314 W 6TH ST 90014
Certificate Information: 314 W 6TH ST 90014
- Application / Permit
- 13016-10000-26553
- Plan Check / Job No.
- B13LA16544
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (27) Joint Living and Working Quarters
- Work Description
- CONVERT OFFICE/RETAIL/MANUF'G BUILDING, FROM SECOND TO SIXTH FLOOR, INTO 50 JOINT LIVE AND WORK QUARTERS FOR ARTISTS AND ARTISANS (TIER 1). FIRST FLOOR TO REMAIN RETAIL (shell only) AND BASEMENT TO REMAIN AS STORAGE.
- Permit Issued
- Issued on 12/1/2015
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2014 | JOE VO |
| Disabled Access Plans Picked Up | 2/24/2014 | APPLICANT |
| Plans on Hold | 2/25/2014 | JOE VO |
| Green Plans Picked Up | 3/28/2014 | APPLICANT |
| Hold Released | 5/15/2014 | JOHN VASQUEZ |
| Corrections Issued | 6/12/2014 | RICARDO TRES |
| Quality Review Completed | 6/23/2014 | CHARLES CHANG |
| Applicant returned to address corrections | 8/27/2014 | RICARDO TRES |
| Applicant returned to address corrections | 9/11/2014 | RICARDO TRES |
| Applicant returned to address corrections | 9/17/2014 | RICARDO TRES |
| Plan Check Approved | 11/16/2015 | RICARDO TRES |
| Issued | 12/1/2015 | LADBS |
| CofO in Progress | 6/13/2022 | KATY RAMIREZ |
| CofO Issued | 6/14/2022 | ERNESTO CORRAL |
| Permit Finaled | 6/14/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/10/2015 | EMMANUELA GUTIERREZ |
| "Q" conditions | Cleared | 2/10/2015 | EMMANUELA GUTIERREZ |
| Hydrant and Access approval | Cleared | 2/10/2015 | JOHN DALLAS |
| Supp. Use District POD/CDO/TDO | Cleared | 2/10/2015 | EMMANUELA GUTIERREZ |
| City Hist. Cultural Monument | Cleared | 2/11/2015 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 2/11/2015 | LAMBERT GIESSINGER |
| DAS Clearance | Cleared | 2/18/2015 | EDDIE GARIN |
| Green Code | Cleared | 2/23/2015 | MARTHA DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2015 | JOHN LIN |
| Address approval | Cleared | 2/26/2015 | AVALYN KAMACHI |
| Sewer availability | Cleared | 2/26/2015 | AVALYN KAMACHI |
| Historical monument | Cleared | 3/3/2015 | JIM URQUHART |
| Historical monument | Cleared | 3/3/2015 | JIM URQUHART |
| Project located in CRA area | Cleared | 3/3/2015 | JIM URQUHART |
| Fire Marshall Fire Life Safety | Cleared | 4/22/2015 | DAVE MYERS |
Contact Information
| Architect | Youssefian, Sam H; Lic. No.: C12562 | 1431 HUNTINGTON DR #201 SOUTH PASADENA, CA 91030 |
| Contractor | Owner-Builder | , |
| Engineer | Gharibans, Edmond T; Lic. No.: S2942 | 18544 BRYMER STREET NORTHRIDGE, CA 913261951 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2016 | Partial Inspection | DANIEL COLLINS |
| Footing/Foundation/Slab | 9/20/2016 | Partial Inspection | KATY RAMIREZ |
| Deputy Reinf. Concrete | 9/22/2016 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 10/13/2016 | Conditional Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 12/20/2016 | Partial Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 1/13/2017 | Partial Approval | JOSE GAXIOLA |
| Light Gage Steel Frame | 1/17/2017 | Partial Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 2/7/2017 | Partial Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 3/21/2017 | Conditional Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 5/25/2017 | Partial Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 11/16/2017 | Partial Approval | NICK DANERI |
| Footing/Foundation/Slab | 11/21/2017 | Partial Approval | JOSE GAXIOLA |
| Deputy Steel/Welding | 12/27/2017 | Conditional Approval | JOSE GAXIOLA |
| Deputy Steel/Welding | 1/4/2018 | Conditional Approval | JOSE GAXIOLA |
| Structural Steel Frame | 1/8/2018 | Partial Approval | JOSE GAXIOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2018 | Partial Approval | JOSE GAXIOLA |
| Deputy Drilled-In Anchors | 4/9/2018 | Conditional Approval | JOSE GAXIOLA |
| Deputy Steel/Welding | 4/16/2018 | Conditional Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 4/19/2018 | Partial Approval | JOSE GAXIOLA |
| Light Gage Steel Frame | 4/19/2018 | Not Ready for Inspection | JOSE GAXIOLA |
| Structural Steel Frame | 4/19/2018 | Partial Approval | JOSE GAXIOLA |
| Light Gage Steel Frame | 7/3/2018 | Partial Approval | JOSE GAXIOLA |
| Deputy Steel/Welding | 8/22/2018 | Conditional Approval | JOSE GAXIOLA |
| Interior/Exterior Lathing | 8/28/2018 | Partial Approval | JOSE GAXIOLA |
| Footing/Foundation/Slab | 9/14/2018 | Partial Approval | JOSE GAXIOLA |
| Structural Steel Frame | 9/14/2018 | Partial Approval | JOSE GAXIOLA |
| Light Gage Steel Frame | 11/14/2018 | Not Ready for Inspection | JOEY BUCHANAN |
| Light Gage Steel Frame | 11/20/2018 | Partial Approval | WINSTON DUNNING |
| Interior/Exterior Lathing | 11/21/2018 | Partial Approval | WINSTON DUNNING |
| Interior/Exterior Lathing | 12/3/2018 | Partial Approval | WINSTON DUNNING |
| Structural Steel Frame | 12/3/2018 | Partial Approval | WINSTON DUNNING |
| Footing/Foundation/Slab | 3/26/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 5/6/2019 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 5/6/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 5/20/2019 | Partial Approval | DANIEL COLLINS |
| Insulation | 5/20/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 5/28/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 5/28/2019 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 5/28/2019 | Partial Approval | DANIEL COLLINS |
| Insulation | 6/3/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 6/5/2019 | Partial Approval | DANIEL COLLINS |
| Green Building Rough | 7/9/2019 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 7/9/2019 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 7/9/2019 | Partial Approval | DANIEL COLLINS |
| Insulation | 7/16/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 8/12/2019 | Partial Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 8/22/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 9/11/2019 | Partial Approval | DANIEL COLLINS |
| Interior/Exterior Lathing | 10/7/2019 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 11/6/2019 | Partial Approval | DANIEL COLLINS |
| Insulation | 11/12/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 11/20/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 11/25/2019 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 10/5/2020 | Partial Inspection | DANIEL COLLINS |
| Deputy Fireproofing | 10/26/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/26/2020 | Partial Approval | DANIEL COLLINS |
| Insulation | 10/30/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/30/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 11/12/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 11/12/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/3/2020 | Partial Approval | DANIEL COLLINS |
| Insulation | 12/8/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/8/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/18/2020 | Partial Approval | DANIEL COLLINS |
| Insulation | 12/28/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/28/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 2/2/2021 | Partial Inspection | DANIEL COLLINS |
| Drywall Nailing | 2/10/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 2/16/2021 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 3/11/2021 | Partial Approval | DANIEL COLLINS |
| Pre-Inspection | 11/16/2021 | Partial Approval | DANIEL COLLINS |
| Final | 11/23/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| Green Building Final | 11/23/2021 | Conditional Approval | BRUCE CAMPBELL |
| Reinforced Concrete Frame | 11/23/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 11/23/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| Pre-Inspection | 12/16/2021 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 5/20/2022 | Approved | KATY RAMIREZ |
| Final | 6/3/2022 | Partial Inspection | KATY RAMIREZ |
| Reinforced Concrete Frame | 6/3/2022 | Partial Approval | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 6/3/2022 | Approved | KATY RAMIREZ |
| Final | 6/13/2022 | OK to Issue CofO | KATY RAMIREZ |
| Reinforced Concrete Frame | 6/13/2022 | Approved | KATY RAMIREZ |