREZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
PAUL BAZERKANIAN, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 7/17/2014 | Partial Approval | WILLIAM THOMPSON |
Deputy Drilled-In Anchors | 8/6/2014 | Conditional Approval | DANIEL MC AULIFFE |
Footing/Foundation/Slab | 8/14/2014 | Partial Approval | JAMES POWERS |
Deputy Steel/Welding | 9/8/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/9/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/10/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/11/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/12/2014 | Approved | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/15/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/16/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/17/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/18/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/19/2014 | Conditional Approval | MICHAEL ALVAREZ |
Deputy Drilled-In Anchors | 9/24/2014 | Conditional Approval | DANIEL MC AULIFFE |
Deputy Steel/Welding | 9/24/2014 | Conditional Approval | DANIEL MC AULIFFE |
Footing/Foundation/Slab | 10/15/2014 | Partial Approval | DANIEL MC AULIFFE |
Deputy Reinf. Concrete | 10/16/2014 | Conditional Approval | DANIEL MC AULIFFE |
Floor/Roof Diaphrgm/Shear Wall | 2/17/2015 | Conditional Approval | NICK DANERI |
Interior/Exterior Lathing | 7/8/2015 | Approved | JEFFREY FULTON |
Drywall Nailing | 12/15/2015 | Not Ready for Inspection | NICK DANERI |
Final | 12/15/2015 | Not Ready for Inspection | NICK DANERI |
Green Building Final | 12/15/2015 | Approved | DONALD CRICHLOW |
Green Building Rough | 12/15/2015 | Approved | DONALD CRICHLOW |
Reinforced Masonry Frame | 12/15/2015 | Partial Inspection | NICK DANERI |
SGSOV-Seismic Gas S/O Valve | 12/15/2015 | SGSOV No Gas | NICK DANERI |
Drywall Nailing | 2/2/2016 | Approved | NICK DANERI |
Final | 2/2/2016 | Conditional Approval | NICK DANERI |
Reinforced Masonry Frame | 2/2/2016 | Approved | NICK DANERI |